CertifiedHours

Prevailing wage rates · Oklahoma · Wage determination

Prevailing wage rates: Creek, Okmulgee, Osage and 4 more counties, Oklahoma

Highway construction · OK20260017 modification 1, published May 18, 2026

The short answer

This sheet sets 54 classifications for highway work in Creek, Okmulgee, Osage and 4 more counties, Oklahoma. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $8.67 an hour (laborer (landscape)) to $18.04 (traffic signal installer). Your contract may lock an earlier modification.

What changed this year

First published January 2, 2026, this sheet is now on modification 1, but none of its modifications has changed a rate.

Latest change

May 18, 2026 · modification 1

10 classifications added, 10 classifications removed

Classifications added or removed
  • Added: TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (TULSA COUNTY) $18.01 + $0.00
  • Added: TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (ROGERS COUNTY) $14.01 + $0.31
  • Added: POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (TULSA COUNTY) $15.19 + $0.00
  • Added: POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (ROGERS COUNTY) $15.11 + $0.00
  • Added: LABORER, TRAFFIC CONTROL… $10.94 + $0.00
  • Added: LABORER, COMMON OR GENERAL (WAGONER) $10.32 + $0.00
  • Added: LABORER, COMMON OR GENERAL (TULSA COUNTY) $10.84 + $0.00
  • Added: LABORER, COMMON OR GENERAL (ROGERS COUNTY) $10.14 + $0.00
  • Added: LABORER, COMMON OR GENERAL (REMAINING COUNTIES) $10.70 + $0.00
  • Added: LABORER, ASPHALT RAKER AND SHOVELER (ROGERS COUNTY) $11.76 + $1.57
  • Removed: LABORER Rogers County
  • Removed: LABORER Remaining Counties
  • Removed: LABORER Rogers County
  • Removed: LABORER Tulsa County
  • Removed: LABORER Wagoner
  • Removed: LABORER Tulsa County
  • Removed: POWER EQUIPMENT OPERATOR: Rogers County
  • Removed: POWER EQUIPMENT OPERATOR: Tulsa County
  • Removed: TRUCK DRIVER Rogers County
  • Removed: TRUCK DRIVER Tulsa County

Compared line by line from each modification as published on SAM.gov. A line we could not pair with certainty is left out rather than guessed.

Rates by classification

These are the rates in modification 1 as published on SAM.gov. The determination and modification written into your contract are the ones that bind you; check that number before relying on this table. Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from and its year; a survey year long past means the rate has not been surveyed since. A marker means the group changed in this modification. In the Since column, a dash means SAM.gov reworded the line during the year and it cannot be matched to the first publication with certainty. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
SUOK2011-004 · Survey of contractors in OK, April 18, 2011
TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (TULSA COUNTY)$18.01$0.00$18.01Survey, 2011
TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (ROGERS COUNTY)$14.01$0.31$14.32Survey, 2011
TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (REMAINING COUNTIES)$16.36$0.00$16.36Survey, 2011
TRUCK DRIVER (WATER TRUCK)$12.00$0.00$12.00Survey, 2011
TRUCK DRIVER (PICKUP TRUCK)$12.32$0.00$12.32Survey, 2011
TRUCK DRIVER (OFF THE ROAD TRUCK)$13.40$0.00$13.40Survey, 2011
TRUCK DRIVER (LOWBOY/FLOAT)$13.80$0.00$13.80Survey, 2011
TRUCK DRIVER (FLATBED TRUCK)$14.69$0.00$14.69Survey, 2011
TRUCK DRIVER (DUMP TRUCK)$13.97$0.00$13.97Survey, 2011
TRAFFIC SIGNAL INSTALLER$18.04$0.00$18.04Survey, 2011
POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (TULSA COUNTY)$15.19$0.00$15.19Survey, 2011
POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (ROGERS COUNTY)$15.11$0.00$15.11Survey, 2011
POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (REMAINING COUNTIES)$15.16$0.00$15.16Survey, 2011
POWER EQUIPMENT OPERATOR: (TRENCHER)$13.87$0.00$13.87Survey, 2011
POWER EQUIPMENT OPERATOR: (TRACTOR/BOX BLADE)$13.67$0.00$13.67Survey, 2011
POWER EQUIPMENT OPERATOR: (STRIPING MACHINE)$11.94$0.00$11.94Survey, 2011
POWER EQUIPMENT OPERATOR: (SCRAPER)$13.34$0.00$13.34Survey, 2011
POWER EQUIPMENT OPERATOR: (ROLLER (DIRT COMPACTION))$11.71$0.00$11.71Survey, 2011
POWER EQUIPMENT OPERATOR: (ROLLER (ASPHALT))$12.79$0.00$12.79Survey, 2011
POWER EQUIPMENT OPERATOR: (OILER)$15.28$0.00$15.28Survey, 2011
POWER EQUIPMENT OPERATOR: (MIXER)$14.43$0.00$14.43Survey, 2011
POWER EQUIPMENT OPERATOR: (MILLING MACHINE)$14.56$0.00$14.56Survey, 2011
POWER EQUIPMENT OPERATOR: (MECHANIC)$17.46$0.00$17.46Survey, 2011
POWER EQUIPMENT OPERATOR: (LOADER (FRONT END))$13.81$0.00$13.81Survey, 2011
POWER EQUIPMENT OPERATOR: (GRADER/BLADE)$16.68$0.00$16.68Survey, 2011
POWER EQUIPMENT OPERATOR: (EXCAVATOR)$14.99$0.00$14.99Survey, 2011
POWER EQUIPMENT OPERATOR: (DISTRIBUTOR TRUCK)$13.34$0.00$13.34Survey, 2011
POWER EQUIPMENT OPERATOR: (CRANE)$17.45$0.00$17.45Survey, 2011
POWER EQUIPMENT OPERATOR: (CONCRETE SAW)$11.94$0.00$11.94Survey, 2011
POWER EQUIPMENT OPERATOR: (CONCRETE PAVING MACHINE)$14.11$0.00$14.11Survey, 2011
POWER EQUIPMENT OPERATOR: (BULLDOZER)$14.28$0.00$14.28Survey, 2011
POWER EQUIPMENT OPERATOR: (BROOM)$11.97$0.00$11.97Survey, 2011
POWER EQUIPMENT OPERATOR: (BOBCAT/SKID LOADER)$12.24$0.00$12.24Survey, 2011
POWER EQUIPMENT OPERATOR: (ASPHALT PAVING MACHINE)$13.95$2.75$16.70Survey, 2011
POWER EQUIPMENT OPERATOR: (ASPHALT PAVER SCREED)$12.96$0.00$12.96Survey, 2011
LABORER, TRAFFIC CONTROL…
Full text

LABORER, TRAFFIC CONTROL (INCLUDES FLAGGER, SETTING UP AND MOVING CONES/BARRELS) (TULSA COUNTY)

$10.94$0.00$10.94Survey, 2011
LABORER, TRAFFIC CONTROL…
Full text

LABORER, TRAFFIC CONTROL (INCLUDES FLAGGER, SETTING UP AND MOVING CONES/BARRELS) (REMAINING COUNTIES)

$11.05$0.00$11.05Survey, 2011
LABORER, COMMON OR GENERAL (WAGONER)$10.32$0.00$10.32Survey, 2011
LABORER, COMMON OR GENERAL (TULSA COUNTY)$10.84$0.00$10.84Survey, 2011
LABORER, COMMON OR GENERAL (ROGERS COUNTY)$10.14$0.00$10.14Survey, 2011
LABORER, COMMON OR GENERAL (REMAINING COUNTIES)$10.70$0.00$10.70Survey, 2011
LABORER, COMMON OR GENERAL (CREEK COUNTY)$10.95$0.00$10.95Survey, 2011
LABORER, ASPHALT RAKER AND SHOVELER (ROGERS COUNTY)$11.76$1.57$13.33Survey, 2011
LABORER, ASPHALT RAKER AND SHOVELER (REMAINING COUNTIES)$12.40$1.57$13.97Survey, 2011
LABORER (POWER TOOL OPERATOR (INCLUDES CHIPPING GUNS AND HANDHELD CONCRETE SAWS))$12.89$0.00$12.89Survey, 2011
LABORER (PIPELAYER)$12.35$0.00$12.35Survey, 2011
LABORER (LANDSCAPE)$8.67$0.00$8.67Survey, 2011
IRONWORKER: REINFORCING$15.38$0.00$15.38Survey, 2011
IRONWORKER, STRUCTURAL$14.21$0.00$14.21Survey, 2011
CEMENT MASON/CONCRETE FINISHER (TULSA COUNTY)$13.44$0.00$13.44Survey, 2011
CEMENT MASON/CONCRETE FINISHER (REMAINING COUNTIES)$13.36$0.00$13.36Survey, 2011
CARPENTER, INCLUDES FORM WORK, AND CURB LINE FORMSETTING (TULSA COUNTY)$12.80$0.00$12.80Survey, 2011
CARPENTER, INCLUDES FORM WORK, AND CURB LINE FORMSETTING (ROGERS COUNTY)$14.82$0.00$14.82Survey, 2011
CARPENTER, INCLUDES FORM WORK, AND CURB LINE FORMSETTING (REMAINING COUNTIES)$13.24$0.00$13.24Survey, 2011

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on OK20260017?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator

Put these rates on a certified payroll.

Start here and OK20260017 is already filled in when you set up the job. CertifiedHours loads this sheet, checks every line against it as you type hours, and prints the WH-347. Free for one payroll a month.

Start a payroll on this sheet

On this sheet

  • 54 classifications in 1 rate groups
  • 0 from agreements, 1 from surveys
  • Counties: Creek, Okmulgee, Osage, Pawnee, Rogers, Tulsa, Wagoner