The short answer

This sheet sets 23 classifications for highway work in Anderson, Bedford, Benton and 92 more counties, Tennessee. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $13.11 an hour (laborer (common/unskilled)) to $26.36 (painter (includes sandblaster)). Your contract may lock an earlier modification.

What changed this year

First published January 2, 2026, this sheet is now on modification 1, but none of its modifications has changed a rate.

Latest change

May 18, 2026 · modification 1

Classification names reworded; no change among the 22 lines we could match

SAM.gov reworded this sheet’s classification names in this modification, so not every line can be matched to the one before. Only lines matched with certainty are compared here; nothing is guessed. If your trade is not listed, compare it against your contract’s copy.

Compared line by line from each modification as published on SAM.gov. A line we could not pair with certainty is left out rather than guessed.

Rates by classification

These are the rates in modification 1 as published on SAM.gov. The determination and modification written into your contract are the ones that bind you; check that number before relying on this table. Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from and its year; a survey year long past means the rate has not been surveyed since. A marker means the group changed in this modification. In the Since column, a dash means SAM.gov reworded the line during the year and it cannot be matched to the first publication with certainty. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
SUTN2016-001 · Survey of contractors in TN, July 13, 2016
TRUCK DRIVER (5 OR MORE AXLES)$16.27$0.00$16.27Survey, 2016
TRUCK DRIVER (3-4 AXLES)$14.86$0.00$14.86Survey, 2016
TRUCK DRIVER (2 AXLES)$15.36$0.00$15.36Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 4 SWEEPING MACHINE (VACUUM) OPERATOR$15.56$0.00$15.56Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 4…
Full text

POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT, CENTRAL MINING PLANT, CONCRETE PUMP, CONCRETE SAW, CURB MACHINE (AUTOMATIC OR MANUAL), DOZER OR LOADER (STOCKPILE), DRILL (PILING), MULCHER OR SEEDER, ROCK DRILL (TRUCK MOUNTED), ROLLER (ASPHALT), ROLLER (COMPACTION SELF-PROPELLED), SOIL STABILIZATION MACHINE, TRACTOR (BOOM AND HOIST), BITUMINOUS DISTRIBUTOR MACHINE, PUMP, TRACK DRILL, STRIPING MACHINE

$16.48$0.00$16.48Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 4 LIGHT DUTY MECHANIC$19.53$0.00$19.53Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 4 HEAVY DUTY MECHANIC$20.33$0.00$20.33Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 3…
Full text

POWER EQUIPMENT OPERATOR: GROUP 3 ASPHALT PAVER, CONCRETE FINISHING MACHINE, CONCRETE PAVER, SCALE, SPREADER (SELF-PROPELLED), CONCRETE GRINDER, ASPHALT MILLING MACHINE, BORING MACHINE (HORIZONTAL)

$17.75$0.00$17.75Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 2…
Full text

POWER EQUIPMENT OPERATOR: GROUP 2 BACKHOE/HYDRAULIC EXCAVATOR (LESS THAN 3/4 YD), BULLDOZER OR PUSH DOZER, END LOADER (LESS THAN 3 YD), MOTOR PATROL (ROUGH), TRACTOR (CRAWLER/ UTILITY), TRUCK DRIVER (HEAVY DUTY, OFF ROAD) SCRAPER, SHOVEL, OR TRENCHING MACHINE

$17.08$0.00$17.08Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 1A FARM TRACTOR OPERATOR (POWER BROOM)$13.50$0.00$13.50Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 1A DRILL OPERATOR (CAISSON)$25.26$0.00$25.26Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 1…
Full text

POWER EQUIPMENT OPERATOR: GROUP 1 BACKHOE/HYDRAULIC EXCAVATOR (3/4 YD & OVER), CRANE (LESS THAN 20 TONS), END LOADER (3 YD & OVER), MOTOR PATROL (FINISH),PILEDRIVER, DRAGLINE

$19.14$0.00$19.14Survey, 2016
POWER EQUIPMENT OPERATOR…
Full text

POWER EQUIPMENT OPERATOR: BOBCAT, CENTRAL MINING PLANT, CONCRETE PUMP, CONCRETE SAW, CURB MACHINE (AUTOMATIC OR MANUAL), DOZER OR LOADER (STOCKPILE), DRILL (PILING), MULCHER OR SEEDER, ROCK DRILL (TRUCK MOUNTED), ROLLER (ASPHALT), ROLLER (COMPACTION SELF-PROPELLED), SOIL STABILIZATION MACHINE, TRACTOR (BOOM AND HOIST), BITUMINOUS DISTRIBUTOR MACHINE, PUMP, TRACK DRILL, STRIPING MACHINE (GROUP 4)

$16.48$0.00$16.48Survey, 2016
POWER EQUIPMENT OPERATOR: GROUP 5 CRANE (OVER 20 TONS)$20.44$0.00$20.44Survey, 2016
PAINTER (INCLUDES SANDBLASTER)$26.36$0.00$26.36Survey, 2016
LABORER, SKILLED (AIR TOOL OPERATOR…
Full text

LABORER, SKILLED (AIR TOOL OPERATOR, ASPHALT RAKER, CHAIN SAW OPERATOR, CONCRETE MIXER (LESS THAN 1 YD), CONCRETE RUBBER, EDGER, FENCE ERECTOR, FORM SETTER (STEEL), GUARD RAIL ERECTOR, MECHANIC'S TENDER (TIRE CHANGER OR OILER), MORTAR MIXER, NOZZLEMAN OR GUN OPERATOR (GUNITE), PIPELAYER, SIGN ERECTOR)

$15.27$0.00$15.27Survey, 2016
LABORER (COMMON/UNSKILLED)$13.11$0.00$13.11Survey, 2016
IRONWORKER (STRUCTURAL)$16.89$0.00$16.89Survey, 2016
IRONWORKER (REINFORCING)$16.29$0.00$16.29Survey, 2016
ELECTRICIAN$24.08$0.00$24.08Survey, 2016
CEMENT MASON/CONCRETE FINISHER$15.55$0.00$15.55Survey, 2016
CARPENTER$17.52$0.00$17.52Survey, 2016
BRICKLAYER$14.26$0.00$14.26Survey, 2016

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on TN20260147?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator

Put these rates on a certified payroll.

Start here and TN20260147 is already filled in when you set up the job. CertifiedHours loads this sheet, checks every line against it as you type hours, and prints the WH-347. Free for one payroll a month.

Start a payroll on this sheet

On this sheet

  • 23 classifications in 1 rate groups
  • 0 from agreements, 1 from surveys
  • Counties: Anderson, Bedford, Benton, Bledsoe, Blount, Bradley, Campbell, Cannon, Carroll, Carter, Cheatham, Chester, Claiborne, Clay, Cocke, Coffee, Crockett, Cumberland, Davidson, De Kalb, Decatur, Dickson, Dyer, Fayette, Fentress, Franklin, Gibson, Giles, Grainger, Greene, Grundy, Hamblen, Hamilton, Hancock, Hardeman, Hardin, Hawkins, Haywood, Henderson, Henry, Hickman, Houston, Humphreys, Jackson, Jefferson, Johnson, Knox, Lake, Lauderdale, Lawrence, Lewis, Lincoln, Loudon, Macon, Madison, Marion, Marshall, Maury, McMinn, McNairy, Meigs, Monroe, Montgomery, Moore, Morgan, Obion, Overton, Perry, Pickett, Polk, Putnam, Rhea, Roane, Robertson, Rutherford, Scott, Sequatchie, Sevier, Shelby, Smith, Stewart, Sullivan, Sumner, Tipton, Trousdale, Unicoi, Union, Van Buren, Warren, Washington, Wayne, Weakley, White, Williamson, Wilson