CertifiedHours

Prevailing wage rates · New Jersey · Wage determination

Prevailing wage rates: Somerset County, New Jersey

Heavy construction · NJ20260063 modification 1, published May 18, 2026

The short answer

This sheet sets 31 classifications for heavy work in Somerset County, New Jersey. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $47.96 an hour (painters: brush and roller) to $107.14 (pipefitter). Your contract may lock an earlier modification.

What changed this year

First published January 2, 2026, this sheet is now on modification 1, and its rates have changed in 1 modification.

Latest change

May 18, 2026 · modification 1

Classification names reworded; 2 fringe formulas changed among the 24 lines we could match

  • Electrician: 1 fringe formula changed
  • Truck drivers: 1 fringe formula changed

SAM.gov reworded this sheet’s classification names in this modification, so not every line can be matched to the one before. Only lines matched with certainty are compared here; nothing is guessed. If your trade is not listed, compare it against your contract’s copy.

Every line that changed (2)
ClassificationWasNowChange
ELECTRICIAN: CABLE SPLICER (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN E…$71.97 + 64.5%$71.97 + $46.42changed
TRUCK DRIVERS: DUMP TRUCK; FLATBED TRUCK;PICK UP TRUCK HAZARDOUS WASTE REMOVAL WORK: WOR…$48.63 + 42.655$48.63 + $42.66changed

Compared line by line from each modification as published on SAM.gov. A line we could not pair with certainty is left out rather than guessed.

Rates by classification

These are the rates in modification 1 as published on SAM.gov. The determination and modification written into your contract are the ones that bind you; check that number before relying on this table. Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from and its year; a survey year long past means the rate has not been surveyed since. A marker means the group changed in this modification. In the Since column, a dash means SAM.gov reworded the line during the year and it cannot be matched to the first publication with certainty. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSince Jan 2Source
BRNJ0004-001 · Bricklayers agreement, May 1, 2025
CEMENT MASON$49.60$37.96$87.56no changeAgreement, 2025
CARP0006-014 · Carpenters agreement, May 1, 2025
CARPENTER THE FIRST SIXTY FEET AT THE REGULAR RATE…
Full text

CARPENTER THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER

$57.42$34.17$91.59—Agreement, 2025
CARP0715-007 · Carpenters agreement, May 1, 2025
MILLWRIGHT Work of erection and dismantling of elevators and towers…
Full text

MILLWRIGHT Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.

$58.84$35.06$93.90—Agreement, 2025
CARP1556-003 · Carpenters agreement, May 1, 2024
CARPENTER DOCK BUILDER…
Full text

CARPENTER DOCK BUILDER (Concrete form Work on land pile driving, floating marine construction and the construction of wharves, while handling and working with creosote and creosote-impregnated products: $.25 per hour Work on hazardous/toxic/contaminated waste removal, on a hazardous/toxic/contaminated waste site, where the worker comes into contact with hazardous/toxic/contaminated waste material, and when A, B or C personal protective equipment is required and used for respiratory, skin or eye protection: 20% per hour additional

$52.02$39.23$91.25no changeAgreement, 2024
CARPENTER DOCK BUILDER…
Full text

CARPENTER DOCK BUILDER (All other Work on land pile driving, floating marine construction and the construction of wharves, while handling and working with creosote and creosote-impregnated products: $.25 per hour Work on hazardous/toxic/contaminated waste removal, on a hazardous/toxic/contaminated waste site, where the worker comes into contact with hazardous/toxic/contaminated waste material, and when A, B or C personal protective equipment is required and used for respiratory, skin or eye protection: 20% per hour additional

$52.98$52.44$105.42no changeAgreement, 2024
ELEC0102-025 · Electrical Workers (IBEW) agreement, June 2, 2025
ELECTRICIAN (SOMERSET COUNTY…
Full text

ELECTRICIAN (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER County line to Harlingen Rd.; then, west along Harlingen Rd. and the Dutchtown-Zion road to the Hillsborough township line) Work forty ft. or more above the ground or protective rigging (does not apply to pole work, or to use of a manlift or high reach-type lift): 10% per hour additional. Work with, or the removal of, asbestos materials: 112% times the journeyman rate

$65.43$42.86$108.29—Agreement, 2025
ELECTRICIAN: CABLE SPLICER…
Full text

ELECTRICIAN: CABLE SPLICER (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF FRANKLIN EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE; DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER County line to Harlingen Rd.; then, west along Harlingen Rd. and the Dutchtown-Zion road to the Hillsborough township line) Work forty ft. or more above the ground or protective rigging (does not apply to pole work, or to use of a manlift or high reach-type lift): 10% per hour additional. Work with, or the removal of, asbestos materials: 112% times the journeyman rate

$71.97$46.42$118.39changedAgreement, 2025
ELEC0269-023 · Electrical Workers (IBEW) agreement, July 6, 2020
ELECTRICIAN (SOMERSET COUNTY…
Full text

ELECTRICIAN (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY (WEST AND SOUTH OF A LINE FOLLOWING U.S. HWY. 206 (FORMERLY STATE HWY. 31) NORTH FROM THE MERCER COUNTY LINE TO HARLINGEN RD.; THEN, WEST ALONG HARLINGEN RD. AND THE DUTCHTOWN-ZION ROAD TO THE HILLSBOROUGH TOWNSHIP LINE))

$51.71$33.46$85.17—Agreement, 2020
ELEC0456-009 · Electrical Workers (IBEW) agreement, May 30, 2022
ELECTRICIAN: (SOMERSET COUNTY…
Full text

ELECTRICIAN: (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE)) WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER HOUR ADDITIONAL

$55.85$39.79$95.64—Agreement, 2022
ELECTRICIAN: CABLE SPLICER…
Full text

ELECTRICIAN: CABLE SPLICER (SOMERSET COUNTY (TOWNSHIP OF FRANKLIN (EAST OF A LINE FOLLOWING CEDAR GROVE LANE FROM THE RARITAN RIVER, IN A SOUTHWESTERLY DIRECTION, TO THE MILLSTONE BRANCH OF THE PENNSYLVANIA RAILROAD; THEN, WEST ALONG THE RAILROAD TO THE DELAWARE AND RARITAN CANAL; THEN, SOUTH ALONG THE CANAL TO THE MIDDLESEX COUNTY LINE)) WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER HOUR ADDITIONAL

$65.35$46.56$111.91—Agreement, 2022
ENGI0825-021 · Operating Engineers agreement, July 1, 2025
POWER EQUIPMENT OPERATORS: GROUP 5…
Full text

POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$52.88$37.50$90.38no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 4…
Full text

POWER EQUIPMENT OPERATORS: GROUP 4 BROOM; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); ROLLER, GRADE; PUMP HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$56.59$37.50$94.09no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 3…
Full text

POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER; COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); CRUSHER; FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$58.22$37.50$95.72no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 2…
Full text

POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$60.13$37.50$97.63no changeAgreement, 2025
POWER EQUIPMENT OPERATORS: GROUP 1…
Full text

POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE) HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$61.72$37.50$99.22no changeAgreement, 2025
IRON0011-010 · Ironworkers agreement, July 1, 2025
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (SOMERSET COUNTY (NORTHERN HALF OF COUNTY))$52.24$50.32$102.56no changeAgreement, 2025
IRONWORKER: REINFORCING (SOMERSET COUNTY (NORTHERN HALF OF COUNTY))$49.94$50.32$100.26no changeAgreement, 2025
IRON0399-018 · Ironworkers agreement, July 1, 2024
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (SOMERSET COUNTY (SOUTHERN HALF OF COUNTY))$54.24$38.40$92.64no changeAgreement, 2024
IRONWORKER: REINFORCING (SOMERSET COUNTY (SOUTHERN HALF OF COUNTY))$53.24$38.40$91.64no changeAgreement, 2024
LABO0077-008 · Laborers agreement, July 1, 2012
LABORER: MASON TENDER: CEMENT/CONCRETE$29.35$23.07$52.42no changeAgreement, 2012
LABO0172-009 · Laborers agreement, March 1, 2025
LABORER: PIPELAYER HAZARDOUS WASTE REMOVAL WORK…
Full text

LABORER: PIPELAYER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS REQUIRED TO WEAR LEVEL A, B OR C PERSONAL PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS NOT REQUIRED TO WEAR LEVEL A, B, OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVED

$51.65$38.53$90.18no changeAgreement, 2025
LABORER: COMMON OR GENERAL LABORER…
Full text

LABORER: COMMON OR GENERAL LABORER; LANDSCAPE LABORER, POWER TOOL OPERATOR HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS REQUIRED TO WEAR LEVEL A, B OR C PERSONAL PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS NOT REQUIRED TO WEAR LEVEL A, B, OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVED

$50.95$38.53$89.48no changeAgreement, 2025
PAIN0711-023 · Painters and Allied Trades agreement, May 1, 2023
PAINTERS: WORK ON BRIDGES (MAJOR BRIDGES DESIGNED FOR COMMERCIAL NAVIGATION)$58.28$33.85$92.13no changeAgreement, 2023
PAIN0711-024 · Painters and Allied Trades agreement, May 1, 2017
PAINTERS: BRUSH AND ROLLER…
Full text

PAINTERS: BRUSH AND ROLLER (REPAINT WORK, ON PROJECTS ON WHICH NO MAJOR ALTERATIONS OCCUR.)

$29.05$18.91$47.96no changeAgreement, 2017
PAINTERS: BRUSH AND ROLLER (NEW CONSTRUCTION)$40.19$22.72$62.91no changeAgreement, 2017
PLUM0009-027 · Plumbers and Pipefitters agreement, July 1, 2025
PLUMBER/PIPEFITTER (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))$59.57$46.45$106.02no changeAgreement, 2025
PLUMBER/PIPEFITTER…
Full text

PLUMBER/PIPEFITTER: SERVICE AND REPAIR (SOMERSET COUNTY (TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))

$46.23$29.23$75.46no changeAgreement, 2025
PLUM0024-020 · Plumbers and Pipefitters agreement, May 1, 2025
PLUMBER (SOMERSET COUNTY…
Full text

PLUMBER (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))

$62.09$45.05$107.14no changeAgreement, 2025
PLUM0475-019 · Plumbers and Pipefitters agreement, May 1, 2025
PIPEFITTER (SOMERSET COUNTY…
Full text

PIPEFITTER (SOMERSET COUNTY (DOES NOT INCLUDE THE TOWNSHIP OF MONTGOMERY; BOROUGH OF ROCKY HILL))

$56.34$50.80$107.14no changeAgreement, 2025
TEAM0469-008 · Teamsters agreement, May 1, 2025
TRUCK DRIVERS: DUMP TRUCK…
Full text

TRUCK DRIVERS: DUMP TRUCK; FLATBED TRUCK;PICK UP TRUCK HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE WHERE THE WORKER IS NOT WORKING IN A ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY. VACATION PAY CREDIT: WORKERS WORKING OR RECEIVING PAY FOR 80 DAYS WITHIN A YEAR RECEIVE ONE WEEK PAID VACATION (48 HOURS); 125 DAYS RECEIVE TWO WEEKS PAID VACATION (96 HOURS); 145 DAYS RECEIVE 15 DAYS PAID VACATION (120 HOURS); 15 YEARS SENIORITY AND 145 DAYS RECEIVE 4 WEEKS PAID VACATION (160 HOURS)

$48.63$42.66$91.29changedAgreement, 2025
TRUCK DRIVERS: OFF THE ROAD TRUCK HAZARDOUS WASTE REMOVAL WORK…
Full text

TRUCK DRIVERS: OFF THE ROAD TRUCK HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE WHERE THE WORKER IS NOT WORKING IN A ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY. VACATION PAY CREDIT: WORKERS WORKING OR RECEIVING PAY FOR 80 DAYS WITHIN A YEAR RECEIVE ONE WEEK PAID VACATION (48 HOURS); 125 DAYS RECEIVE TWO WEEKS PAID VACATION (96 HOURS); 145 DAYS RECEIVE 15 DAYS PAID VACATION (120 HOURS); 15 YEARS SENIORITY AND 145 DAYS RECEIVE 4 WEEKS PAID VACATION (160 HOURS)

$48.78$42.66$91.44—Agreement, 2025

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on NJ20260063?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator

Put these rates on a certified payroll.

Start here and NJ20260063 is already filled in when you set up the job. CertifiedHours loads this sheet, checks every line against it as you type hours, and prints the WH-347. Free for one payroll a month.

Start a payroll on this sheet

On this sheet

  • 31 classifications in 18 rate groups
  • 18 from agreements, 0 from surveys
  • Counties: Somerset