This sheet sets 96 classifications for building work in Erie County, New York. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $19.82 an hour (sprinkler fitter) to $100.83 (elevator mechanic). Your contract may lock an earlier modification.

What changed this year

First published January 2, 2026, this sheet is now on modification 1, and its rates have changed in 1 modification.

Latest change

May 18, 2026 · modification 1

Classification names reworded; 13 fringe formulas changed among the 53 lines we could match

  • Electrician line construction: 5 fringe formulas changed
  • Communications system: 4 fringe formulas changed
  • Truck drivers: 2 fringe formulas changed
  • Electrician line construction telephone: 1 fringe formula changed
  • Elevator mechanic: 1 fringe formula changed

SAM.gov reworded this sheet’s classification names in this modification, so not every line can be matched to the one before. Only lines matched with certainty are compared here; nothing is guessed. If your trade is not listed, compare it against your contract’s copy.

Every line that changed (13)
ClassificationWasNowChange
COMMUNICATIONS SYSTEM (SOUND WIREMAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION…$44.50 + 36.05+a$44.50 + $36.05changed
COMMUNICATIONS SYSTEM (MASTER TECHNICIAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLA…$44.50 + 36.05+a$44.50 + $36.05changed
COMMUNICATIONS SYSTEM (INSTALLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MA…$22.90 + 21.38+a$22.90 + $21.38changed
COMMUNICATIONS SYSTEM (CABLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINT…$14.20 + 14.02+a$14.20 + $14.02changed
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER O…$42.29 + 7%+27.70$42.29 + $30.66changed
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER O…$52.86 + 7%+31.90$52.86 + $35.60changed
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER O…$47.57 + 7%+27.70$47.57 + $31.03changed
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER O…$42.29 + 7%+27.70$42.29 + $30.66changed
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER O…$31.72 + 7%+27.65$31.72 + $29.87changed
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLI…$40.81 + 3%+5.77$40.81 + $6.99changed
ELEVATOR MECHANIC$62.39 + 38.435+a+b$62.39 + $38.44changed
TRUCK DRIVERS: INCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS (ERIE COUNTY) WORK…$47.18 + 15.09+b$47.18 + $15.09changed
TRUCK DRIVERS:: DUMP TRUCK ONLY, EXCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS$32.00 + a$32.00 + $0.00changed

Compared line by line from each modification as published on SAM.gov. A line we could not pair with certainty is left out rather than guessed.

Rates by classification

These are the rates in modification 1 as published on SAM.gov. The determination and modification written into your contract are the ones that bind you; check that number before relying on this table. Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from and its year; a survey year long past means the rate has not been surveyed since. A marker means the group changed in this modification. In the Since column, a dash means SAM.gov reworded the line during the year and it cannot be matched to the first publication with certainty. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSince Jan 2Source
BOIL0007-001 · Boilermakers agreement, January 1, 2025
BOILERMAKER$39.35$33.18$72.53no changeAgreement, 2025
BRNY0045-004 · Bricklayers agreement, July 1, 2021
CEMENT MASON$32.53$22.10$54.63no changeAgreement, 2021
MARBLE SETTER$36.85$30.80$67.65no changeAgreement, 2021
TILE FINISHER$34.71$17.54$52.25no changeAgreement, 2021
TERRAZZO FINISHER$34.71$17.54$52.25no changeAgreement, 2021
TILESETTER & TERRAZZO WORKER$38.85$32.20$71.05no changeAgreement, 2021
BRICKLAYER$39.44$32.11$71.55no changeAgreement, 2021
BRNY0045-004 · Bricklayers agreement, July 1, 2023
CEMENT MASON$32.53$22.10$54.63—Agreement, 2023
MARBLE SETTER$36.85$30.80$67.65—Agreement, 2023
TILE FINISHER$34.71$17.54$52.25—Agreement, 2023
TERRAZZO FINISHER$34.71$17.54$52.25—Agreement, 2023
TILESETTER & TERRAZZO WORKER$38.85$32.20$71.05—Agreement, 2023
BRICKLAYER$39.44$32.11$71.55—Agreement, 2023
BRNY0045-004 · Bricklayers agreement, July 1, 2024
CEMENT MASON$32.53$22.10$54.63—Agreement, 2024
MARBLE SETTER$36.85$30.80$67.65—Agreement, 2024
TILE FINISHER$34.71$17.54$52.25—Agreement, 2024
TERRAZZO FINISHER$34.71$17.54$52.25—Agreement, 2024
TILESETTER & TERRAZZO WORKER$38.85$32.20$71.05—Agreement, 2024
BRICKLAYER$39.44$32.11$71.55—Agreement, 2024
BRNY0045-004 · Bricklayers agreement, July 1, 2025
CEMENT MASON$32.53$22.10$54.63—Agreement, 2025
MARBLE SETTER$36.85$30.80$67.65—Agreement, 2025
TILE FINISHER$34.71$17.54$52.25—Agreement, 2025
TERRAZZO FINISHER$34.71$17.54$52.25—Agreement, 2025
TILESETTER & TERRAZZO WORKER$38.85$32.20$71.05—Agreement, 2025
BRICKLAYER$39.44$32.11$71.55—Agreement, 2025
CARP0276-014 · Carpenters agreement, July 1, 2024
CARPENTER$34.73$28.61$63.34no changeAgreement, 2024
ELEC0041-003 · Electrical Workers (IBEW) agreement, April 1, 2014
CABLE SPLICER$36.73$23.39$60.12—Agreement, 2014
ELECTRICIAN$44.50$36.06$80.56no changeAgreement, 2014
ELEC0041-003 · Electrical Workers (IBEW) agreement, May 26, 2025
CABLE SPLICER$36.73$23.39$60.12—Agreement, 2025
ELECTRICIAN$44.50$36.06$80.56—Agreement, 2025
ELEC0041-004 · Electrical Workers (IBEW) agreement, May 26, 2025
COMMUNICATIONS SYSTEM…
Full text

COMMUNICATIONS SYSTEM (SOUND WIREMAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK

$44.50$36.05$80.55changedAgreement, 2025
COMMUNICATIONS SYSTEM…
Full text

COMMUNICATIONS SYSTEM (MASTER TECHNICIAN) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK

$44.50$36.05$80.55changedAgreement, 2025
COMMUNICATIONS SYSTEM…
Full text

COMMUNICATIONS SYSTEM (INSTALLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK

$22.90$21.38$44.28changedAgreement, 2025
COMMUNICATIONS SYSTEM…
Full text

COMMUNICATIONS SYSTEM (CABLER) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK

$14.20$14.02$28.22changedAgreement, 2025
ELEC1249-003 · Electrical Workers (IBEW) agreement, May 5, 2025
ELECTRICIAN LINE CONSTRUCTION…
Full text

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC

FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

$42.29$30.66$72.95changedAgreement, 2025
ELECTRICIAN LINE CONSTRUCTION…
Full text

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN

FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

$52.86$35.60$88.46changedAgreement, 2025
ELECTRICIAN LINE CONSTRUCTION…
Full text

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT)

FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

$47.57$31.03$78.60changedAgreement, 2025
ELECTRICIAN LINE CONSTRUCTION…
Full text

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER)

FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

$42.29$30.66$72.95changedAgreement, 2025
ELECTRICIAN LINE CONSTRUCTION…
Full text

ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN

FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY

$31.72$29.87$61.59changedAgreement, 2025
ELEC1249-004 · Electrical Workers (IBEW) agreement, May 5, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)

$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:)$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins

$61.56$36.21$97.77—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:)$61.56$36.21$97.77—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:)

$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat

$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab

$55.40$31.78$87.18—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:)$55.40$31.78$87.18—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

$55.40$31.78$87.18—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)

$35.34$30.12$65.46—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:)$35.34$30.12$65.46—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :)

$35.34$30.12$65.46—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION…
Full text

ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation)

$64.59$42.92$107.51—Agreement, 2025
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:)$63.14$33.82$96.96—Agreement, 2025
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES…
Full text

ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT)

FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY

$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER

FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY

$49.25$31.15$80.40—Agreement, 2025
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK…
Full text

ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN

FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY

$61.56$36.21$97.77—Agreement, 2025
ELEC1249-008 · Electrical Workers (IBEW) agreement, January 1, 2025
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…
Full text

ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY

$38.73$6.93$45.66—Agreement, 2025
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…
Full text

ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY

$20.53$6.39$26.92—Agreement, 2025
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…
Full text

ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY

$40.81$6.99$47.80changedAgreement, 2025
ELEV0014-001 · Elevator Constructors agreement, January 1, 2025
ELEVATOR MECHANIC

FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY

$62.39$38.44$100.83changedAgreement, 2025
ENGI0017-001 · Operating Engineers agreement, July 1, 2025
POWER EQUIPMENT OPERATORS: GROUP 8 MASTER MEACHANIC

NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

$45.47$35.40$80.87no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 7 ANY TOWER CRANES

NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

$49.98$35.40$85.38no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 6 ANY CRANE 400 TONS AND OVER

NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

$49.48$35.40$84.88no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 5 ANY CRANE 200 - 399 TONS

NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

$48.98$35.40$84.38no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 4 ANY CRANE 61 - 199 TONS

NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

$48.48$35.40$83.88no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 3 ANY CRANE UP TO 60 TONS

NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

$47.48$35.40$82.88no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 2…
Full text

POWER EQUIPMENT OPERATORS: GROUP 2 AGGREGATE BIN, CMI AND SIMILAR TYPE CONCRETE SPREADS, CEMENT BIN, CHIPPING MACHINE AND CHIP SPREADER, COMPRESSORS (4 OR LESS), COMPRESSORS: (ANY SIZE, BUT SUBJECT TO OTHER PROVISIONS FOR COMPRESSORS, DUST COLLECTORS, GENERATORS, MECHANICAL HEATERS, PUMPS, WELDING MACHINES (FOUR OF ANY TYPE OR COMBINATION), CONCRETE MIXER (1/2 CU. YD. AND UNDER), FIREMAN, FORM TAMPER, FUEL TRUCK, HEATING BOILER (USED FOR TEMPRORY HEAT), JEEP TRENCHER, POWER HEATERMAN, POWER PLANT IN EXCESS OF 10 K.W., PUMP (4"" OR OVER), REVINIUS WIDENER, STEM CLEANER, STUMP CHIPPING MACHINE, WELDING MACHINE (1 MACHINE OVER 300 AMPS OR 2 OR 3 MACHINES REGARDLESS OF AMPS).

NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

$39.14$35.40$74.54no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 1…
Full text

POWER EQUIPMENT OPERATORS: GROUP 1 AIR HOIST, ALL BOOM TYPE EQUIPMENT (100 FT. OR LESS), ALL PAN AND CARRY-ALLS, ARCHER HOIST, ASPHALT ROLLER ASPHALT SPREADER OR PAVER, AUTOMATIC FINE GRADE MACHINE (CMI AND SIMILAR TYPE), ARCHER HOIST, BACKHOE AND PULL HOE (TRACTOR MOUNTED AND RUBBER MOUNTED), BACK FILLING MACHINE, BELT PLACE (CMI AND SIMILAR), BENDING MACHINE (PIPE), BITUMINOUS SPREADER AND MIXER, BLACK TOP PLANT (AUTOMATED), BLACK TOP PLANT (NON-AUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACK MOUNTED), BLOWER FOR BURNING BRUSH, BOILER (WHEN USED FOR POWER), BOOM TRUCKS, BORING MACHINE, BULLDOZER, CABLEWAY CAGE HOIST, CAISSON AUGER, CENTRAL MIX PLANT (AND ALL CONCRETE BATCHING PLANTS), CHERRY PICKER (OVER 5 TONS), CHERRY PICKER (UNDER 5 TONS), CHIPPING MACHINE AND CHIP SPREADER, CONCRETE CURB AND GUTTER MACHINES, CONCRETE CURING MACHINE, CONCRETE MIXER (OVER 1/2 CU. YD.) CONCRETE PAVEMENT SPREADERS AND FINISHERS, CONCRETE PAVER, CONCRETE PUMP, CONCRETE SAW (SELF-PROPELLED), CONVEYOR, CORE DRILL, CRANE, CRUSHER, DERRICK OPERATOR, DRAGLINE, DREDGE, DRILL RIG (TRACTOR MOUNTED), DUAL DRUM PAVER, ELECTRIC PUMP USED IN CONJUNCTION WITH WELL POINT SYSTEMS, ELEVATING GRADER SELF- PROPELLED OR TOWED), ELEVATOR EXCAVATOR (ALL PURPOSE, HYDRAULCALLY OPERATED) FARM TRACTOR WITH ACCESSORIES, FINE GRADE MACHINE, FORKLIFT, FRONT END LOADER, GENERATOR (10 OUTLETS OR MORE), GRADALL, GRADER, GROUT OR GUNITE MACHINE, HEAD TOWER, HOIST-ONE DRUM, HOISTING ENGINE, HYDRAULIC BOOM, HYDRAULIC HAMMER, (SELF PROPELLED), HYDRAULIC PIPE JACK MACHINE (OR SIMILAR TYPE MACHINE), HYDRAULIC SYSTEM PUMPS, HYDRO CRANE, HYDRO HAMMER (OR SIMILAR TYPE), INDUSTRIAL TRACTOR, JERSEY SPREADER, KOLMAN PLANT LOADER (AND SIMILAR TYPE LOADERS), LOCOMOTIVE, LUBRICATION TRUCK, MAINTENANCE ENGINEER, MAINTENANCE LUBRICATION UNIT OR TRUCK, MINE HOIST, MIXR FOR STABILIZED BASE (SELF-PROPELLED), MONORAIL, MOTORIZED HYDRAULIC PIN PULLER, MOTORIZED HYDRAULIC SEEDER MUCKING MACHINE, MULCHING MACHINE, MULTIPLE DRUM HOIST (MORE THAN 1 DRUM IN USE), OVERHEAD CRANE, PEINE CRANE (OR SIMILAR TYPE), PILE DRIVER, PLANT ENGINEER, PNEUMATIC MIXER, POST HOLE DIGGER, POWER BOOM, PUMP CRETE, PUSH OR SNATCH CAT, QUARRY MASTER OR EQUIVALENT ROAD WIDENER, ROCK BIT SHARPENER (ALL TYPES), ROLLER (ALL), ROLLING MACHIN (PIPE), ROTOMILL, SCOOPMOBILE, SHOVEL, SIDE BOOM, SKIMMER, SLIP FORM PAVER (CMI AND SIMILAR TYPE, FIRST AND SECOND OPERATOR), SNORKEL, STRATO-TOWER, STUMP CHIPPING MACHINE, TIRE TRUCK AND REPAIR, TOWED ROLLER, TRACTOR DRAWN BELT TYPE GRADER/LOADER, TRACTOR SHOVEL, TRACTOR WITH TOWED ACCESSORIES, TRACTORS (WHEN USING WINCH POWER), TRACTORS, TRENCHER, TRUCK CRANE, TUNNEL SHOVEL, TUBE FINISHER (CMI AND SIMILAR TYPE), VIBRATORY COMPACTOR, VIBRO TAMP, WELL DRILLING MACHINE, WELL POINT, WINCH, WINCH TRUCK WITH ""A"" FRAME.

NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY

$44.23$35.40$79.63no changeAgreement, 2025
IRON0006-015 · Ironworkers agreement, July 1, 2024
IRONWORKER: SHEETER$35.49$32.30$67.79no changeAgreement, 2024
IRONWORKER$35.49$32.30$67.79no changeAgreement, 2024
LABO0210-001 · Laborers agreement, July 1, 2023
LABORERS: GROUP 6 HAZARDOUS WASTE WORKER$32.43$28.25$60.68no changeAgreement, 2023
LABORERS: GROUP 5 ASBESTOS REMOVAL, DELEADER$31.93$28.25$60.18no changeAgreement, 2023
LABORERS: GROUP 4 STONE CUTTER, CURB SETTER AND FLAG LAYER$31.18$28.25$59.43no changeAgreement, 2023
LABORERS: GROUP 3…
Full text

LABORERS: GROUP 3 WORKER ON ANY SWING SCAFFOLD, BLASTER, PLUMBING LABORER, WAGON DRILLER, BOTTOM (CAISSON OR COFFERDAM), LASER SETTER, ASPHALT RAKERS, ASPHALT SCREED MAN

$30.71$28.25$58.96no changeAgreement, 2023
LABORERS: GROUP 2…
Full text

LABORERS: GROUP 2 MORTAR MIXER, ASPHALT SMOOTHERS, PNEUMATIC GAS ELECTRIC TOOL OPERATOR INCLUDING ALL FORMS OF BUSTERS, JACKHAMMERS, AND CHIPPING GUNS OVER 8' IN DEPTH

$30.60$28.25$58.85no changeAgreement, 2023
LABORERS: GROUP 1…
Full text

LABORERS: GROUP 1 BASIC, BOAT SAFETY MAN, FLAGMAN, TOOL ROOM MAN, NURSERYMAN DEMOLITION WORKER; TOP MAN; WRECKER; IBC BARRIERS EXCEPT ON STRUCTURERS; GUARD RAIL. ASPHALT SHOVELERS, FOUNDATION LABORERS OVER 8' IN DEPTH, HOD CARRIERS, PLASTER TENDER, PLASTER SCAFFOLD BUILDER, PNEUMATIC GAS, ELECTRIC OPERATOR, INCLUDING ALL FORMS OF BUSTERS, JACKHAMMERS, CHIPPING GUNS AND STEEL BURNERS

$30.43$28.25$58.68no changeAgreement, 2023
PAIN0004-007 · Painters and Allied Trades agreement, May 1, 2025
GLAZIER$34.68$27.64$62.32no changeAgreement, 2025
PAIN0004-018 · Painters and Allied Trades agreement, May 1, 2017
PAINTERS: TAPERS ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))$26.45$23.69$50.14no changeAgreement, 2017
PAINTERS: SPRAYING…
Full text

PAINTERS: SPRAYING, PAPERHANGERS, SAND BLASTING, SWINGING SCAFFOLD ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

$25.95$23.69$49.64no changeAgreement, 2017
PAINTERS: LEAD ABATEMENT ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))$25.95$23.69$49.64no changeAgreement, 2017
PAINTERS ((AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))$25.95$23.69$49.64no changeAgreement, 2017
PAIN0004-024 · Painters and Allied Trades agreement, May 1, 2025
PAINTERS: TAPING/DRYWALL…
Full text

PAINTERS: TAPING/DRYWALL (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

$34.00$28.51$62.51no changeAgreement, 2025
PAINTERS: SPRAY, SANDBLASTING…
Full text

PAINTERS: SPRAY, SANDBLASTING, SWING SCAFFOLD OR ANY HANGED RIGGING PLATFORM, EPOXY (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

$33.00$28.21$61.21no changeAgreement, 2025
PAINTERS: BRUSH & ROLL…
Full text

PAINTERS: BRUSH & ROLL (ENTIRE COUNTY, (EXCLUDING AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK))

$33.00$28.21$61.21no changeAgreement, 2025
PLAS0009-001 · Plasterers and Cement Masons agreement, April 1, 2025
PLASTERER$33.05$25.09$58.14no changeAgreement, 2025
PLAS0111-001 · Plasterers and Cement Masons agreement, July 1, 2025
CEMENT FINISHER$33.65$31.47$65.12no changeAgreement, 2025
PLUM0022-008 · Plumbers and Pipefitters agreement, April 29, 2024
PIPEFITTER: (ZONE 1) ERIE- ALL TOWNSHIPS IN THE COUNTY$42.20$29.80$72.00no changeAgreement, 2024
ROOF0074-001 · Roofers agreement, June 1, 2024
ROOFERS: SLATE & TILE (ERIE COUNTY)$35.11$26.03$61.14no changeAgreement, 2024
ROOFERS: COMPOSITION (ERIE COUNTY)$34.96$26.03$60.99no changeAgreement, 2024
SHEE0071-001 · Sheet Metal Workers agreement, May 27, 2024
SHEET METAL WORKER (ERIE COUNTY)$39.50$29.18$68.68no changeAgreement, 2024
SUNY1999-001 · Survey of contractors in NY, June 18, 1999
SPRINKLER FITTER$15.94$3.88$19.82no changeSurvey, 1999
TEAM0449-004 · Teamsters agreement, July 1, 2025
TRUCK DRIVERS: INCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS…
Full text

TRUCK DRIVERS: INCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS (ERIE COUNTY) WORK ON A HAZARDOUS WASTE SITE THEN ADDITIONAL $2.00 PER HOUR. EUCLIDS ADD $0.25 TO JOURNEYMAN RATE

FOOTNOTE: A. HEALTH AND WELFARE $438.61 PER WEEK B. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND AFTER THE HOLIDAY

$47.18$15.09$62.27changedAgreement, 2025
TEAM0449-007 · Teamsters agreement, June 1, 2025
TRUCK DRIVERS:: DUMP TRUCK ONLY, EXCLUDES SINGLE AXLE DUMP AND OFF-HIGHWAY DUMP TRUCKS

FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND AFTER THE HOLIDAY

$32.00$0.00$32.00changedAgreement, 2025

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on NY20260050?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator

Put these rates on a certified payroll.

Start here and NY20260050 is already filled in when you set up the job. CertifiedHours loads this sheet, checks every line against it as you type hours, and prints the WH-347. Free for one payroll a month.

Start a payroll on this sheet

On this sheet

  • 96 classifications in 27 rate groups
  • 26 from agreements, 1 from surveys
  • Counties: Erie