This sheet sets 68 classifications for highway work in Adair, Cherokee, Craig and 8 more counties, Oklahoma. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $9.70 an hour (guardrail installer (includes guardrail/post driver work)) to $18.96 (power equipment operator: mechanic (muskogee county)). Your contract may lock an earlier modification.
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| SUOK2011-006 · Survey of contractors in OK, April 18, 2011 | ||||
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (REMAINING COUNTIES) | $15.75 | $0.00 | $15.75 | Survey |
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (MUSKOGEE COUNTY) | $16.14 | $0.00 | $16.14 | Survey |
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (MAYES COUNTY) | $16.93 | $0.00 | $16.93 | Survey |
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (DELAWARE COUNTY) | $15.15 | $0.00 | $15.15 | Survey |
| TRUCK DRIVER: DUMP TRUCK (REMAINING COUNTIES) | $13.91 | $0.00 | $13.91 | Survey |
| TRUCK DRIVER: DUMP TRUCK (MUSKOGEE COUNTY) | $13.93 | $0.00 | $13.93 | Survey |
| TRUCK DRIVER (WATER TRUCK) | $13.44 | $0.00 | $13.44 | Survey |
| TRUCK DRIVER (STRAIGHT TRUCK) | $15.92 | $0.00 | $15.92 | Survey |
| TRUCK DRIVER (SINGLE AXLE TRUCK (INCLUDES PILOT CAR)) | $13.15 | $0.00 | $13.15 | Survey |
| TRUCK DRIVER (OFF THE ROAD TRUCK) | $13.64 | $0.00 | $13.64 | Survey |
| TRUCK DRIVER (LOWBOY/FLOAT) | $15.20 | $0.69 | $15.89 | Survey |
| TRUCK DRIVER (FLATBED TRUCK) | $16.18 | $0.00 | $16.18 | Survey |
| TRUCK DRIVER (CONCRETE TRUCK) | $14.22 | $0.00 | $14.22 | Survey |
| POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (REMAINING COUNTIES) | $13.48 | $0.00 | $13.48 | Survey |
| POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (MUSKOGEE COUNTY) | $12.58 | $0.00 | $12.58 | Survey |
| POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (ADAIR COUNTY) | $13.12 | $0.00 | $13.12 | Survey |
| POWER EQUIPMENT OPERATOR: OILER (REMAINING COUNTIES) | $14.59 | $0.00 | $14.59 | Survey |
| POWER EQUIPMENT OPERATOR: OILER (MUSKOGEE COUNTY) | $13.38 | $0.00 | $13.38 | Survey |
| POWER EQUIPMENT OPERATOR: MECHANIC (REMAINING COUNTIES) | $18.77 | $0.00 | $18.77 | Survey |
| POWER EQUIPMENT OPERATOR: MECHANIC (MUSKOGEE COUNTY) | $18.96 | $0.00 | $18.96 | Survey |
| POWER EQUIPMENT OPERATOR: LOADER (FRONT END) (REMAINING COUNTIES) | $13.66 | $0.00 | $13.66 | Survey |
| POWER EQUIPMENT OPERATOR: LOADER (FRONT END) (MUSKOGEE COUNTY) | $13.83 | $0.00 | $13.83 | Survey |
| POWER EQUIPMENT OPERATOR: BULLDOZER (REMAINING COUNTIES) | $14.61 | $0.00 | $14.61 | Survey |
| POWER EQUIPMENT OPERATOR: BULLDOZER (MUSKOGEE COUNTY) | $14.33 | $0.00 | $14.33 | Survey |
| POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (REMAINING COUNTIES) | $16.13 | $0.00 | $16.13 | Survey |
| POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (MUSKOGEE COUNTY) | $14.99 | $0.00 | $14.99 | Survey |
| POWER EQUIPMENT OPERATOR: (TRENCHER) | $14.66 | $0.00 | $14.66 | Survey |
| POWER EQUIPMENT OPERATOR: (TRANSFER MATERIAL MACHINE) | $12.38 | $0.75 | $13.13 | Survey |
| POWER EQUIPMENT OPERATOR: (TRACTOR/BOX BLADE) | $12.83 | $0.00 | $12.83 | Survey |
| POWER EQUIPMENT OPERATOR: (STRIPING MACHINE) | $11.54 | $0.00 | $11.54 | Survey |
| POWER EQUIPMENT OPERATOR: (SCRAPER) | $14.13 | $0.00 | $14.13 | Survey |
| POWER EQUIPMENT OPERATOR: (ROTOMILL) | $17.33 | $0.00 | $17.33 | Survey |
| POWER EQUIPMENT OPERATOR: (ROLLER (DIRT COMPACTION)) | $12.44 | $0.00 | $12.44 | Survey |
| POWER EQUIPMENT OPERATOR: (MIXER) | $14.56 | $0.00 | $14.56 | Survey |
| POWER EQUIPMENT OPERATOR: (MILLING MACHINE) | $14.87 | $0.00 | $14.87 | Survey |
| POWER EQUIPMENT OPERATOR: (GRADER/BLADE) | $16.47 | $0.00 | $16.47 | Survey |
| POWER EQUIPMENT OPERATOR: (EXCAVATOR) | $14.75 | $0.00 | $14.75 | Survey |
| POWER EQUIPMENT OPERATOR: (DISTRIBUTOR TRUCK) | $13.34 | $0.00 | $13.34 | Survey |
| POWER EQUIPMENT OPERATOR: (CRANE) | $18.63 | $0.00 | $18.63 | Survey |
| POWER EQUIPMENT OPERATOR: (CONCRETE SAW) | $14.65 | $0.00 | $14.65 | Survey |
POWER EQUIPMENT OPERATOR…Full textPOWER EQUIPMENT OPERATOR: (CONCRETE PAVING MACHINE).$ 14.42 0.00 POWER EQUIPMENT OPERATOR: (BROOM) | $11.02 | $0.00 | $11.02 | Survey |
| POWER EQUIPMENT OPERATOR: (BOBCAT/SKID LOADER) | $12.56 | $0.00 | $12.56 | Survey |
| POWER EQUIPMENT OPERATOR: (ASPHALT PLANT) | $14.70 | $0.00 | $14.70 | Survey |
| POWER EQUIPMENT OPERATOR: (ASPHALT PAVING MACHINE) | $14.84 | $0.00 | $14.84 | Survey |
| POWER EQUIPMENT OPERATOR: (ASPHALT PAVER SCREED) | $14.77 | $0.00 | $14.77 | Survey |
| LABORER, COMMON OR GENERAL (REMAINING COUNTIES) | $10.64 | $0.00 | $10.64 | Survey |
| LABORER, COMMON OR GENERAL (OKFUSKEE COUNTY) | $10.55 | $0.00 | $10.55 | Survey |
| LABORER, COMMON OR GENERAL (MUSKOGEE COUNTY) | $10.68 | $0.00 | $10.68 | Survey |
| LABORER, COMMON OR GENERAL (MAYES COUNTY) | $10.07 | $0.00 | $10.07 | Survey |
| LABORER, COMMON OR GENERAL (DELAWARE COUNTY) | $11.16 | $0.00 | $11.16 | Survey |
| LABORER, COMMON OR GENERAL (CHEROKEE COUNTY) | $11.12 | $0.00 | $11.12 | Survey |
| LABORER, COMMON OR GENERAL (ADAIR COUNTY) | $11.96 | $0.00 | $11.96 | Survey |
| LABORER (VIBRATING PLATE) | $12.70 | $0.00 | $12.70 | Survey |
| LABORER (TRAFFIC CONTROL (INCLUDES FLAGGER, SETTING UP AND MOVING CONES/BARRELS)) | $10.28 | $0.00 | $10.28 | Survey |
| LABORER (PIPELAYER) | $11.13 | $0.00 | $11.13 | Survey |
| LABORER (ASPHALT RAKER AND SHOVELER) | $12.41 | $0.00 | $12.41 | Survey |
| LABORER (AIR/POWER TOOL OPERATOR (INCLUDES HANDHELD CONCRETE SAWS AND CHIPPING GUNS)) | $12.79 | $0.00 | $12.79 | Survey |
| IRONWORKER: REINFORCING | $13.63 | $0.00 | $13.63 | Survey |
| GUARDRAIL INSTALLER (INCLUDES GUARDRAIL/POST DRIVER WORK) | $9.70 | $0.00 | $9.70 | Survey |
| FORM WORKER/FORM SETTER (INCLUDING CURB LINE SETTING) | $12.30 | $0.00 | $12.30 | Survey |
CEMENT MASON/CONCRETE FINISHER…Full textCEMENT MASON/CONCRETE FINISHER (REMAINING COUNTIES).$ 13.70 0.00 CEMENT MASON/CONCRETE FINISHER (OTTAWA COUNTY) | $14.72 | $1.35 | $16.07 | Survey |
| CEMENT MASON/CONCRETE FINISHER (MUSKOGEE COUNTY) | $14.24 | $0.00 | $14.24 | Survey |
| CEMENT MASON/CONCRETE FINISHER (DELAWARE COUNTY) | $13.27 | $0.00 | $13.27 | Survey |
| CARPENTER, EXCLUDES FORM WORK AND FORM SETTING (REMAINING COUNTIES) | $13.94 | $0.00 | $13.94 | Survey |
| CARPENTER, EXCLUDES FORM WORK AND FORM SETTING (MUSKOGEE COUNTY) | $13.48 | $0.00 | $13.48 | Survey |
| CARPENTER, EXCLUDES FORM WORK AND FORM SETTING (DELAWARE COUNTY) | $13.69 | $0.00 | $13.69 | Survey |
| CARPENTER, EXCLUDES FORM WORK AND FORM SETTING (CHEROKEE COUNTY) | $14.00 | $0.00 | $14.00 | Survey |
| CARPENTER, EXCLUDES FORM WORK AND FORM SETTING (ADAIR COUNTY) | $13.70 | $0.00 | $13.70 | Survey |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on OK20260019?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator