Prevailing wage rates · New York · Wage determination
Prevailing wage rates: Erie County, New York
Building construction · NY20260050 modification 1, published May 18, 2026
The short answer
This sheet sets 96 classifications for building work in Erie County, New York. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $19.82 an hour (sprinkler fitter) to $107.51 (electrician, line construction). Your contract may lock an earlier modification.
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| BOIL0007-001 · Boilermakers agreement, January 1, 2025 | ||||
| BOILERMAKER | $39.35 | $33.18 | $72.53 | Agreement |
| BRNY0045-004 · Bricklayers agreement, July 1, 2021 | ||||
| CEMENT MASON | $32.53 | $22.10 | $54.63 | Agreement |
| MARBLE SETTER | $36.85 | $30.80 | $67.65 | Agreement |
| TILE FINISHER | $34.71 | $17.54 | $52.25 | Agreement |
| TERRAZZO FINISHER | $34.71 | $17.54 | $52.25 | Agreement |
| TILESETTER & TERRAZZO WORKER | $38.85 | $32.20 | $71.05 | Agreement |
| BRICKLAYER | $39.44 | $32.11 | $71.55 | Agreement |
| BRNY0045-004 · Bricklayers agreement, July 1, 2023 | ||||
| CEMENT MASON | $32.53 | $22.10 | $54.63 | Agreement |
| MARBLE SETTER | $36.85 | $30.80 | $67.65 | Agreement |
| TILE FINISHER | $34.71 | $17.54 | $52.25 | Agreement |
| TERRAZZO FINISHER | $34.71 | $17.54 | $52.25 | Agreement |
| TILESETTER & TERRAZZO WORKER | $38.85 | $32.20 | $71.05 | Agreement |
| BRICKLAYER | $39.44 | $32.11 | $71.55 | Agreement |
| BRNY0045-004 · Bricklayers agreement, July 1, 2024 | ||||
| CEMENT MASON | $32.53 | $22.10 | $54.63 | Agreement |
| MARBLE SETTER | $36.85 | $30.80 | $67.65 | Agreement |
| TILE FINISHER | $34.71 | $17.54 | $52.25 | Agreement |
| TERRAZZO FINISHER | $34.71 | $17.54 | $52.25 | Agreement |
| TILESETTER & TERRAZZO WORKER | $38.85 | $32.20 | $71.05 | Agreement |
| BRICKLAYER | $39.44 | $32.11 | $71.55 | Agreement |
| BRNY0045-004 · Bricklayers agreement, July 1, 2025 | ||||
| CEMENT MASON | $32.53 | $22.10 | $54.63 | Agreement |
| MARBLE SETTER | $36.85 | $30.80 | $67.65 | Agreement |
| TILE FINISHER | $34.71 | $17.54 | $52.25 | Agreement |
| TERRAZZO FINISHER | $34.71 | $17.54 | $52.25 | Agreement |
| TILESETTER & TERRAZZO WORKER | $38.85 | $32.20 | $71.05 | Agreement |
| BRICKLAYER | $39.44 | $32.11 | $71.55 | Agreement |
| CARP0276-014 · Carpenters agreement, July 1, 2024 | ||||
| CARPENTER | $34.73 | $28.61 | $63.34 | Agreement |
| ELEC0041-003 · Electrical Workers (IBEW) agreement, April 1, 2014 | ||||
| CABLE SPLICER | $36.73 | $23.39 | $60.12 | Agreement |
| ELECTRICIAN | $44.50 | $36.06 | $80.56 | Agreement |
| ELEC0041-003 · Electrical Workers (IBEW) agreement, May 26, 2025 | ||||
| CABLE SPLICER | $36.73 | $23.39 | $60.12 | Agreement |
| ELECTRICIAN | $44.50 | $36.06 | $80.56 | Agreement |
| ELEC0041-004 · Electrical Workers (IBEW) agreement, May 26, 2025 | ||||
COMMUNICATIONS SYSTEM…Full textCOMMUNICATIONS SYSTEM (SOUND WIREMAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK | $44.50 | $36.05 | $80.55 | Agreement |
COMMUNICATIONS SYSTEM…Full textCOMMUNICATIONS SYSTEM (MASTER TECHNICIAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK | $44.50 | $36.05 | $80.55 | Agreement |
COMMUNICATIONS SYSTEM…Full textCOMMUNICATIONS SYSTEM (INSTALLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK | $22.90 | $21.38 | $44.28 | Agreement |
COMMUNICATIONS SYSTEM…Full textCOMMUNICATIONS SYSTEM (CABLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK | $14.20 | $14.02 | $28.22 | Agreement |
| ELEC1249-003 · Electrical Workers (IBEW) agreement, May 5, 2025 | ||||
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $42.29 | $30.66 | $72.95 | Agreement |
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $52.86 | $35.60 | $88.46 | Agreement |
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $47.57 | $31.03 | $78.60 | Agreement |
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $42.29 | $30.66 | $72.95 | Agreement |
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $31.72 | $29.87 | $61.59 | Agreement |
| ELEC1249-004 · Electrical Workers (IBEW) agreement, May 5, 2025 | ||||
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $49.25 | $31.15 | $80.40 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | $61.56 | $36.21 | $97.77 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | $61.56 | $36.21 | $97.77 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | $55.40 | $31.78 | $87.18 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | $55.40 | $31.78 | $87.18 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $55.40 | $31.78 | $87.18 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $35.34 | $30.12 | $65.46 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | $35.34 | $30.12 | $65.46 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $35.34 | $30.12 | $65.46 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $64.59 | $42.92 | $107.51 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | $63.14 | $33.82 | $96.96 | Agreement |
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES…Full textELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | $80.40 | Agreement |
| ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK…Full textELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $61.56 | $36.21 | $97.77 | Agreement |
| ELEC1249-008 · Electrical Workers (IBEW) agreement, January 1, 2025 | ||||
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…Full textELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $38.73 | $6.93 | $45.66 | Agreement |
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…Full textELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $20.53 | $6.39 | $26.92 | Agreement |
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…Full textELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.81 | $6.99 | $47.80 | Agreement |
| ELEV0014-001 · Elevator Constructors agreement, January 1, 2025 | ||||
| ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | $62.39 | $38.44 | $100.83 | Agreement |
| ENGI0017-001 · Operating Engineers agreement, July 1, 2025 | ||||
| POWER EQUIPMENT OPERATORS: GROUP 8 MASTER MEACHANIC NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $45.47 | $35.40 | $80.87 | Agreement |
| POWER EQUIPMENT OPERATORS: GROUP 7 ANY TOWER CRANES NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $49.98 | $35.40 | $85.38 | Agreement |
| POWER EQUIPMENT OPERATORS: GROUP 6 ANY CRANE 400 TONS AND OVER NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $49.48 | $35.40 | $84.88 | Agreement |
| POWER EQUIPMENT OPERATORS: GROUP 5 ANY CRANE 200 - 399 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $48.98 | $35.40 | $84.38 | Agreement |
| POWER EQUIPMENT OPERATORS: GROUP 4 ANY CRANE 61 - 199 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $48.48 | $35.40 | $83.88 | Agreement |
| POWER EQUIPMENT OPERATORS: GROUP 3 ANY CRANE UP TO 60 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $47.48 | $35.40 | $82.88 | Agreement |
POWER EQUIPMENT OPERATORS: GROUP 2…Full textPOWER EQUIPMENT OPERATORS: GROUP 2 AGGREGATE BIN, CMI AND SIMILAR TYPE CONCRETE SPREADS, CEMENT BIN, CHIPPING MACHINE AND CHIP SPREADER, COMPRESSORS (4 OR LESS), COMPRESSORS: (ANY SIZE, BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS, DUST COLLECTORS, GENERATORS, MECHANICAL HEATERS, PUMPS, WELDING MACHINES (FOUR OF ANY TYPE OR COMBINATION), CONCRETE MIXER (1/2 CU. YD. AND UNDER), FIREMAN, FORM TAMPER, FUEL TRUCK, HEATING BOILER (USED FOR TEMPRORY HEAT), JEEP TRENCHER, POWER HEATERMAN, POWER PLANT IN EXCESS OF 10 K.W., PUMP (4"" OR OVER), REVINIUS WIDENER, STEM CLEANER, STUMP CHIPPING MACHINE, WELDING MACHINE (1 MACHINE OVER 300 AMPS OR 2 OR 3 MACHINES REGARDLESS OF AMPS). NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $39.14 | $35.40 | $74.54 | Agreement |
POWER EQUIPMENT OPERATORS: GROUP 1…Full textPOWER EQUIPMENT OPERATORS: GROUP 1 AIR HOIST, ALL BOOM TYPE EQUIPMENT (100 FT. OR LESS), ALL PAN AND CARRY-ALLS, ARCHER HOIST, ASPHALT ROLLER ASPHALT SPREADER OR PAVER, AUTOMATIC FINE GRADE MACHINE (CMI AND SIMILAR TYPE), ARCHER HOIST, BACKHOE AND PULL HOE (TRACTOR MOUNTED AND RUBBER MOUNTED), BACK FILLING MACHINE, BELT PLACE (CMI AND SIMILAR), BENDING MACHINE (PIPE), BITUMINOUS SPREADER AND MIXER, BLACK TOP PLANT (AUTOMATED), BLACK TOP PLANT (NON-AUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACK MOUNTED), BLOWER FOR BURNING BRUSH, BOILER (WHEN USED FOR POWER), BOOM TRUCKS, BORING MACHINE, BULLDOZER, CABLEWAY CAGE HOIST, CAISSON AUGER, CENTRAL MIX PLANT (AND ALL CONCRETE BATCHING PLANTS), CHERRY PICKER (OVER 5 TONS), CHERRY PICKER (UNDER 5 TONS), CHIPPING MACHINE AND CHIP SPREADER, CONCRETE CURB AND GUTTER MACHINES, CONCRETE CURING MACHINE, CONCRETE MIXER (OVER 1/2 CU. YD.) CONCRETE PAVEMENT SPREADERS AND FINISHERS, CONCRETE PAVER, CONCRETE PUMP, CONCRETE SAW (SELF-PROPELLED), CONVEYOR, CORE DRILL, CRANE, CRUSHER, DERRICK OPERATOR, DRAGLINE, DREDGE, DRILL RIG (TRACTOR MOUNTED), DUAL DRUM PAVER, ELECTRIC PUMP USED IN CONJUNCTION WITH WELL POINT SYSTEMS, ELEVATING GRADER SELF- PROPELLED OR TOWED), ELEVATOR EXCAVATOR (ALL PURPOSE, HYDRAULCALLY OPERATED) FARM TRACTOR WITH ACCESSORIES, FINE GRADE MACHINE, FORKLIFT, FRONT END LOADER, GENERATOR (10 OUTLETS OR MORE), GRADALL, GRADER, GROUT OR GUNITE MACHINE, HEAD TOWER, HOIST-ONE DRUM, HOISTING ENGINE, HYDRAULIC BOOM, HYDRAULIC HAMMER, (SELF PROPELLED), HYDRAULIC PIPE JACK MACHINE (OR SIMILAR TYPE MACHINE), HYDRAULIC SYSTEM PUMPS, HYDRO CRANE, HYDRO HAMMER (OR SIMILAR TYPE), INDUSTRIAL TRACTOR, JERSEY SPREADER, KOLMAN PLANT LOADER (AND SIMILAR TYPE LOADERS), LOCOMOTIVE, LUBRICATION TRUCK, MAINTENANCE ENGINEER, MAINTENANCE LUBRICATION UNIT OR TRUCK, MINE HOIST, MIXR FOR STABILIZED BASE (SELF-PROPELLED), MONORAIL, MOTORIZED HYDRAULIC PIN PULLER, MOTORIZED HYDRAULIC SEEDER MUCKING MACHINE, MULCHING MACHINE, MULTIPLE DRUM HOIST (MORE THAN 1 DRUM IN USE), OVERHEAD CRANE, PEINE CRANE (OR SIMILAR TYPE), PILE DRIVER, PLANT ENGINEER, PNEUMATIC MIXER, POST HOLE DIGGER, POWER BOOM, PUMP CRETE, PUSH OR SNATCH CAT, QUARRY MASTER OR EQUIVALENT ROAD WIDENER, ROCK BIT SHARPENER (ALL TYPES), ROLLER (ALL), ROLLING MACHIN (PIPE), ROTOMILL, SCOOPMOBILE, SHOVEL, SIDE BOOM, SKIMMER, SLIP FORM PAVER (CMI AND SIMILAR TYPE, FIRST AND SECOND OPERATOR), SNORKEL, STRATO-TOWER, STUMP CHIPPING MACHINE, TIRE TRUCK AND REPAIR, TOWED ROLLER, TRACTOR DRAWN BELT TYPE GRADER/LOADER, TRACTOR SHOVEL, TRACTOR WITH TOWED ACCESSORIES, TRACTORS (WHEN USING WINCH POWER), TRACTORS, TRENCHER, TRUCK CRANE, TUNNEL SHOVEL, TUBE FINISHER (CMI AND SIMILAR TYPE), VIBRATORY COMPACTOR, VIBRO TAMP, WELL DRILLING MACHINE, WELL POINT, WINCH, WINCH TRUCK WITH ""A"" FRAME. NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $44.23 | $35.40 | $79.63 | Agreement |
| IRON0006-015 · Ironworkers agreement, July 1, 2024 | ||||
| IRONWORKER: SHEETER | $35.49 | $32.30 | $67.79 | Agreement |
| IRONWORKER | $35.49 | $32.30 | $67.79 | Agreement |
| LABO0210-001 · Laborers agreement, July 1, 2023 | ||||
| LABORERS: GROUP 6 HAZARDOUS WASTE WORKER | $32.43 | $28.25 | $60.68 | Agreement |
| LABORERS: GROUP 5 ASBESTOS REMOVAL, DELEADER | $31.93 | $28.25 | $60.18 | Agreement |
| LABORERS: GROUP 4 STONE CUTTER, CURB SETTER AND FLAG LAYER | $31.18 | $28.25 | $59.43 | Agreement |
LABORERS: GROUP 3…Full textLABORERS: GROUP 3 WORKER ON ANY SWING SCAFFOLD, BLASTER, PLUMBING LABORER, WAGON DRILLER, BOTTOM (CAISSON OR COFFERDAM), LASER SETTER, ASPHALT RAKERS, ASPHALT SCREED MAN | $30.71 | $28.25 | $58.96 | Agreement |
LABORERS: GROUP 2…Full textLABORERS: GROUP 2 MORTAR MIXER, ASPHALT SMOOTHERS, PNEUMATIC GAS ELECTRIC TOOL OPERATOR INCLUDING ALL FORMS OF BUSTERS, JACKHAMMERS, AND CHIPPING GUNS OVER 8' IN DEPTH | $30.60 | $28.25 | $58.85 | Agreement |
LABORERS: GROUP 1…Full textLABORERS: GROUP 1 BASIC, BOAT SAFETY MAN, FLAGMAN, TOOL ROOM MAN, NURSERYMAN DEMOLITION WORKER; TOP MAN; WRECKER; IBC BARRIERS EXCEPT ON STRUCTURERS; GUARD RAIL. ASPHALT SHOVELERS, FOUNDATION LABORERS OVER 8' IN DEPTH, HOD CARRIERS, PLASTER TENDER, PLASTER SCAFFOLD BUILDER, PNEUMATIC GAS, ELECTRIC OPERATOR, INCLUDING ALL FORMS OF BUSTERS, JACKHAMMERS, CHIPPING GUNS AND STEEL BURNERS | $30.43 | $28.25 | $58.68 | Agreement |
| PAIN0004-007 · Painters and Allied Trades agreement, May 1, 2025 | ||||
| GLAZIER | $34.68 | $27.64 | $62.32 | Agreement |
| PAIN0004-018 · Painters and Allied Trades agreement, May 1, 2017 | ||||
| PAINTERS: TAPERS ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK)) | $26.45 | $23.69 | $50.14 | Agreement |
PAINTERS: SPRAYING…Full textPAINTERS: SPRAYING, PAPERHANGERS, SAND BLASTING, SWINGING SCAFFOLD ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK)) | $25.95 | $23.69 | $49.64 | Agreement |
| PAINTERS: LEAD ABATEMENT ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK)) | $25.95 | $23.69 | $49.64 | Agreement |
| PAINTERS ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK)) | $25.95 | $23.69 | $49.64 | Agreement |
| PAIN0004-024 · Painters and Allied Trades agreement, May 1, 2025 | ||||
PAINTERS: TAPING/DRYWALL…Full textPAINTERS: TAPING/DRYWALL (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK)) | $34.00 | $28.51 | $62.51 | Agreement |
PAINTERS: SPRAY, SANDBLASTING…Full textPAINTERS: SPRAY, SANDBLASTING, SWING SCAFFOLD OR ANY HANGED RIGGING PLATFORM, EPOXY (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK)) | $33.00 | $28.21 | $61.21 | Agreement |
PAINTERS: BRUSH & ROLL…Full textPAINTERS: BRUSH & ROLL (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK)) | $33.00 | $28.21 | $61.21 | Agreement |
| PLAS0009-001 · Plasterers and Cement Masons agreement, April 1, 2025 | ||||
| PLASTERER | $33.05 | $25.09 | $58.14 | Agreement |
| PLAS0111-001 · Plasterers and Cement Masons agreement, July 1, 2025 | ||||
| CEMENT FINISHER | $33.65 | $31.47 | $65.12 | Agreement |
| PLUM0022-008 · Plumbers and Pipefitters agreement, April 29, 2024 | ||||
| PIPEFITTER: (ZONE 1) ERIE- ALL TOWNSHIPS IN THE COUNTY | $42.20 | $29.80 | $72.00 | Agreement |
| ROOF0074-001 · Roofers agreement, June 1, 2024 | ||||
| ROOFERS: SLATE & TILE (ERIE COUNTY) | $35.11 | $26.03 | $61.14 | Agreement |
| ROOFERS: COMPOSITION (ERIE COUNTY) | $34.96 | $26.03 | $60.99 | Agreement |
| SHEE0071-001 · Sheet Metal Workers agreement, May 27, 2024 | ||||
| SHEET METAL WORKER (ERIE COUNTY) | $39.50 | $29.18 | $68.68 | Agreement |
| SUNY1999-001 · Survey of contractors in NY, June 18, 1999 | ||||
| SPRINKLER FITTER | $15.94 | $3.88 | $19.82 | Survey |
| TEAM0449-004 · Teamsters agreement, July 1, 2025 | ||||
TRUCK DRIVERS: INCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS…Full textTRUCK DRIVERS: INCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS (ERIE COUNTY) WORK ON A HAZARDOUS WASTE SITE THEN ADDITIONAL $2.00 PER HOUR. EUCLIDS ADD $0.25 TO JOURNEYMAN RATE FOOTNOTE: A. HEALTH AND WELFARE $438.61 PER WEEK B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND AFTER THE HOLIDAY | $47.18 | $15.09 | $62.27 | Agreement |
| TEAM0449-007 · Teamsters agreement, June 1, 2025 | ||||
| TRUCK DRIVERS:: DUMP TRUCK ONLY, EXCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND AFTER THE HOLIDAY | $32.00 | $0.00 | $32.00 | Agreement |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on NY20260050?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator