Prevailing wage rates · Texas · Wage determination
Prevailing wage rates: Grayson County, Texas
Heavy construction · TX20260019 modification 1, published May 18, 2026
The short answer
This sheet sets 69 classifications for heavy work in Grayson County, Texas. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $7.25 an hour (truck drivers: single axle, light) to $11.95 (electrician). Your contract may lock an earlier modification.
Scope
Water and Sewer Lines
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| SUTX1992-003 · Survey of contractors in TX, April 10, 1992 | ||||
| WELDER | $9.85 | $0.00 | $9.85 | Survey |
| TRUCK DRIVERS: SINGLE AXLE, LIGHT | $7.25 | $0.00 | $7.25 | Survey |
| TRUCK DRIVERS: SINGLE AXLE, HEAVY | $7.40 | $0.00 | $7.40 | Survey |
| TRUCK DRIVERS: (WINCH) | $7.25 | $0.00 | $7.25 | Survey |
| TRUCK DRIVERS: (TRANSIT-MIX) | $7.25 | $0.00 | $7.25 | Survey |
| TRUCK DRIVERS: (TANDEM AXLE OR SEMI-TRAILER) | $7.25 | $0.00 | $7.25 | Survey |
| TRUCK DRIVERS: (LOWBOY-FLOAT) | $7.90 | $0.00 | $7.90 | Survey |
| SPREADER BOX OPERATOR | $7.30 | $0.00 | $7.30 | Survey |
| SIGN ERECTOR | $8.30 | $0.00 | $8.30 | Survey |
| SERVICER | $7.55 | $0.00 | $7.55 | Survey |
| REINFORCING STEEL SETTER (STRUCT.) | $9.60 | $0.00 | $9.60 | Survey |
| REINFORCING STEEL SETTER (PAVING) | $7.25 | $0.00 | $7.25 | Survey |
| POWER EQUIPMENT OPERATORS: (TRENCHING MACHINE, LIGHT) | $7.80 | $0.00 | $7.80 | Survey |
| POWER EQUIPMENT OPERATORS: (TRENCHING MACHINE, HEAVY) | $8.00 | $0.00 | $8.00 | Survey |
| POWER EQUIPMENT OPERATORS: (TRAVELING MIXER) | $7.25 | $0.00 | $7.25 | Survey |
| POWER EQUIPMENT OPERATORS: (TRACTOR (PNEUMATIC) OVER 80 HP) | $7.40 | $0.00 | $7.40 | Survey |
| POWER EQUIPMENT OPERATORS: (TRACTOR (PNEUMATIC) 80 HP & LESS) | $7.35 | $0.00 | $7.35 | Survey |
| POWER EQUIPMENT OPERATORS: (TRACTOR (CRAWLER) OVER 150 HP) | $8.30 | $0.00 | $8.30 | Survey |
| POWER EQUIPMENT OPERATORS: (TRACTOR (CRAWLER) 150 HP & LESS) | $8.00 | $0.00 | $8.00 | Survey |
| POWER EQUIPMENT OPERATORS: (SIDE BOOM) | $7.25 | $0.00 | $7.25 | Survey |
| POWER EQUIPMENT OPERATORS: (SELF-PROPELLED HAMMER) | $7.25 | $0.00 | $7.25 | Survey |
| POWER EQUIPMENT OPERATORS: (SCRAPER (OVER 17 CU YD)) | $8.30 | $0.00 | $8.30 | Survey |
| POWER EQUIPMENT OPERATORS: (SCRAPER (17 CU YD & LESS)) | $7.90 | $0.00 | $7.90 | Survey |
| POWER EQUIPMENT OPERATORS: (ROLLER, STEEL WHEEL OTHER-FLAT WHEEL OR TAMPING)) | $8.05 | $0.00 | $8.05 | Survey |
| POWER EQUIPMENT OPERATORS: (ROLLER, STEEL WHEEL (PLANT-MIX PAVEMENT)) | $8.10 | $0.00 | $8.10 | Survey |
| POWER EQUIPMENT OPERATORS: (ROLLER, PNEUMATIC (SELF-PROPELLED)) | $7.25 | $0.00 | $7.25 | Survey |
| POWER EQUIPMENT OPERATORS: (MOTOR GRADER OPERATOR) | $9.00 | $0.00 | $9.00 | Survey |
| POWER EQUIPMENT OPERATORS: (MOTOR GRADER OPERATOR (FINE GRADE)) | $9.75 | $0.00 | $9.75 | Survey |
| POWER EQUIPMENT OPERATORS: (MIXER (16 CF & LESS)) | $7.25 | $0.00 | $7.25 | Survey |
| POWER EQUIPMENT OPERATORS: (FRONT END LOADER (2.5 CU YD OR LESS)) | $8.30 | $0.00 | $8.30 | Survey |
| POWER EQUIPMENT OPERATORS: (FRONT END LOAD (OVER 2.5 CU YD)) | $9.05 | $0.00 | $9.05 | Survey |
| POWER EQUIPMENT OPERATORS: (FOUNDATION DRILL OPERATOR (TRUCK MOUNTED)) | $10.05 | $0.00 | $10.05 | Survey |
| POWER EQUIPMENT OPERATORS: (FORM LOADER) | $7.25 | $0.00 | $7.25 | Survey |
| POWER EQUIPMENT OPERATORS: (CRUSHER OR SCREENING PLANT) | $7.25 | $0.00 | $7.25 | Survey |
POWER EQUIPMENT OPERATORS…Full textPOWER EQUIPMENT OPERATORS: (CRANE, CLAMSHELL, BACKHOE, DERRICK, DRAGLINE, SHOVEL (LESS THAN 1.5 CU. YD.)) | $9.10 | $0.00 | $9.10 | Survey |
POWER EQUIPMENT OPERATORS…Full textPOWER EQUIPMENT OPERATORS: (CRANE, CLAMSHELL, BACKHOE, DERRICK, DRAGLINE, SHOVEL (1.5 CU YD AND OVER)) | $9.80 | $0.00 | $9.80 | Survey |
| POWER EQUIPMENT OPERATORS: (CONCRETE PAVING SPREADER) | $8.60 | $0.00 | $8.60 | Survey |
| POWER EQUIPMENT OPERATORS: (CONCRETE PAVING SAW) | $8.30 | $0.00 | $8.30 | Survey |
| POWER EQUIPMENT OPERATORS: (CONCRETE PAVING JOINT MACHINE) | $8.00 | $0.00 | $8.00 | Survey |
| POWER EQUIPMENT OPERATORS: (CONCRETE PAVING FORM GRADER) | $9.75 | $0.00 | $9.75 | Survey |
| POWER EQUIPMENT OPERATORS: (CONCRETE PAVING FINISHING MACHINE) | $9.05 | $0.00 | $9.05 | Survey |
| POWER EQUIPMENT OPERATORS: (CONCRETE PAVING CURING MACHINE) | $8.40 | $0.00 | $8.40 | Survey |
| POWER EQUIPMENT OPERATORS: (BULLDOZER OVER 150 HP) | $9.05 | $0.00 | $9.05 | Survey |
| POWER EQUIPMENT OPERATORS: (BULLDOZER 150 HP OR LESS) | $8.05 | $0.00 | $8.05 | Survey |
| POWER EQUIPMENT OPERATORS: (BROOM OR SWEEPER OPERATOR) | $8.75 | $0.00 | $8.75 | Survey |
POWER EQUIPMENT OPERATORS…Full textPOWER EQUIPMENT OPERATORS: (ASPHALT PAVING MACHINE).$ 8.95 0.00 POWER EQUIPMENT OPERATORS: (ASPHALT DISTRIBUTOR) | $7.85 | $0.00 | $7.85 | Survey |
| PNEUMATIC MORTAR OPERATOR | $7.25 | $0.00 | $7.25 | Survey |
| PIPELAYER | $7.45 | $0.00 | $7.45 | Survey |
| PAINTER (STRUCTURES) | $10.00 | $0.00 | $10.00 | Survey |
| OILER | $8.50 | $0.00 | $8.50 | Survey |
| MECHANIC (UNDEFINED) | $10.00 | $0.00 | $10.00 | Survey |
| LABORERS: (UTILITY) | $7.25 | $0.00 | $7.25 | Survey |
| LABORERS: (COMMON) | $7.25 | $0.00 | $7.25 | Survey |
| FORM SETTER-STRUCTURES | $8.10 | $0.00 | $8.10 | Survey |
| FORM SETTER - PAVING & CURB | $8.55 | $0.00 | $8.55 | Survey |
| FORM LINER - PAVING & CURB | $8.50 | $0.00 | $8.50 | Survey |
| FORM BUILDER (STRUCTURES) | $8.20 | $0.00 | $8.20 | Survey |
| FLAGGER | $7.25 | $0.00 | $7.25 | Survey |
| ELECTRICIAN | $11.95 | $0.00 | $11.95 | Survey |
| CONCRETE RUBBER | $7.25 | $0.00 | $7.25 | Survey |
| CONCRETE FINISHER (STRUCTURES) | $8.90 | $0.00 | $8.90 | Survey |
| CONCRETE FINISHER (PAVING) | $9.20 | $0.00 | $9.20 | Survey |
| CARPENTER | $9.10 | $0.00 | $9.10 | Survey |
| BATTERBOARD SETTER | $8.45 | $0.00 | $8.45 | Survey |
| BATCHING PLANT SCALE OPERATOR | $8.50 | $0.00 | $8.50 | Survey |
| ASPHALT SHOVELER | $8.25 | $0.00 | $8.25 | Survey |
| ASPHALT RAKER | $9.00 | $0.00 | $9.00 | Survey |
| ASPHALT HEATER OPERATOR | $8.00 | $0.00 | $8.00 | Survey |
| AIR TOOL OPERATOR | $7.50 | $0.00 | $7.50 | Survey |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on TX20260019?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator