Prevailing wage rates · New York · Wage determination
Prevailing wage rates: Allegany, Cattaraugus, Cortland and 6 more counties, New York
Heavy construction · NY20260048 modification 1, published May 18, 2026
The short answer
This sheet sets 56 classifications for heavy work in Allegany, Cattaraugus, Cortland and 6 more counties, New York. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $23.34 an hour (laborers: (rakers)) to $107.51 (electrician, line construction). Your contract may lock an earlier modification.
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| ELEC0041-005 · Electrical Workers (IBEW) agreement, April 1, 2014 | ||||
Group definitions, zones and premiums for ELEC0041-005CABLE SPLICER (CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MANSFIELD, NEW ALBION, OTTO, PERRYSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD)).$ 36.73 23.39 ELECTRICIAN (CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MANSFIELD, NEW ALBION, OTTO, PERRYSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD)).$ 44.50 36.06 | ||||
| ELEC0041-005 · Electrical Workers (IBEW) agreement, May 26, 2025 | ||||
Group definitions, zones and premiums for ELEC0041-005CABLE SPLICER (CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MANSFIELD, NEW ALBION, OTTO, PERRYSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD)).$ 36.73 23.39 ELECTRICIAN (CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MANSFIELD, NEW ALBION, OTTO, PERRYSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD)).$ 44.50 36.06 | ||||
| ELEC0041-006 · Electrical Workers (IBEW) agreement, May 26, 2025 | ||||
COMMUNICATIONS SYSTEM…Full textCOMMUNICATIONS SYSTEM, SOUND WIREMAN (CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, THE DAY AFTER THANKSGIVING, CHRISTMAS DAY | $44.50 | $36.05 | $80.55 | Agreement |
COMMUNICATIONS SYSTEM…Full textCOMMUNICATIONS SYSTEM, MASTER TECHNICIAN (CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, THE DAY AFTER THANKSGIVING, CHRISTMAS DAY | $44.50 | $36.05 | $80.55 | Agreement |
COMMUNICATIONS SYSTEM…Full textCOMMUNICATIONS SYSTEM, INSTALLER (CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, THE DAY AFTER THANKSGIVING, CHRISTMAS DAY | $22.90 | $21.38 | $44.28 | Agreement |
COMMUNICATIONS SYSTEM…Full textCOMMUNICATIONS SYSTEM (CATTARAUGUS (TOWNSHIPS OF ASHFORD, EAST OTTO, ELLICOTTVILLE, FARMERSVILLE FREEDOM, FRANKLINVILLE, LYNDON, MACHIAS, MASNFIELD, NEW ALBION, OTTO, PERRSBURG, PERSIA AND YORKSHIRE) WYOMING (TOWNSHIPS OF ARCADE, ATTICA, BENNINGTON, EAGLE, JAVA, ORANGEVILLE, SHELDON AND WETHERFIELD) WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES (VOICE, DATA AND VIDEO) INCLUDING OUTSIDE PLANT, TELEPHONE AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICES, PABX FIBER OPTIC CABLE AND EQUIPMENT, RAILROAD COMMUNICATIONS, MICRO WAVES, V-SAT, BYPASS, CATV, WAN (WIDE AREA NETWORKS); LAN (LOCAL AREA NETWORKS) AND ISDN (INTEGRATED SYSTEMS DIGITAL NETWORK). ALSO, INSTALLATION OF SOUND SYSTEMS, NURSES CALL SYSTEMS, INTERCOM SYSTEMS, STAFF REGISTRY/LOCATING/SIGNALING SYSTEMS, ANTENNA SYSTEMS AND ASSOCIATED DEVICES; INSTALLATION OF SECURITY SYSTEMS AND APPARATUS, AND CABLING FROM VDT'S TO COMPUTERS. THIS WORK DOES NOT APPLY TO NEW CONSTRUCTION, OR TO THE INSTALLATION OF RACEWAY SYSTEMS AND BOXES FOR THE ABOVE WORK. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, THE DAY AFTER THANKSGIVING, CHRISTMAS DAY | $14.20 | $14.02 | $28.22 | Agreement |
| ELEC0043-006 · Electrical Workers (IBEW) agreement, June 1, 2025 | ||||
| ELECTRICIAN (CORTLAND AND TOMPKINS COUNTIES) | $50.50 | $35.03 | $85.53 | Agreement |
| ELEC0086-003 · Electrical Workers (IBEW) agreement, May 26, 2025 | ||||
| ELECTRICIAN (WYOMING (REMAINDER OF COUNTY)) | $44.30 | $30.20 | $74.50 | Agreement |
| ELEC0106-001 · Electrical Workers (IBEW) agreement, January 1, 2014 | ||||
CABLE SPLICER (ALLEGANY…Full textCABLE SPLICER (ALLEGANY (TOWNSHIPS OF ALMA, BELFAST, BELMONT, BOLIVAR, CONEADEA, CENTERVILLE, CLARKSVILLE, CUBA, FRIENDSHIP, GENESEE, NEW HUDSON, RUSHFORD, SCIO AND WIRT CATTARAUGUS (REMAINDER OF COUNTY)) | $35.75 | $20.68 | $56.43 | Agreement |
ELECTRICIAN (ALLEGANY…Full textELECTRICIAN (ALLEGANY (TOWNSHIPS OF ALMA, BELFAST, BELMONT, BOLIVAR, CONEADEA, CENTERVILLE, CLARKSVILLE, CUBA, FRIENDSHIP, GENESEE, NEW HUDSON, RUSHFORD, SCIO AND WIRT CATTARAUGUS (REMAINDER OF COUNTY)) | $42.50 | $27.23 | $69.73 | Agreement |
| ELEC0106-001 · Electrical Workers (IBEW) agreement, January 1, 2024 | ||||
CABLE SPLICER (ALLEGANY…Full textCABLE SPLICER (ALLEGANY (TOWNSHIPS OF ALMA, BELFAST, BELMONT, BOLIVAR, CONEADEA, CENTERVILLE, CLARKSVILLE, CUBA, FRIENDSHIP, GENESEE, NEW HUDSON, RUSHFORD, SCIO AND WIRT CATTARAUGUS (REMAINDER OF COUNTY)) | $35.75 | $20.68 | $56.43 | Agreement |
ELECTRICIAN (ALLEGANY…Full textELECTRICIAN (ALLEGANY (TOWNSHIPS OF ALMA, BELFAST, BELMONT, BOLIVAR, CONEADEA, CENTERVILLE, CLARKSVILLE, CUBA, FRIENDSHIP, GENESEE, NEW HUDSON, RUSHFORD, SCIO AND WIRT CATTARAUGUS (REMAINDER OF COUNTY)) | $42.50 | $27.23 | $69.73 | Agreement |
| ELEC0139-002 · Electrical Workers (IBEW) agreement, June 1, 2025 | ||||
ELECTRICIAN (ALLEGANY…Full textELECTRICIAN (ALLEGANY (REMAINDER OF COUNTY), SCHUYLER (REMAINDER OF COUNTY) AND STEUBEN COUNTIES) | $43.40 | $31.72 | $75.12 | Agreement |
| ELEC0241-002 · Electrical Workers (IBEW) agreement, June 1, 2025 | ||||
ELECTRICIAN (SENECA…Full textELECTRICIAN (SENECA (TOWNSHIPS OF COVERT AND LODI) AND SCHUYLER (TOWNSHIPS OF CATHARINE, CAYUTA, HECTOR)) | $44.50 | $31.89 | $76.39 | Agreement |
| ELEC0840-003 · Electrical Workers (IBEW) agreement, June 1, 2025 | ||||
| ELECTRICIAN (SENECA (REMAINDER OF COUNTY) AND YATES COUNTY) | $45.00 | $31.12 | $76.12 | Agreement |
| ELEC1249-003 · Electrical Workers (IBEW) agreement, May 5, 2025 | ||||
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $42.29 | $30.66 | $72.95 | Agreement |
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $52.86 | $35.60 | $88.46 | Agreement |
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $47.57 | $31.03 | $78.60 | Agreement |
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $42.29 | $30.66 | $72.95 | Agreement |
ELECTRICIAN LINE CONSTRUCTION…Full textELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $31.72 | $29.87 | $61.59 | Agreement |
| ELEC1249-004 · Electrical Workers (IBEW) agreement, May 5, 2025 | ||||
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $49.25 | $31.15 | $80.40 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | $61.56 | $36.21 | $97.77 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | $61.56 | $36.21 | $97.77 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | $55.40 | $31.78 | $87.18 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | $55.40 | $31.78 | $87.18 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $55.40 | $31.78 | $87.18 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $35.34 | $30.12 | $65.46 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | $35.34 | $30.12 | $65.46 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $35.34 | $30.12 | $65.46 | Agreement |
ELECTRICIAN, LINE CONSTRUCTION…Full textELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $64.59 | $42.92 | $107.51 | Agreement |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | $63.14 | $33.82 | $96.96 | Agreement |
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES…Full textELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | $80.40 | Agreement |
| ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | $80.40 | Agreement |
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK…Full textELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $61.56 | $36.21 | $97.77 | Agreement |
| ELEC1249-008 · Electrical Workers (IBEW) agreement, January 1, 2025 | ||||
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…Full textELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $38.73 | $6.93 | $45.66 | Agreement |
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…Full textELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $20.53 | $6.39 | $26.92 | Agreement |
ELECTRICIAN LINE CONSTRUCTION TELEPHONE…Full textELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.81 | $6.99 | $47.80 | Agreement |
| ENGI0017-003 · Operating Engineers agreement, July 1, 2025 | ||||
| POWER EQUIPMENT OPERATORS:: PAVERS (CATTARAUGUS AND WYOMING COUNTIES) A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $47.39 | $36.89 | $84.28 | Agreement |
| ENGI0158-025 · Operating Engineers agreement, July 1, 2018 | ||||
| POWER EQUIPMENT OPERATORS: PAVER (ALLEGANY, SCHUYLER, STEUBEN AND YATES COUNTIES) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY PROVIDED THE EMPLOYEE WORKS THE WORING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $40.80 | $28.25 | $69.05 | Agreement |
| ENGI0545-009 · Operating Engineers agreement, July 1, 2017 | ||||
| POWER EQUIPMENT OPERATOR: PAVERS (CORTLAND, SENECA AND TOMPKINS COUNTIES) A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY | $40.80 | $25.15 | $65.95 | Agreement |
| SUNY2000-002 · Survey of contractors in NY, January 11, 2000 | ||||
| TRUCK DRIVER: DUMP | $16.94 | $7.11 | $24.05 | Survey |
| POWER EQUIPMENT OPERATORS: BULLDOZERS | $22.28 | $11.79 | $34.07 | Survey |
| POWER EQUIPMENT OPERATORS: BACKHOES | $22.08 | $11.31 | $33.39 | Survey |
| POWER EQUIPMENT OPERATORS: (TRACTORS) | $20.57 | $10.95 | $31.52 | Survey |
| POWER EQUIPMENT OPERATORS: (ROLLERS) | $21.08 | $11.73 | $32.81 | Survey |
| POWER EQUIPMENT OPERATORS: (LOADERS) | $22.10 | $11.44 | $33.54 | Survey |
| POWER EQUIPMENT OPERATORS: (EXCAVATORS) | $22.63 | $12.14 | $34.77 | Survey |
| LABORERS: UNSKILLED | $17.20 | $6.63 | $23.83 | Survey |
| LABORERS: PIPELAYERS | $17.79 | $6.70 | $24.49 | Survey |
| LABORERS: (RAKERS) | $17.04 | $6.30 | $23.34 | Survey |
| CEMENT MASON/CONCRETE FINISHER | $17.45 | $7.90 | $25.35 | Survey |
| CARPENTER | $20.61 | $7.49 | $28.10 | Survey |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on NY20260048?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator