Prevailing wage rates · Nevada · Wage determination
Prevailing wage rates: Clark, Lincoln and Nye Counties, Nevada
Building, Heavy, Highway construction · NV20260002 modification 3, published June 1, 2026
The short answer
This sheet sets 52 classifications for building, heavy, highway work in Clark, Lincoln and Nye Counties, Nevada. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $51.81 an hour (tile finisher (zone pay) to $107.87 (elevator machanic (zone pay: zone a- las vegas. zone b-mercury $2.00. zone c- nttr $2.50.). Your contract may lock an earlier modification.
Scope
Department of Energy-Nevada National Security Site (NNSS). The Nevada National Security Sites, shall include work performed at the Nevada National Security Site (NNSS, formerly the Nevada Test Site), Remote Sensing Lab-Nellis (RSL-N), North Las Vegas Facility (NLV), Nevada Test and Training Range (NTTR), and other facilities under the cognizance of the Department of Energy (DOE), National Nuclear Security Administration Nevada Field Office (NNSA/NFO), located within the State of Nevada
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| ASBE0135-004 · Asbestos Workers and Heat & Frost Insulators agreement, October 1, 2025 | ||||
ASBESTOS/INSULATOR WORKER…Full textASBESTOS/INSULATOR WORKER: MECHANIC (ZONE PAY (0-19 MILES, LAS VEGAS): $0.00 ZONE PAY (20-45 MILES): $4.00 ZONE PAY (46-75 MILES, MERCURY): $5.00 ZONE PAY (76-150 MILES, FORWARD AREAS): $7.00 ZONE PAY (150+ MILES, NTTR): $8.00) | $67.19 | $19.88 | $87.07 | Agreement |
| BOIL0092-006 · Boilermakers agreement, October 1, 2024 | ||||
BOILERMAKER: BLACKSMITH ZONE PAY…Full textBOILERMAKER: BLACKSMITH ZONE PAY (ZONE A - LAS VEGAS $0.00 ZONE B - MERCURY & FORWARD AREAS $2.00 ZONE C - NTTR $2.50) | $44.31 | $28.96 | $73.27 | Agreement |
| BRNV0013-003 · Bricklayers agreement, October 1, 2025 | ||||
TILE FINISHER (ZONE PAY…Full textTILE FINISHER (ZONE PAY: ZONE 1: FREE ZONE 0-40 MILES $0.00 ZONE 2: 41-50 MILES - $3.75 ZONE 3: 51-70 MILES - $5.00 ZONE 4: OVER 71 MILES - $10.00) | $37.07 | $14.74 | $51.81 | Agreement |
TILE SETTER (ZONE PAY…Full textTILE SETTER (ZONE PAY: ZONE 1: FREE ZONE 0-40 MILES $0.00 ZONE 2: 41-50 MILES - $3.75 ZONE 3: 51-70 MILES - $5.00 ZONE 4: OVER 71 MILES - $10.00) | $49.74 | $18.79 | $68.53 | Agreement |
TERRAZZO WORKER/SETTER…Full textTERRAZZO WORKER/SETTER (ZONE PAY: ZONE 1: FREE ZONE 0-40 MILES $0.00 ZONE 2: 41-50 MILES - $3.75 ZONE 3: 51-70 MILES - $5.00 ZONE 4: OVER 71 MILES - $10.00) | $52.44 | $18.79 | $71.23 | Agreement |
MARBLE SETTER (ZONE PAY…Full textMARBLE SETTER (ZONE PAY: ZONE 1: FREE ZONE 0-40 MILES $0.00 ZONE 2: 41-50 MILES - $3.75 ZONE 3: 51-70 MILES - $5.00 ZONE 4: OVER 71 MILES - $10.00) | $52.44 | $18.79 | $71.23 | Agreement |
CAULKER (ZONE PAY: ZONE 1…Full textCAULKER (ZONE PAY: ZONE 1: FREE ZONE 0-40 MILES $0.00 ZONE 2: 41-50 MILES - $3.75 ZONE 3: 51-70 MILES - $5.00 ZONE 4: OVER 71 MILES - $10.00) | $52.79 | $20.89 | $73.68 | Agreement |
BRICKLAYER (ZONE PAY…Full textBRICKLAYER (ZONE PAY: ZONE 1: FREE ZONE 0-40 MILES $0.00 ZONE 2: 41-50 MILES - $3.75 ZONE 3: 51-70 MILES - $5.00 ZONE 4: OVER 71 MILES - $10.00) | $52.79 | $20.89 | $73.68 | Agreement |
| CARP1607-006 · Carpenters agreement, October 1, 2025 | ||||
MILLWRIGHT (ZONE PAY…Full textMILLWRIGHT (ZONE PAY: ZONE A: LAS VEGAS- FREE ZONE ZONE B: MERCURY, FORWARD & NTTR AREAS-$4.25) | $54.16 | $27.84 | $82.00 | Agreement |
| CARP1977-007 · Carpenters agreement, October 1, 2025 | ||||
CARPENTER (ZONE PAY…Full textCARPENTER (ZONE PAY: ZONE A: LAS VEGAS - FREE ZONE ZONE B: MERCURY, FORWARD & NTTR AREAS - $4.25) | $52.12 | $28.08 | $80.20 | Agreement |
| ELEC0357-005 · Electrical Workers (IBEW) agreement, October 1, 2025 | ||||
ELECTRICIAN: CABLE SPLICER…Full textELECTRICIAN: CABLE SPLICER (ZONE PAY ZONE A: 1-25 MILES - $0.00 ZONE B: 25-55 MILES - $7.00 ZONE C: OVER 55 MILES NNSS - $7.00 ZONE D: NTTR - $7.50) | $61.22 | $28.70 | $89.92 | Agreement |
ELECTRICIAN: COMMUNICATION TECHNICIAN ONLY…Full textELECTRICIAN: COMMUNICATION TECHNICIAN ONLY (ZONE PAY ZONE A: 1-25 MILES - $0.00 ZONE B: 25-55 MILES - $7.00 ZONE C: OVER 55 MILES NNSS - $7.00 ZONE D: NTTR - $7.50) | $64.37 | $28.81 | $93.18 | Agreement |
ELECTRICIAN (ZONE PAY ZONE A…Full textELECTRICIAN (ZONE PAY ZONE A: 1-25 MILES - $0.00 ZONE B: 25-55 MILES - $7.00 ZONE C: OVER 55 MILES NNSS - $7.00 ZONE D: NTTR - $7.50) | $64.37 | $28.81 | $93.18 | Agreement |
| ELEC0396-004 · Electrical Workers (IBEW) agreement, October 1, 2025 | ||||
| LINE CONSTRUCTION: LINEMAN (ZONE PAY -NNSS $5.00; NTTR $5.00) | $62.08 | $31.99 | $94.07 | Agreement |
| LINE CONSTRUCTION: HEAVY EQUIPMENT OPERATOR (ZONE PAY -NNSS $5.00; NTTR $5.00) | $62.08 | $31.99 | $94.07 | Agreement |
| LINE CONSTRUCTION: GROUNDMAN (ZONE PAY -NNSS $5.00; NTTR $5.00) | $49.66 | $31.50 | $81.16 | Agreement |
| ELEV0018-003 · Elevator Constructors agreement, January 1, 2025 | ||||
| ELEVATOR MACHANIC (ZONE PAY: ZONE A- LAS VEGAS. ZONE B-MERCURY $2.00. ZONE C- NTTR $2.50. FOOTNOTE: ADDITIONAL FRINGE BENEFITS TO BE PAID A: PAID VACATION: EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR 0 MONTHS TO 5 YEARS OF SERVICE. B: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY.) | $69.43 | $38.44 | $107.87 | Agreement |
| ENGI0012-023 · Operating Engineers agreement, October 1, 2025 | ||||
POWER EQUIPMENT OPERATOR GROUP 9…Full textPOWER EQUIPMENT OPERATOR GROUP 9 COMBINATION HEAVY DUTY REPAIRMAN AND WELDER; RUBBER-TIRED ANYTANDEM, MULTIPLE ENGINE EARTH-MOVING EQUIPMENT OPERATOR. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $58.74 | $34.00 | $92.74 | Agreement |
POWER EQUIPMENT OPERATOR GROUP 8…Full textPOWER EQUIPMENT OPERATOR GROUP 8 EXCAVATOR/TRACKHOE OR SIMILAR. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $58.92 | $34.00 | $92.92 | Agreement |
POWER EQUIPMENT OPERATOR GROUP 7…Full textPOWER EQUIPMENT OPERATOR GROUP 7 HEAVY DUTY REPAIRMAN; HEAVY DUTY WELDER; LIGHT DUTY REPAIRMAN (HYBRID/ALL ELECTRIC). (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $57.99 | $34.00 | $91.99 | Agreement |
POWER EQUIPMENT OPERATOR GROUP 6…Full textPOWER EQUIPMENT OPERATOR GROUP 6 BATCH PLANT OPERATOR; BULK PLANT OPERATOR; CONCRETE MIXER OPERATOR (PAVING); CONCRETE MOBILE MIXER OPERATOR; CONCRETE PUMP OR PUMPCRETE GUN OPERATOR; CRUSHING PLANT ENGINEER; DANDY DIGGER; DRILLER (ROTATRY/CORE); ELEVATING GRADE OPERATOR; FORKLIFT OPERATOR (OVER 5 TIMES); GRADE-ALL OPERATOR; HIGHLINE CABLEWAY OPERATOR; HOIST OPERATOR; JUMBO PIPE CARRIER; KOLMAN BELT LOADER, AND SIMILAR TYPE; LIFT SLAB MACHINE OPERATOR; LOADER OPERATOR; MACHINIST OPERATOR; MICRO TUNNEL SYSTEM (BELOW GROUND); MOTOR PATROL OPERATOR (ANY TYPE OR SIZE); OZZIE PADDER (OR SIMILAR TYPE); PNEUMATIC CONCRETE PLACING MACHINE OPERATOR (OR SIMILAR TYPE); PNEUMATIC PIPE RAMMING TOOL (AND SIMILAR TYPES); ROTOMIL OPERATOR; SEWER PLANT OPERATOR; SHOVEL, CRANE, BACKHOE, DRAGLINE, CLAMSHELL; DERRICK, DERRICK BARGE, PILE DRIVER, AND MUCKING MACHINE OPERATOR; SHUTTLE BUGGY; SKIPLOADER (WHEEL TYPE OVER 1 1/2 YARDS); SURFACE HEATER AND PLANER OPERATOR; TRACTOR LOADER OPERATOR, (CRAWLER TYPE- ALL TYPES AND SIZES); TRACTOR OPERATOR (WITH BOOM ATTACHMENTS); TRAVELING PIPE WRAPPING, CLEANING AND BENDING MACHINE OPERATOR; TRENCHING MACHINE OPERATOR (OVER 6-FT DEPTH); TUNNEL BORING MACHINE; WATER PULL (COMPACTION); WATER WELL DRILLER. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $57.74 | $34.00 | $91.74 | Agreement |
POWER EQUIPMENT OPERATOR GROUP 5…Full textPOWER EQUIPMENT OPERATOR GROUP 5 ASPHALT OR CONCRETE SPREADING MECHANICAL TAMPING OR FINISHING MACHINE OPERATOR-ROLLER (ALL TYPES AND SIZES), SOIL CEMENT, ASPHALT FINISH; ASPHALT PLANT ENGINEER; DECK ENGINE OPERATOOR; GRADE CHECKER; PAVEMENT-BREAKER OPERATOR; PNEUMATIC HEADING SHIELD- TUNNEL; ROAD OIL MIXING MACHINE OPEREATOR; FORKLIFT (UNDER (5) TONS); RUBBER TIRED, HEAVY DUTY EQUIPMENT OPERATOR; SKIPLOADER (WHEELTYPE, OVER 3-4 YARDS); SLIP FORM PUMP OPERATOR; TRACKOR OPERATOR, DRAG-TYPE SHOVEL, BULLDOZER, TAMPER, SCRAPER, AND PUSH TRACTOR. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $57.62 | $34.00 | $91.62 | Agreement |
POWER EQUIPMENT OPERATOR GROUP 4…Full textPOWER EQUIPMENT OPERATOR GROUP 4 ASPHALT PLANT FIREMAN; BORING MACHINE OPERATOR; BORING SYSTEMS ELECTRONIC TRACKING LOCATOR; BOXMAN OR MIXER BOX OPERATOR (CONCRETE OR ASPHALT PLANT); FISHING TOOL ENGINEER; HIGHLINE CABLEWAY SIGNALMAN; HORIZONTAL DIRECTIONAL DRILLING MACHINE; INSTRUMENTMAN; LOCOMOTIVE ENGINEER; MICO-TUNNELING (ABOVE GROUND TUNNEL); MINI EXCAVATOR OPERATOR; MUD PLANT OPERATOR; POWER SWEEPER OPERATOR; ROLLER OPERATOR (COMPACTING); SCREED OPERATOR; SEEDER; TRENCHING MACHINE OPERATOR, VACCUM TRUCK. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $56.52 | $34.00 | $90.52 | Agreement |
POWER EQUIPMENT OPERATOR GROUP 3…Full textPOWER EQUIPMENT OPERATOR GROUP 3 A-FRAME OR WINCH TRUCK OPERATOR; BOBCAT OR SIMILAR TYPE (SKIDSTEER); DERRICKMAN (ROTARY AND CORE); DINKY LOCOMOTIVE OR TUNNEL MOTOR OPERATOR; ELEVATOR HOIST OPERATOR; EQUIPMENT GREASER; FORD, FERGUSON OR SIMILAR TYPE (WITH DRAG-TYPE ATTACHMENTS); HYDRA-HAMMER OR SIMILAR TYPE EQUIPMENT; MATERIAL HOIST/OUTSIDE MANLIFT OPERATOR; POWER CONCRETE CURING MACHINE; PPOWER CONCRETE SAW OPERATOR (OR SIMILAR TYPE); POWER DRIVEN JUMBO FORM SETTER OPERATOR; RODMAN & CHAINMAN; ROSS CARRIER OPERATOR; SELF-CLIMBING SCAFFOLD (OR SIMILAR TYPE); SELF-PROPELLED TAR PIPELINING MACHINE OPERATOR; STATIONARY PIPE WRAPPING AND CLEANING MACHINE OPERATOR; STEAM AND WATER PLANT OPERATOR; TOWBLADE OPERATOR. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $55.03 | $34.00 | $89.03 | Agreement |
POWER EQUIPMENT OPERATOR GROUP 2…Full textPOWER EQUIPMENT OPERATOR GROUP 2 CONCRETE MIXER OPERATOR (SKID TYPE); CONVEYOR AND BELTMAN; FIREMAN; GENERATOR PUMP OR COMPRESSOR OPERATOR; GENERATOR, PUMP OR COMPRESSOR PLANT OPERATOR; HYDROSTATIC PUMP MOTORMAN (ROTARY AND CORE); PJU SIDEDUMP JACK; SCREENING AND CONVEYOR MACHINE (SIMILAR TYPE); SKIPLOADER (WHEELTYPE, FORD, FERGUSON, JEEP OR SIMILAR TYPE, 3/4 YARDS OR LESS, WITHOUT DRAG-TYPE ATTACHMENTS); TEMPORARY HEATING PLANT OPERATOR; TRUCK CRANE OILER. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $54.74 | $34.00 | $88.74 | Agreement |
POWER EQUIPMENT OPERATOR GROUP 1…Full textPOWER EQUIPMENT OPERATOR GROUP 1 AIR COMPRESSOR, PUMP OR GENERATOR OPERATOR; BLADE OPERATOR, ENGINEER-OILER AND SIGNALMAN; RAIL MOUNTED JLG; ROTARY DRILL TENDER (ROTARY AND CORE); STEAM CLEANER/PRESSURE WASHER; SWITCHMAN OR BRAKEMAN. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $53.79 | $34.00 | $87.79 | Agreement |
| IRON0118-014 · Ironworkers agreement, October 1, 2025 | ||||
| IRONWORKER (ZONE PAY- NNSS $5.50; NTTR $5.50) | $55.06 | $37.26 | $92.32 | Agreement |
| LABO0872-009 · Laborers agreement, October 1, 2025 | ||||
LABORER GROUP 3…Full textLABORER GROUP 3 ASBESTOS ABATEMENT; HAZARDOUS WASTE; LEAD ABATEMENT; MICROBIAL REMEDIATION WHICH INCLUDES HANTAVIRUS; PETROCHEMICAL HANDLER; RADIATION WORKER. (ZONE PAY: MERCURY, FORWARD AREAS & NTTR $5.00 FOOT NOTE: SAVINGS ACCOUNT OF $5.55 SHOULD BE ADDED TO THE BASE RATE) | $41.57 | $27.22 | $68.79 | Agreement |
LABORER GROUP 2…Full textLABORER GROUP 2 ASPHALT RAKER, IRONER, SPREADER; BUGGYMOBILE MAN; CEMENT DUMPER; CONCRETE CORE CUTTER, SAWMAN AND CEMENT GRINDING OPERATOR; CONCRETE CURER; CRIBBER OR SHORER; CUTTING TORCH OPERATOR (DEMOLITION); DRILLER; DRY PACKING CONCRETE & FILLING OF FORM BOLT HOLES; GAS & OIL PIPELINE WRAPPER; HEAD ROCK SLINGER; JACKHAMMER, DRILLER AND/OR PAVEMENT BREAKER; LAYING OF ALL NONMETALLIC PIPE, INCLUDING SEWER PIPE, DRAIN PIPE AND UNDERGROUND TILE; MACHINE TOOL OPERATOR (OPERATORS AND TENDERS OF PNEUMATIC & ELECTRIC TOOLS, VIBRATING MACHINES AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY CLASSIFIED HEREIN, INCLUDING HAND GUIDED DITCH WITCH AND HAND-TYPE ROLLER); PAVING, AIRPORT RUNWAYS & SIMILAR WORK; PESTICIDE, HERBICIDE, INSECTICIDE APPLICATOR; POTHOLER; POWDERMAN; ROCK SLINGER; SANDBLASTER (NOZZLEMAN); SANDBLASTER (POT TENDER); SHOTCRETE (NOZZLEMAN); SHOTCRETE (POT TENDER); STEEL HEADERBOARD MAN. (ZONE PAY: MERCURY, FORWARD AREAS & NTTR $5.00 FOOT NOTE: SAVINGS ACCOUNT OF $5.55 SHOULD BE ADDED TO THE BASE RATE) | $41.39 | $27.22 | $68.61 | Agreement |
LABORER GROUP 1…Full textLABORER GROUP 1 BUILDING/OFFICE CLEANUP: CESSPOOL DIGGER & INSTALLER; DRINKING WATER; FENCE BUILDER; FINE GRADER, HIGHWAY & STREET; FLAGPERSON; GAS & OIL PIPELINE LABORER; GAS & OIL PIPELINE WRAPPER - POT TENDER AND FORM MAN; GUINEA CHASER; PACKING ROD STEEL AND PLANS; GENERAL (CONSTRUCTION CLEANUP); DEMOLITION; LANDSCAPE GARDENER, NURSERYMAN AND GROUNDS KEEPER; MAKING & CAULKING OF ALL NONMETALLIC PIPE JOINTS; RIP RAP STONE PAVER; ROTO-SCRAPER; SCALER; SEPTIC TANK DIGGER & INSTALLER (LEADMAN); TANK SCALER AND CLEANER; TOOL ATTENDANT (JOBSITE ONLY); TREE CLIMBER, FALLER, CHAIN SAW OPERATOR, PITTSBURGH CHIPPER AND SIMILAR TYPE OF BRUSH SHEDDERS; WINDOW CLEANER (ZONE PAY: MERCURY, FORWARD AREAS & NTTR $5.00 FOOT NOTE: SAVINGS ACCOUNT OF $5.55 SHOULD BE ADDED TO THE BASE RATE) | $41.13 | $27.22 | $68.35 | Agreement |
| LABO0872-010 · Laborers agreement, October 1, 2025 | ||||
| LABORER: BULLGANG, MUCKER, TRACKMAN (ZONE PAY: MERCURY, FORWARD AREAS & NTTR $5.00 FOOT NOTE: SAVINGS ACCOUNT OF $4.22 SHOULD BE ADDED TO THE BASE RATE) | $46.44 | $27.27 | $73.71 | Agreement |
| LABORER: MINER-TUNNEL HARDROCK (ZONE PAY: MERCURY, FORWARD AREAS & NTTR $5.00 FOOT NOTE: SAVINGS ACCOUNT OF $4.22 SHOULD BE ADDED TO THE BASE RATE) | $46.69 | $27.27 | $73.96 | Agreement |
| LABORER: SHAFT, RAISE, STOPE MINER (ZONE PAY: MERCURY, FORWARD AREAS & NTTR $5.00 FOOT NOTE: SAVINGS ACCOUNT OF $4.22 SHOULD BE ADDED TO THE BASE RATE) | $47.69 | $27.27 | $74.96 | Agreement |
| PAIN0159-002 · Painters and Allied Trades agreement, October 1, 2025 | ||||
PAINTER: FLOORCOVERER…Full textPAINTER: FLOORCOVERER, CARPET, LINOLEUM AND TILE GLAZIER (ZONE PAY- NNSS $5.00; NTTR $5.00) | $52.40 | $24.18 | $76.58 | Agreement |
| PAINTER (ZONE PAY- NNSS $5.00; NTTR $5.00) | $51.79 | $24.18 | $75.97 | Agreement |
| PAINTER, SPRAY AND PAPERHANGER SIGN (ZONE PAY- NNSS $5.00; NTTR $5.00) | $52.14 | $24.18 | $76.32 | Agreement |
| PAINTER, TAPER, FLUSHER AND DETAILER (ZONE PAY- NNSS $5.00; NTTR $5.00) | $52.14 | $24.18 | $76.32 | Agreement |
| PLAS0797-004 · Plasterers and Cement Masons agreement, October 1, 2024 | ||||
PLASTERER (ZONE PAY ZONE A - LAS VEGAS - NO PAY ZONE ZONE B - MERCURY AND FORWARD…Full textPLASTERER (ZONE PAY ZONE A - LAS VEGAS - NO PAY ZONE ZONE B - MERCURY AND FORWARD AREAS-$5.00 ZONE C - NTTR-$5.50) | $42.03 | $28.05 | $70.08 | Agreement |
CEMENT MASON (ZONE PAY ZONE A - LAS VEGAS - NO PAY ZONE ZONE B - MERCURY AND FORWARD…Full textCEMENT MASON (ZONE PAY ZONE A - LAS VEGAS - NO PAY ZONE ZONE B - MERCURY AND FORWARD AREAS-$5.00 ZONE C - NTTR-$5.50) | $43.27 | $29.66 | $72.93 | Agreement |
| PLAS0797-004 · Plasterers and Cement Masons agreement, October 1, 2025 | ||||
PLASTERER (ZONE PAY ZONE A - LAS VEGAS - NO PAY ZONE ZONE B - MERCURY AND FORWARD…Full textPLASTERER (ZONE PAY ZONE A - LAS VEGAS - NO PAY ZONE ZONE B - MERCURY AND FORWARD AREAS-$5.00 ZONE C - NTTR-$5.50) | $42.03 | $28.05 | $70.08 | Agreement |
CEMENT MASON (ZONE PAY ZONE A - LAS VEGAS - NO PAY ZONE ZONE B - MERCURY AND FORWARD…Full textCEMENT MASON (ZONE PAY ZONE A - LAS VEGAS - NO PAY ZONE ZONE B - MERCURY AND FORWARD AREAS-$5.00 ZONE C - NTTR-$5.50) | $43.27 | $29.66 | $72.93 | Agreement |
| PLUM0525-007 · Plumbers and Pipefitters agreement, October 1, 2025 | ||||
PIPEFITTER: INCLUDING INERT GAS WELDER…Full textPIPEFITTER: INCLUDING INERT GAS WELDER (ZONE PAY: MERCURY $7.50; FORWARD AREAS $11.25; NTTR $11.25) | $62.85 | $26.75 | $89.60 | Agreement |
PLUMBER: INCLUDLING LEAD BURNER…Full textPLUMBER: INCLUDLING LEAD BURNER (ZONE PAY: MERCURY $7.50; FORWARD AREAS $11.25; NTTR $11.25) | $62.85 | $26.75 | $89.60 | Agreement |
| REFRIGERATION MECHANIC (ZONE PAY: MERCURY $7.50; FORWARD AREAS $11.25; NTTR $11.25) | $62.85 | $26.75 | $89.60 | Agreement |
| ROOF0162-003 · Roofers agreement, October 1, 2025 | ||||
| ROOFER (INCLUDING WATERPROOFING) | $39.74 | $12.42 | $52.16 | Agreement |
| SFNV0669-003 · SFNV, October 1, 2025 | ||||
SPRINKLER FITTER ZONE PAY ZONE A…Full textSPRINKLER FITTER ZONE PAY ZONE A: LAS VEGAS - $0.00 ZONE B: NNSS - $4.50 ZONE C: NTTR - $4.50 | $56.69 | $28.62 | $85.31 | SFNV |
| SHEE0088-003 · Sheet Metal Workers agreement, October 1, 2025 | ||||
| SHEET METAL WORKER (ZONE PAY: NNSS $5.50; NTTR $5.50) | $66.73 | $30.01 | $96.74 | Agreement |
| TEAM0631-007 · Teamsters agreement, October 1, 2025 | ||||
TRUCK DRIVER, GROUP 5…Full textTRUCK DRIVER, GROUP 5 TIREMAN (ZONE PAY ZONE 1: $2.00 1-20 MILES ZONE 2: $2.50 20-40 MILES ZONE 3: $3.50 40-60 MILES ZONE 4: $6.00 OVER 60 MILES) | $44.26 | $28.37 | $72.63 | Agreement |
TRUCK DRIVER, GROUP 4…Full textTRUCK DRIVER, GROUP 4 BOOTMAN, OFF-ROAD AND SPECIAL EQUIPMENT DRIVER (ZONE PAY ZONE 1: $2.00 1-20 MILES ZONE 2: $2.50 20-40 MILES ZONE 3: $3.50 40-60 MILES ZONE 4: $6.00 OVER 60 MILES) | $44.78 | $28.37 | $73.15 | Agreement |
TRUCK DRIVER, GROUP 3…Full textTRUCK DRIVER, GROUP 3 EXTRA HEAVY DUTY DRIVER, FORKLIFT DRIVER (OVER 15 TONS). (ZONE PAY ZONE 1: $2.00 1-20 MILES ZONE 2: $2.50 20-40 MILES ZONE 3: $3.50 40-60 MILES ZONE 4: $6.00 OVER 60 MILES) | $44.06 | $28.37 | $72.43 | Agreement |
TRUCK DRIVER, GROUP 2…Full textTRUCK DRIVER, GROUP 2 EQUIPMENT PARTS CLERK, FLEET OPERATIONS DISPATCHER, FORKLIFT DRIVER (UNDER 15 TONS), HEAVY DUTY DRIVER, WAREHOUSEMAN. (ZONE PAY ZONE 1: $2.00 1-20 MILES ZONE 2: $2.50 20-40 MILES ZONE 3: $3.50 40-60 MILES ZONE 4: $6.00 OVER 60 MILES) | $43.86 | $28.37 | $72.23 | Agreement |
TRUCK DRIVER, GROUP 1…Full textTRUCK DRIVER, GROUP 1 LIGHT DUTY DRIVER, LIGHT VEHICLE DISPATCHER, TRUCK GREASER. (ZONE PAY ZONE 1: $2.00 1-20 MILES ZONE 2: $2.50 20-40 MILES ZONE 3: $3.50 40-60 MILES ZONE 4: $6.00 OVER 60 MILES) | $43.69 | $28.37 | $72.06 | Agreement |
Modification history
| Modification 1 | January 30, 2026 |
| Modification 2 | May 18, 2026 |
| Modification 3 | June 1, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on NV20260002?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 3 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator