Prevailing wage rates · Washington · Wage determination
Prevailing wage rates: Grays Harbor County, Washington
Building construction · WA20260027 modification 1, published May 18, 2026
The short answer
This sheet sets 33 classifications for building work in Grays Harbor County, Washington. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $21.98 an hour (painter: spray) to $103.25 (sheet metal worker (hvac duct work only)). Your contract may lock an earlier modification.
What changed this year
First published January 2, 2026, this sheet is now on modification 1, but none of its modifications has changed a rate.
Latest change
May 18, 2026 · modification 1
Classification names reworded; no change among the 33 lines we could match
SAM.gov reworded this sheet’s classification names in this modification, so not every line can be matched to the one before. Only lines matched with certainty are compared here; nothing is guessed. If your trade is not listed, compare it against your contract’s copy.
Compared line by line from each modification as published on SAM.gov. A line we could not pair with certainty is left out rather than guessed.
Rates by classification
These are the rates in modification 1 as published on SAM.gov. The determination and modification written into your contract are the ones that bind you; check that number before relying on this table. Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from and its year; a survey year long past means the rate has not been surveyed since. A marker means the group changed in this modification. In the Since column, a dash means SAM.gov reworded the line during the year and it cannot be matched to the first publication with certainty. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| ASBE0007-005 · Asbestos Workers and Heat & Frost Insulators agreement, June 1, 2025 | ||||
| ASBESTOS WORKER/HEAT & FROST INSULATOR (PIPE INSULATION) | $75.37 | $18.82 | $94.19 | Agreement, 2025 |
| BRWA0001-015 · Bricklayers agreement, June 1, 2025 | ||||
| BRICKLAYER | $55.34 | $20.05 | $75.39 | Agreement, 2025 |
| BRWA0001-016 · Bricklayers agreement, June 1, 2025 | ||||
| TILE SETTER | $49.70 | $18.62 | $68.32 | Agreement, 2025 |
| TILE FINISHER | $40.98 | $18.17 | $59.15 | Agreement, 2025 |
| CARP0096-001 · Carpenters agreement, June 1, 2025 | ||||
| MILLWRIGHT | $55.39 | $22.38 | $77.77 | Agreement, 2025 |
| CARP0360-004 · Carpenters agreement, June 1, 2025 | ||||
| CARPENTER (INCLUDES ACOUSTICAL CEILING MECHANIC, DRYWALL HANGER & FORM WORK) | $63.98 | $19.13 | $83.11 | Agreement, 2025 |
| ELEC0076-005 · Electrical Workers (IBEW) agreement, August 31, 2025 | ||||
| ELECTRICIAN | $65.14 | $26.56 | $91.70 | Agreement, 2025 |
| ENGI0302-024 · Operating Engineers agreement, June 1, 2025 | ||||
POWER EQUIPMENT OPERATORS: GROUP 1AAA…Full textPOWER EQUIPMENT OPERATORS: GROUP 1AAA Cranes-over 300 tons, or 300 ft of boom (including jib with attachments) | $63.35 | $27.57 | $90.92 | Agreement, 2025 |
POWER EQUIPMENT OPERATOR: GROUP 4…Full textPOWER EQUIPMENT OPERATOR: GROUP 4 ROLLER-OTHER THAN PLANT MIX; FORKLIFT: UNDER 3000 LBS WITH ATTACHMENTS | $55.43 | $27.57 | $83.00 | Agreement, 2025 |
POWER EQUIPMENT OPERATOR: GROUP 3…Full textPOWER EQUIPMENT OPERATOR: GROUP 3 DOZERS-D-9 AND UNDER; ROLLER-PLANT MIX; EXCAVATOR/TRACKHOE, BACKHOE: UNDER 15 METRIC TONS; FORKLIFT: 3000 LBS AND OVER WITH ATTACHMENTS | $59.23 | $27.57 | $86.80 | Agreement, 2025 |
POWER EQUIPMENT OPERATOR: GROUP 2…Full textPOWER EQUIPMENT OPERATOR: GROUP 2 EXCAVATOR/TRACKHOE, BACKHOE: 15 TO 30 METRIC TONS; LOADERS-OVERHEAD UNDER 6 YARDS; MECHANIC | $59.88 | $27.57 | $87.45 | Agreement, 2025 |
POWER EQUIPMENT OPERATOR: GROUP 1…Full textPOWER EQUIPMENT OPERATOR: GROUP 1 EXCAVATOR/TRACKHOE, BACKHOES: OVER 30 METRIC TONS TO 50 METRIC TONS; LOADER- OVERHEAD 6 YARDS TO, BUT NOT INCLUDING 8 YARDS; DOZER D-10 | $60.67 | $27.57 | $88.24 | Agreement, 2025 |
| POWER EQUIPMENT OPERATOR: GROUP 1AA EXCAVATOR/TRACKHOE, BACKHOES: OVER 90 METRIC TONS | $62.47 | $27.57 | $90.04 | Agreement, 2025 |
POWER EQUIPMENT OPERATOR: GROUP 1A…Full textPOWER EQUIPMENT OPERATOR: GROUP 1A LOADERS-OVERHEAD, 8 YARDS AND OVER; EXCAVATOR/TRACKHOE, BACKHOES: OVER 50 METRIC TONS TO 90 METRIC TONS | $61.56 | $27.57 | $89.13 | Agreement, 2025 |
| IRON0086-003 · Ironworkers agreement, July 7, 2025 | ||||
| IRONWORKER (REINFORCING, STRUCTURAL AND ORNAMENTAL) | $57.94 | $34.52 | $92.46 | Agreement, 2025 |
| LABO0252-008 · Laborers agreement, June 1, 2025 | ||||
| LABORER: ZONE 1: GROUP 5 MASON TENDER-BRICK; MASON TENDER-CEMENT/CONCRETE; GRADE CHECKER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - PROJECTS WITHIN 25 RADIUS MILES OF THE RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL | $52.31 | $17.01 | $69.32 | Agreement, 2025 |
| LABORER: ZONE 1: GROUP 4 PIPE LAYER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - PROJECTS WITHIN 25 RADIUS MILES OF THE RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL | $51.52 | $16.99 | $68.51 | Agreement, 2025 |
| LABORER: ZONE 1: GROUP 3 GENERAL OR COMMON LABORER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - PROJECTS WITHIN 25 RADIUS MILES OF THE RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL | $50.38 | $16.96 | $67.34 | Agreement, 2025 |
| PAIN0188-001 · Painters and Allied Trades agreement, July 1, 2025 | ||||
| GLAZIER | $61.14 | $23.76 | $84.90 | Agreement, 2025 |
| PAIN0300-004 · Painters and Allied Trades agreement, July 1, 2025 | ||||
| PAINTER (BRUSH AND ROLLER, EXCLUDES SPRAY AND DRYWALL FINISHING/TAPING) | $41.24 | $14.70 | $55.94 | Agreement, 2025 |
| PAIN1238-002 · Painters and Allied Trades agreement, July 1, 2025 | ||||
| SOFT FLOOR LAYER (INCLUDING VINYL AND CARPET) | $42.01 | $20.20 | $62.21 | Agreement, 2025 |
| PLAS0528-004 · Plasterers and Cement Masons agreement, June 1, 2024 | ||||
| CEMENT MASON/CONCRETE FINISHER | $54.16 | $21.27 | $75.43 | Agreement, 2024 |
| PLUM0026-010 · Plumbers and Pipefitters agreement, June 1, 2025 | ||||
| PIPEFITTER | $60.72 | $34.15 | $94.87 | Agreement, 2025 |
| ROOF0153-001 · Roofers agreement, June 1, 2024 | ||||
| ROOFER (INCLUDES ROOF TEAR OFF, WATERPROOFING, AND INSTALLATION OF METAL ROOFS) | $47.98 | $16.47 | $64.45 | Agreement, 2024 |
| SFWA0699-006 · SFWA, January 1, 2023 | ||||
| SPRINKLER FITTER (FIRE SPRINKLERS) | $44.13 | $26.40 | $70.53 | SFWA |
| SHEE0066-003 · Sheet Metal Workers agreement, June 1, 2025 | ||||
| SHEET METAL WORKER (HVAC DUCT WORK ONLY) | $69.86 | $33.39 | $103.25 | Agreement, 2025 |
| SUWA2002-007 · Survey of contractors in WA, June 18, 2009 | ||||
| TRUCK DRIVER: DUMP TRUCK | $23.50 | $6.87 | $30.37 | Survey, 2009 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $24.83 | $0.00 | $24.83 | Survey, 2009 |
| PLUMBER | $35.00 | $0.00 | $35.00 | Survey, 2009 |
| PAINTER: SPRAY | $17.80 | $4.18 | $21.98 | Survey, 2009 |
| PAINTER: DRYWALL FINISHING/TAPING | $29.90 | $0.00 | $29.90 | Survey, 2009 |
| OPERATOR: CRANE | $30.40 | $0.00 | $30.40 | Survey, 2009 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $27.94 | $0.00 | $27.94 | Survey, 2009 |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on WA20260027?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator
Put these rates on a certified payroll.
Start here and WA20260027 is already filled in when you set up the job. CertifiedHours loads this sheet, checks every line against it as you type hours, and prints the WH-347. Free for one payroll a month.
Start a payroll on this sheetOn this sheet
- 33 classifications in 18 rate groups
- 16 from agreements, 1 from surveys
- Counties: Grays Harbor