CertifiedHours

Prevailing wage rates · Oklahoma · Wage determination

Prevailing wage rates: Beckham, Caddo, Cotton and 10 more counties, Oklahoma

Highway construction · OK20260018 modification 1, published May 18, 2026

The short answer

This sheet sets 64 classifications for highway work in Beckham, Caddo, Cotton and 10 more counties, Oklahoma. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $9.54 an hour (laborer, common or general (kiowa county)) to $17.33 (power equipment operator: (rotomill)). Your contract may lock an earlier modification.

What changed this year

First published January 2, 2026, this sheet is now on modification 1, but none of its modifications has changed a rate.

Latest change

May 18, 2026 · modification 1

12 classifications added, 12 classifications removed

Classifications added or removed
  • Added: POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (REMAINING COUNTIES) $12.61 + $0.00
  • Added: POWER EQUIPMENT OPERATOR: GRADER/BLADE (REMAINING COUNTIES) $13.30 + $0.00
  • Added: POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (REMAINING COUNTIES) $13.71 + $0.00
  • Added: LABORER, COMMON OR GENERAL (WASHITA COUNTY) $10.27 + $0.00
  • Added: LABORER, COMMON OR GENERAL (STEPHENS COUNTY) $10.31 + $0.00
  • Added: LABORER, COMMON OR GENERAL (ROGER MILLS COUNTY) $10.08 + $0.00
  • Added: LABORER, COMMON OR GENERAL (REMAINING COUNTIES) $10.29 + $0.00
  • Added: LABORER, COMMON OR GENERAL (KIOWA COUNTY) $9.54 + $0.00
  • Added: LABORER, COMMON OR GENERAL (JEFFERSON COUNTY) $10.07 + $0.00
  • Added: LABORER, COMMON OR GENERAL (GREER COUNTY) $10.05 + $0.00
  • Added: LABORER, COMMON OR GENERAL (CUSTER COUNTY) $10.60 + $0.00
  • Added: LABORER, COMMON OR GENERAL (CADDO COUNTY) $10.30 + $0.00
  • Removed: LABORER Caddo County
  • Removed: LABORER Custer County
  • Removed: LABORER Greer County
  • Removed: LABORER Jefferson County
  • Removed: LABORER Kiowa County
  • Removed: LABORER Remaining Counties
  • Removed: LABORER Roger Mills County
  • Removed: LABORER Stephens County
  • Removed: LABORER Washita County
  • Removed: POWER EQUIPMENT OPERATOR: Remaining Counties
  • Removed: POWER EQUIPMENT OPERATOR: Remaining Counties
  • Removed: POWER EQUIPMENT OPERATOR: Remaining Counties

Compared line by line from each modification as published on SAM.gov. A line we could not pair with certainty is left out rather than guessed.

Rates by classification

These are the rates in modification 1 as published on SAM.gov. The determination and modification written into your contract are the ones that bind you; check that number before relying on this table. Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from and its year; a survey year long past means the rate has not been surveyed since. A marker means the group changed in this modification. In the Since column, a dash means SAM.gov reworded the line during the year and it cannot be matched to the first publication with certainty. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
SUOK2011-005 · Survey of contractors in OK, April 18, 2011
TRUCK DRIVER (WATER TRUCK)$12.00$0.00$12.00Survey, 2011
TRUCK DRIVER (TANDEM AXLE/SEMI TRAILER)$13.53$0.00$13.53Survey, 2011
TRUCK DRIVER (STRAIGHT TRUCK)$15.92$0.00$15.92Survey, 2011
TRUCK DRIVER (SINGLE AXLE TRUCK (INCLUDES PILOT CAR))$12.30$0.00$12.30Survey, 2011
TRUCK DRIVER (OFF THE ROAD TRUCK)$11.84$0.00$11.84Survey, 2011
TRUCK DRIVER (LOWBOY/FLOAT)$16.02$0.00$16.02Survey, 2011
TRUCK DRIVER (FLATBED TRUCK)$15.30$0.00$15.30Survey, 2011
TRUCK DRIVER (DUMP TRUCK)$12.84$0.00$12.84Survey, 2011
TRUCK DRIVER (CONCRETE TRUCK)$14.22$0.00$14.22Survey, 2011
POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (REMAINING COUNTIES)$12.61$0.00$12.61Survey, 2011
POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (CADDO COUNTY)$12.73$0.00$12.73Survey, 2011
POWER EQUIPMENT OPERATOR: GRADER/BLADE (REMAINING COUNTIES)$13.30$0.00$13.30Survey, 2011
POWER EQUIPMENT OPERATOR: GRADER/BLADE (CADDO COUNTY)$13.18$0.00$13.18Survey, 2011
POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (REMAINING COUNTIES)$13.71$0.00$13.71Survey, 2011
POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (CADDO COUNTY)$13.46$0.00$13.46Survey, 2011
POWER EQUIPMENT OPERATOR: (TRENCHER)$14.66$0.00$14.66Survey, 2011
POWER EQUIPMENT OPERATOR: (TRANSFER MATERIAL MACHINE)$12.38$0.75$13.13Survey, 2011
POWER EQUIPMENT OPERATOR: (TRACTOR/BOX BLADE)$9.79$0.00$9.79Survey, 2011
POWER EQUIPMENT OPERATOR: (STRIPING MACHINE)$12.11$0.00$12.11Survey, 2011
POWER EQUIPMENT OPERATOR: (SCRAPER)$12.82$0.00$12.82Survey, 2011
POWER EQUIPMENT OPERATOR: (ROTOMILL)$17.33$0.00$17.33Survey, 2011
POWER EQUIPMENT OPERATOR: (ROLLER (DIRT COMPACTION))$10.22$0.00$10.22Survey, 2011
POWER EQUIPMENT OPERATOR: (OILER)$13.84$0.00$13.84Survey, 2011
POWER EQUIPMENT OPERATOR: (MIXER)$14.56$0.00$14.56Survey, 2011
POWER EQUIPMENT OPERATOR: (MILLING MACHINE)$11.81$0.00$11.81Survey, 2011
POWER EQUIPMENT OPERATOR: (MECHANIC)$16.89$0.00$16.89Survey, 2011
POWER EQUIPMENT OPERATOR: (LOADER (FRONT END))$12.21$0.00$12.21Survey, 2011
POWER EQUIPMENT OPERATOR: (EXCAVATOR)$15.45$0.00$15.45Survey, 2011
POWER EQUIPMENT OPERATOR: (DISTRIBUTOR TRUCK)$12.24$0.00$12.24Survey, 2011
POWER EQUIPMENT OPERATOR: (CRANE)$16.61$0.00$16.61Survey, 2011
POWER EQUIPMENT OPERATOR: (CONCRETE SAW)$12.46$0.00$12.46Survey, 2011
POWER EQUIPMENT OPERATOR: (CONCRETE PAVING MACHINE)$14.42$0.00$14.42Survey, 2011
POWER EQUIPMENT OPERATOR: (BULLDOZER)$13.69$0.00$13.69Survey, 2011
POWER EQUIPMENT OPERATOR: (BROOM)$11.02$0.00$11.02Survey, 2011
POWER EQUIPMENT OPERATOR: (BOBCAT/SKID LOADER)$12.06$0.00$12.06Survey, 2011
POWER EQUIPMENT OPERATOR: (ASPHALT PLANT)$14.70$0.00$14.70Survey, 2011
POWER EQUIPMENT OPERATOR: (ASPHALT PAVING MACHINE)$12.32$0.00$12.32Survey, 2011
POWER EQUIPMENT OPERATOR: (ASPHALT PAVER SCREED)$13.19$0.00$13.19Survey, 2011
LABORER, COMMON OR GENERAL (WASHITA COUNTY)$10.27$0.00$10.27Survey, 2011
LABORER, COMMON OR GENERAL (STEPHENS COUNTY)$10.31$0.00$10.31Survey, 2011
LABORER, COMMON OR GENERAL (ROGER MILLS COUNTY)$10.08$0.00$10.08Survey, 2011
LABORER, COMMON OR GENERAL (REMAINING COUNTIES)$10.29$0.00$10.29Survey, 2011
LABORER, COMMON OR GENERAL (KIOWA COUNTY)$9.54$0.00$9.54Survey, 2011
LABORER, COMMON OR GENERAL (JEFFERSON COUNTY)$10.07$0.00$10.07Survey, 2011
LABORER, COMMON OR GENERAL (GREER COUNTY)$10.05$0.00$10.05Survey, 2011
LABORER, COMMON OR GENERAL (CUSTER COUNTY)$10.60$0.00$10.60Survey, 2011
LABORER, COMMON OR GENERAL (CADDO COUNTY)$10.30$0.00$10.30Survey, 2011
LABORER, COMMON OR GENERAL (BECKHAM COUNTY)$10.47$0.00$10.47Survey, 2011
LABORER (VIBRATING PLATE)$12.70$0.00$12.70Survey, 2011
LABORER (TRAFFIC CONTROL (INCLUDES FLAGGER, SETTING UP AND MOVING CONES/BARRELS))$10.39$0.00$10.39Survey, 2011
LABORER (PIPELAYER)$11.83$0.00$11.83Survey, 2011
LABORER (ASPHALT RAKER AND SHOVELER)$10.49$0.00$10.49Survey, 2011
LABORER (AIR/POWER TOOL OPERATOR (INCLUDES HANDHELD CONCRETE SAWS AND CHIPPING GUNS))$12.79$0.00$12.79Survey, 2011
IRONWORKER: REINFORCING$13.63$0.00$13.63Survey, 2011
GUARDRAIL INSTALLER (INCLUDES GUARDRAIL/POST DRIVER WORK)$9.70$0.00$9.70Survey, 2011
FORM WORKER (WASHITA COUNTY)$11.13$0.00$11.13Survey, 2011
FORM WORKER (REMAINING COUNTIES)$11.46$0.00$11.46Survey, 2011
CEMENT MASON/CONCRETE FINISHER (WASHITA COUNTY)$12.95$0.00$12.95Survey, 2011
CEMENT MASON/CONCRETE FINISHER (REMAINING COUNTIES)$12.53$0.00$12.53Survey, 2011
CEMENT MASON/CONCRETE FINISHER (CUSTER COUNTY)$13.38$0.00$13.38Survey, 2011
CEMENT MASON/CONCRETE FINISHER (CADDO COUNTY)$11.04$0.00$11.04Survey, 2011
CARPENTER, EXCLUDES FORM WORK (REMAINING COUNTIES)$12.57$0.00$12.57Survey, 2011
CARPENTER, EXCLUDES FORM WORK (CUSTER COUNTY)$12.39$0.00$12.39Survey, 2011
CARPENTER, EXCLUDES FORM WORK (CADDO COUNTY)$12.18$0.00$12.18Survey, 2011

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on OK20260018?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator

Put these rates on a certified payroll.

Start here and OK20260018 is already filled in when you set up the job. CertifiedHours loads this sheet, checks every line against it as you type hours, and prints the WH-347. Free for one payroll a month.

Start a payroll on this sheet

On this sheet

  • 64 classifications in 1 rate groups
  • 0 from agreements, 1 from surveys
  • Counties: Beckham, Caddo, Cotton, Custer, Greer, Harmon, Jackson, Jefferson, Kiowa, Roger Mills, Stephens, Tillman, Washita