Prevailing wage rates: Monongalia County, West Virginia

Building construction · WV20260042 modification 1, published May 18, 2026

The short answer

This sheet sets 36 classifications for building work in Monongalia County, West Virginia. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $28.87 an hour (operator: backhoe) to $76.06 (boilermaker). Your contract may lock an earlier modification.

Rates by classification

Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
ASBE0002-002 · Asbestos Workers and Heat & Frost Insulators agreement, August 1, 2024
ASBESTOS WORKER/HEAT & FROST INSULATOR$46.50$29.43$75.93Agreement
BOIL0667-005 · Boilermakers agreement, January 1, 2025
BOILERMAKER$47.13$28.93$76.06Agreement
BRWV0009-007 · Bricklayers agreement, December 1, 2022
TILE SETTER$31.65$25.56$57.21Agreement
BRWV0015-004 · Bricklayers agreement, June 1, 2024
BRICKLAYER (BRICKLAYER & BRICK POINTER/CAULKER/CLEANER)$31.65$25.82$57.47Agreement
BRWV0015-009 · Bricklayers agreement, June 1, 2021
BRICKLAYER (BRICK REFRACTORY/BRICK PLACEMENT WORKER)$32.64$23.95$56.59Agreement
BRWV0015-010 · Bricklayers agreement, June 1, 2024
MASON - STONE$33.00$26.18$59.18Agreement
BRWV0015-014 · Bricklayers agreement, June 1, 2024
TILE FINISHER$27.00$22.57$49.57Agreement
CARP0436-008 · Carpenters agreement, December 1, 2024
CARPENTER (INCLUDING BATT INSULATION, DRYWALL HANGING, FORM WORK AND SCAFFOLD BUILDER)$30.51$26.05$56.56Agreement
CARP0443-009 · Carpenters agreement, June 1, 2023
MILLWRIGHT$37.40$26.06$63.46Agreement
ELEC0596-006 · Electrical Workers (IBEW) agreement, June 1, 2025
ELECTRICIAN$43.77$27.72$71.49Agreement
ENGI0132-012 · Operating Engineers agreement, December 1, 2024
POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID STEER/SKID LOADER, FARM TYPE TRACTOR, LOADER$34.71$22.05$56.76Agreement
POWER EQUIPMENT OPERATOR: GROUP 3…
Full text

POWER EQUIPMENT OPERATOR: GROUP 3 BULLDOZER, EXCAVATOR, FORKLIFT, NON-FARM TYPE TRACTOR, ALL OTHER CRANES, ALL OTHER MECHANICS

$45.21$22.05$67.26Agreement
POWER EQUIPMENT OPERATOR: GROUP 2…
Full text

POWER EQUIPMENT OPERATOR: GROUP 2 OPERATING CRANES AND TOWER CRANES WITH A LIFTING CAPACITY OF 15 TONS AND OVER

$46.21$22.05$68.26Agreement
POWER EQUIPMENT OPERATOR: GROUP 1…
Full text

POWER EQUIPMENT OPERATOR: GROUP 1 ALL FRICTION CRANES, TOWER CRANES AND ALL CRANES WITH 180 FT. OR MORE OF BOOM INCLUDING MAST AND JIBS OR LIFTING CAPACITY OF 100 TONS OR MORE AND HOISTS WITH 30,000 POUND LINE PULL OR MORE, MECHANICS WITH TOOLS WITH 3/4 INCH DRIVE AND BELOW

$46.56$22.05$68.61Agreement
IRON0549-009 · Ironworkers agreement, December 1, 2022
IRONWORKER: ORNAMENTAL, REINFORCING, SHEETING AND STRUCTURAL$35.19$25.66$60.85Agreement
LABO0379-012 · Laborers agreement, December 1, 2024
LABORER: GROUP 4 FLAGGER$24.94$16.20$41.14Agreement
LABORER: GROUP 3 PIPELAYER$24.94$16.20$41.14Agreement
LABORER: GROUP 2…
Full text

LABORER: GROUP 2 ASPHALT RAKER, BOBCAT OPERATOR (CLEAN UP/DEMOLITION), CHAIN SAW, CONCRETE SAW (HAND HELD/WALK BEHIND), CONCRETE WORKER, DEWATERING, FENCE ERECTION, GRADE CHECKER, GROUTING, JACK HAMMER, MASON TENDER-BRICK, MASON TENDER-CEMENT CONCRETE, MORTAR MIXER, MOTORIZED BUGGY OPERATOR, RODMAN, SCAFFOLD BUILDER (BRICK AND MASONRY), SKYTRAK FORKLIFT OPERATOR, TAMPER (HAND HELD)

$24.94$16.20$41.14Agreement
LABORER: GROUP 1 CARPENTER TENDER, COMMON OR GENERAL, DEMOLITION, LANDSCAPE$24.94$16.20$41.14Agreement
LABO1149-007 · Laborers agreement, December 1, 2024
LABORER: WATER BOY$25.92$16.88$42.80Agreement
LABORER (PLASTER TENDER)$25.92$16.88$42.80Agreement
PAIN0804-006 · Painters and Allied Trades agreement, December 1, 2024
PAINTER (BRUSH, ROLLER AND SPRAY)$30.49$19.16$49.65Agreement
PAIN0970-007 · Painters and Allied Trades agreement, December 1, 2024
PAINTER: DRYWALL FINISHING/TAPING$30.57$20.06$50.63Agreement
PAIN1195-002 · Painters and Allied Trades agreement, December 1, 2024
GLAZIER$32.89$13.38$46.27Agreement
PLAS0926-005 · Plasterers and Cement Masons agreement, July 1, 2025
PLASTERER (EIFS AND FIREPROOFING)$30.50$22.22$52.72Agreement
CEMENT MASON/CONCRETE FINISHER$30.38$22.87$53.25Agreement
PLUM0152-009 · Plumbers and Pipefitters agreement, November 1, 2024
PLUMBER$34.05$41.05$75.10Agreement
PLUM0152-010 · Plumbers and Pipefitters agreement, November 1, 2024
PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION)$34.05$41.05$75.10Agreement
ROOF0188-003 · Roofers agreement, July 1, 2025
ROOFER$34.00$19.11$53.11Agreement
SHEE0033-003 · Sheet Metal Workers agreement, June 1, 2024
SHEET METAL WORKER (INCLUDES HVAC DUCT INSTALLATION)$34.92$29.70$64.62Agreement
SUWV2012-040 · Survey of contractors in WV, August 13, 2012
OPERATOR: ROLLER$25.24$16.15$41.39Survey
OPERATOR: BACKHOE$21.51$7.36$28.87Survey
LABORER: WACKER ROLLER OPERATOR$23.07$11.07$34.14Survey
TEAM0175-005 · Teamsters agreement, October 1, 2024
TRUCK DRIVER: GROUP 3…
Full text

TRUCK DRIVER: GROUP 3 DUMP TRUCK (5 CU. YDS. & OVER), TRACTOR HAUL TRUCK, WATER TANK TRUCK (SEMI)

$29.96$22.50$52.46Agreement
TRUCK DRIVER: GROUP 2 DUMP TRUCK (UP TO 5 CU. YDS.), WATER TANK TRUCK (STRAIGHT)$29.81$22.50$52.31Agreement
UAVGWV0027 · Union average, January 1, 2019
LABORER: POWER TOOL OPERATOR$22.81$16.50$39.31Union average

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on WV20260042?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator