Prevailing wage rates: Adams County, Washington

Building construction · WA20260021 modification 2, published May 18, 2026

The short answer

This sheet sets 31 classifications for building work in Adams County, Washington. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $14.88 an hour (metal building erector) to $100.11 (pipefitter). Your contract may lock an earlier modification.

What changed this year

First published January 2, 2026, this sheet is now on modification 2, and its rates have changed in 1 modification. Of the 31 rates we can follow line by line from the first publication to today, 8 are higher.

If you bid the job or set pay from an earlier copy, find your trades below. The rates that bind you are the ones in the modification written into your contract.

Latest change

May 18, 2026 · modification 2

Classification names reworded; no change among the 31 lines we could match

SAM.gov reworded this sheet’s classification names in this modification, so not every line can be matched to the one before. Only lines matched with certainty are compared here; nothing is guessed. If your trade is not listed, compare it against your contract’s copy.

Earlier modifications

  • January 23, 2026 · modification 18 rates raised
    • Power equipment operator: 8 rates raised by $3.21 to $3.43 an hour
    Every line that changed (8)
    ClassificationWasNowChange
    POWER EQUIPMENT OPERATOR GROUP 1$38.91 + $22.45$41.17 + $23.40+$3.21 (+5.2%)
    POWER EQUIPMENT OPERATOR GROUP 2$39.28 + $22.45$41.56 + $23.40+$3.23 (+5.2%)
    POWER EQUIPMENT OPERATOR GROUP 3$39.99 + $22.45$42.31 + $23.40+$3.27 (+5.2%)
    POWER EQUIPMENT OPERATOR GROUP 4$40.18 + $22.45$42.51 + $23.40+$3.28 (+5.2%)
    POWER EQUIPMENT OPERATOR GROUP 5$40.37 + $22.45$42.71 + $23.40+$3.29 (+5.2%)
    POWER EQUIPMENT OPERATOR GROUP 6$40.69 + $22.45$43.05 + $23.40+$3.31 (+5.2%)
    POWER EQUIPMENT OPERATOR GROUP 7$41.01 + $22.45$43.39 + $23.40+$3.33 (+5.2%)
    POWER EQUIPMENT OPERATOR GROUP 8$42.88 + $22.45$45.36 + $23.40+$3.43 (+5.3%)

Compared line by line from each modification as published on SAM.gov. A line we could not pair with certainty is left out rather than guessed.

Rates by classification

These are the rates in modification 2 as published on SAM.gov. The determination and modification written into your contract are the ones that bind you; check that number before relying on this table. Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from and its year; a survey year long past means the rate has not been surveyed since. A marker means the group changed in this modification. In the Since column, a dash means SAM.gov reworded the line during the year and it cannot be matched to the first publication with certainty. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSince Jan 2Source
BRWA0003-002 · Bricklayers agreement, June 1, 2021
BRICKLAYER$33.95$19.33$53.28no changeAgreement, 2021
BRWA0003-009 · Bricklayers agreement, June 1, 2021
TILE SETTER$29.86$13.95$43.81no changeAgreement, 2021
CARP0059-022 · Carpenters agreement, June 1, 2025
CARPENTER (INCLUDING DRYWALL HANGING AND FORM WORK)$44.21$17.28$61.49no changeAgreement, 2025
ELEC0073-004 · Electrical Workers (IBEW) agreement, July 1, 2025
ELECTRICIAN$49.55$19.09$68.64no changeAgreement, 2025
ENGI0302-132 · Operating Engineers agreement, June 1, 2025
POWER EQUIPMENT OPERATOR: GROUP 8…
Full text

POWER EQUIPMENT OPERATOR: GROUP 8 CRANES (85 TONS AND OVER, AND ALL CLIMBING, OVERHEAD,RAIL AND TOWER); LOADERS (OVERHEAD AND FRONT-END, 10 YARDS AND OVER)

$45.36$23.40$68.76+$3.43 (+5.3%)Agreement, 2025
POWER EQUIPMENT OPERATOR: GROUP 7…
Full text

POWER EQUIPMENT OPERATOR: GROUP 7 BACKHOE (OVER 110,000); TRACKHOE/EXCAVATOR (3 YDS & OVER); CRANES (OVER 45 TONS TO BUT NOT INCLUDING 85 TONS); LOADERS (OVERHEAD & FRONT-END, OVER 8 YDS. TO 10 YDS.)

$43.39$23.40$66.79+$3.33 (+5.2%)Agreement, 2025
POWER EQUIPMENT OPERATOR: GROUP 6…
Full text

POWER EQUIPMENT OPERATOR: GROUP 6 ASPHALT ROLLER; BACKHOE (45,000 GW AND OVER TO 110,000 GW); TRACKHOE/EXCAVATOR (3/4 YD. TO 3 YD.); CRANES (OVER 25 TONS, TO AND INCLUDING 45 TONS), BULLDOZER, 834 R/T & SIMILAR; LOADER OPERATOR (FRONT-END & OVERHEAD, 4 YDS. INCL. 8 YDS.); MECHANIC

$43.05$23.40$66.45+$3.31 (+5.2%)Agreement, 2025
POWER EQUIPMENT OPERATOR: GROUP 5…
Full text

POWER EQUIPMENT OPERATOR: GROUP 5 BACKHOE (UNDER 45,000 GW); TRACKHOE/EXCAVATOR (UNDER 3/4 YD.); CRANES (25 TONS & UNDER)

$42.71$23.40$66.11+$3.29 (+5.2%)Agreement, 2025
POWER EQUIPMENT OPERATOR: GROUP 4 LOADERS (OVERHEAD & FRONT-END, UNDER 4 YDS. R/T)$42.51$23.40$65.91+$3.28 (+5.2%)Agreement, 2025
POWER EQUIPMENT OPERATOR: GROUP 3 BULLDOZER (UP TO D-6 OR EQUIVALENT)$42.31$23.40$65.71+$3.27 (+5.2%)Agreement, 2025
POWER EQUIPMENT OPERATOR: GROUP 2 FORK LIFT$41.56$23.40$64.96+$3.23 (+5.2%)Agreement, 2025
POWER EQUIPMENT OPERATOR: GROUP 1…
Full text

POWER EQUIPMENT OPERATOR: GROUP 1 ROLLERS, ALL TYPES ON SUBGRADE, INCLUDING SEAL AND CHIP COATINGS

$41.17$23.40$64.57+$3.21 (+5.2%)Agreement, 2025
IRON0014-012 · Ironworkers agreement, July 7, 2025
IRONWORKER: ORNAMENTAL, REINFORCING AND STRUCTURAL$43.40$32.77$76.17no changeAgreement, 2025
LABO0238-007 · Laborers agreement, June 1, 2025
LABORER, MASON TENDER BRICK$38.05$16.75$54.80no changeAgreement, 2025
LABO0238-025 · Laborers agreement, June 1, 2025
LABORER: A-2: GROUP 10 GRADE CHECKER$43.21$16.90$60.11no changeAgreement, 2025
LABORER: A-2: GROUP 3 CEMENT/CONCRETE; PIPELAYER$40.46$16.90$57.36no changeAgreement, 2025
LABORER: A-2: GROUP 2 COMMON OR GENERAL LABORER$40.13$16.90$57.03no changeAgreement, 2025
PAIN0427-004 · Painters and Allied Trades agreement, July 1, 2025
PAINTER (BRUSH & SPRAY ONLY)$33.95$15.65$49.60no changeAgreement, 2025
PLAS0072-008 · Plasterers and Cement Masons agreement, June 1, 2025
CEMENT MASON/CONCRETE FINISHER…
Full text

CEMENT MASON/CONCRETE FINISHER: ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $3.00 BASE POINTS: SPOKANE, PASCO, LEWISTON, WENATCHEE ZONE 1: 0 - 45 RADIUS MILES FROM THE MAIN POST OFFICE ZONE 2: 45 RADIUS MILES FROM THE MAIN POST OFFICE

$40.89$18.64$59.53no changeAgreement, 2025
PLUM0598-018 · Plumbers and Pipefitters agreement, June 1, 2025
PIPEFITTER$65.20$34.91$100.11no changeAgreement, 2025
ROOF0189-001 · Roofers agreement, July 1, 2025
ROOFER (INCLUDES ROOF TEAR OFF, WATERPROOFING, AND INSTALLATION OF METAL ROOFS)$35.75$14.40$50.15no changeAgreement, 2025
SFWA0699-005 · SFWA, April 1, 2025
SPRINKLER FITTER (FIRE SPRINKLERS)$44.30$28.58$72.88no changeSFWA
SHEE0055-012 · Sheet Metal Workers agreement, June 1, 2025
SHEETMETAL WORKER (INCLUDING HVAC DUCT INSTALLATION)$45.83$27.92$73.75no changeAgreement, 2025
SUWA2002-001 · Survey of contractors in WA, June 18, 2009
TRUCK DRIVER, INCLUDES DUMP TRUCK$23.50$6.87$30.37no changeSurvey, 2009
ROOFER: SINGLE PLY ROOF$26.77$0.68$27.45no changeSurvey, 2009
PLUMBER$35.00$0.00$35.00no changeSurvey, 2009
PIPE INSULATOR/WRAPPER$24.21$4.07$28.28no changeSurvey, 2009
PAINTER: ROLLER$22.06$2.72$24.78no changeSurvey, 2009
PAINTER: DRYWALL FINISHING/TAPING$25.17$4.41$29.58no changeSurvey, 2009
OPERATOR: BOBCAT/SKID STEER/SKID LOADER$27.94$0.00$27.94no changeSurvey, 2009
METAL BUILDING ERECTOR$11.30$3.58$14.88no changeSurvey, 2009

Modification history

Modification 1January 23, 2026
Modification 2May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on WA20260021?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 2 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator

Put these rates on a certified payroll.

Start here and WA20260021 is already filled in when you set up the job. CertifiedHours loads this sheet, checks every line against it as you type hours, and prints the WH-347. Free for one payroll a month.

Start a payroll on this sheet

On this sheet

  • 31 classifications in 15 rate groups
  • 13 from agreements, 1 from surveys
  • Counties: Adams