The short answer
This sheet sets 38 classifications for building work in Cuyahoga County, Ohio. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $35.18 an hour (painter: spray) to $102.23 (elevator mechanic). Your contract may lock an earlier modification.
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| ASBE0003-002 · Asbestos Workers and Heat & Frost Insulators agreement, August 1, 2024 | ||||
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $43.88 | $26.93 | $70.81 | Agreement |
| BROH0005-006 · Bricklayers agreement, May 1, 2023 | ||||
| BRICKLAYER | $38.13 | $20.19 | $58.32 | Agreement |
| BROH0005-007 · Bricklayers agreement, May 1, 2023 | ||||
| BRICK POINTER/CAULKER/CLEANER | $38.13 | $20.19 | $58.32 | Agreement |
| BROH0005-009 · Bricklayers agreement, May 1, 2024 | ||||
| TILE FINISHER | $31.50 | $16.23 | $47.73 | Agreement |
| BROH0036-001 · Bricklayers agreement, May 1, 2024 | ||||
| TILE SETTER | $36.07 | $19.49 | $55.56 | Agreement |
| CARP0373-001 · Carpenters agreement, May 1, 2024 | ||||
| SOFT FLOOR LAYER | $37.52 | $23.50 | $61.02 | Agreement |
| CARP0435-004 · Carpenters agreement, May 1, 2024 | ||||
CARPENTER (INCLUDING DRYWALL HANGING AND METAL STUD INSTALLATION…Full textCARPENTER (INCLUDING DRYWALL HANGING AND METAL STUD INSTALLATION; EXCLUDING SOFT FLOOR LAYING AND FORM WORK) | $37.52 | $23.50 | $61.02 | Agreement |
| CARP1090-001 · Carpenters agreement, May 1, 2025 | ||||
| PILEDRIVERMAN | $36.34 | $27.50 | $63.84 | Agreement |
| ELEC0038-005 · Electrical Workers (IBEW) agreement, April 28, 2025 | ||||
| ELECTRICIAN (LOW VOLTAGE WIRING ONLY) FOOTNOTES: ; A. 6 PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; JULY 4TH; LABOR DAY; THANKSGIVING DAY; & CHRISTMAS DAY B. 1 WEEK'S PAID VACATION FOR 1 YEAR'S SERVICE; 2 WEEKS' PAID VACATION FOR 2 OR MORE YEARS' SERVICE | $33.05 | $14.91 | $47.96 | Agreement |
| ELEC0038-006 · Electrical Workers (IBEW) agreement, April 28, 2025 | ||||
| ELECTRICIAN: INCLUDING HVAC/TEMPERATURE CONTROLS AND ALARM INSTALLATION FOOTNOTES: ; A. 6 PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; JULY 4TH; LABOR DAY; THANKSGIVING DAY; & CHRISTMAS DAY B. 1 WEEK'S PAID VACATION FOR 1 YEAR'S SERVICE; 2 WEEKS' PAID VACATION FOR 2 OR MORE YEARS' SERVICE | $46.63 | $24.92 | $71.55 | Agreement |
| ELEV0017-002 · Elevator Constructors agreement, January 1, 2025 | ||||
| ELEVATOR MECHANIC PAID HOLIDAYS: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERN'S DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE TO VACATION PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE | $63.79 | $38.44 | $102.23 | Agreement |
| ENGI0018-039 · Operating Engineers agreement, May 1, 2024 | ||||
| POWER EQUIPMENT OPERATOR (OILER) | $36.93 | $16.41 | $53.34 | Agreement |
| POWER EQUIPMENT OPERATOR (BACKHOE/EXCAVATOR/TRACKHOE; CRANE) | $46.71 | $16.41 | $63.12 | Agreement |
| ENGI0018-040 · Operating Engineers agreement, May 1, 2024 | ||||
| POWER EQUIPMENT OPERATOR: BULLDOZER | $46.71 | $16.41 | $63.12 | Agreement |
| ENGI0066-045 · Operating Engineers agreement, June 1, 2017 | ||||
| POWER EQUIPMENT OPERATOR: GRADER/BLADE | $32.42 | $19.66 | $52.08 | Agreement |
| POWER EQUIPMENT OPERATOR: FORKLIFT | $28.87 | $19.66 | $48.53 | Agreement |
| POWER EQUIPMENT OPERATOR (MECHANIC) | $32.92 | $19.66 | $52.58 | Agreement |
| IRON0017-011 · Ironworkers agreement, May 1, 2024 | ||||
| IRONWORKER (ORNAMENTAL, REINFORCING, & STRUCTURAL) | $36.83 | $29.01 | $65.84 | Agreement |
| LABO0310-002 · Laborers agreement, June 1, 2024 | ||||
| LABORER (COMMON OR GENERAL; MASON TENDER - BRICK & CEMENT/CONCRETE) | $31.89 | $22.66 | $54.55 | Agreement |
| LABO0894-003 · Laborers agreement, June 1, 2018 | ||||
| LABORER: PIPELAYER | $31.27 | $10.90 | $42.17 | Agreement |
| LABO0894-004 · Laborers agreement, May 1, 2018 | ||||
| LABORER (FORM WORK) | $32.28 | $10.95 | $43.23 | Agreement |
| PAIN0181-001 · Painters and Allied Trades agreement, May 1, 2024 | ||||
| GLAZIER | $34.82 | $20.80 | $55.62 | Agreement |
| PAIN0707-002 · Painters and Allied Trades agreement, May 1, 2024 | ||||
| PAINTER: BRUSH AND ROLLER | $32.35 | $19.45 | $51.80 | Agreement |
| PAIN0707-003 · Painters and Allied Trades agreement, May 1, 2025 | ||||
| PAINTER (DRYWALL FINISHING/TAPING ONLY) | $35.45 | $20.20 | $55.65 | Agreement |
| PLAS0031-018 · Plasterers and Cement Masons agreement, May 1, 2014 | ||||
| PLASTERER (INCLUDING FLOOR LAYER: FLOOR COATING/EPOXY) | $29.51 | $15.67 | $45.18 | Agreement |
| PLAS0404-001 · Plasterers and Cement Masons agreement, May 1, 2025 | ||||
| CEMENT MASON/CONCRETE FINISHER | $35.58 | $23.71 | $59.29 | Agreement |
| PLUM0055-002 · Plumbers and Pipefitters agreement, May 5, 2025 | ||||
| PLUMBER (EXCLUDES HVAC PIPE INSTALLATION) | $44.86 | $30.03 | $74.89 | Agreement |
| PLUM0120-009 · Plumbers and Pipefitters agreement, May 1, 2025 | ||||
| SPRINKLER FITTER (FIRE SPRINKLERS) | $49.17 | $28.55 | $77.72 | Agreement |
| PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION) | $49.17 | $28.55 | $77.72 | Agreement |
| ROOF0044-003 · Roofers agreement, April 27, 2025 | ||||
| ROOFER | $40.15 | $21.28 | $61.43 | Agreement |
| SHEE0033-044 · Sheet Metal Workers agreement, May 1, 2024 | ||||
| SHEET METAL WORKER (INCLUDING HVAC DUCT AND UNIT INSTALLATION) | $43.06 | $30.11 | $73.17 | Agreement |
| SUOH2012-076 · Survey of contractors in OH, August 29, 2014 | ||||
| TRUCK DRIVER: DUMP (ALL TYPES) | $24.32 | $11.73 | $36.05 | Survey |
| PAINTER: SPRAY | $22.78 | $12.40 | $35.18 | Survey |
| OPERATOR: ROLLER | $31.48 | $12.80 | $44.28 | Survey |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $31.48 | $12.80 | $44.28 | Survey |
| OPERATOR: LOADER | $29.66 | $12.61 | $42.27 | Survey |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $32.88 | $12.26 | $45.14 | Survey |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $24.53 | $14.55 | $39.08 | Survey |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on OH20260074?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator