Prevailing wage rates: Hunterdon County, New Jersey

Building construction · NJ20260034 modification 2, published May 18, 2026

The short answer

This sheet sets 41 classifications for building work in Hunterdon County, New Jersey. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $49.99 an hour (asbestos removal laborer the removal) to $113.99 (electrician (including low voltage wiring)). Your contract may lock an earlier modification.

Rates by classification

Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
ASBE0032-006 · Asbestos Workers and Heat & Frost Insulators agreement, September 19, 2024
Group definitions, zones and premiums for ASBE0032-006
ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement) (HUNTERDON COUNTY (Borough of Califon; Township of Tewksbury)).$ 51.74 46.20
ASBE0089-006 · Asbestos Workers and Heat & Frost Insulators agreement, July 1, 2025
ASBESTOS WORKER/HEAT & FROST INSULATOR…
Full text

ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement) (HUNTERDON COUNTY (does not include the Borough of Califon; Township of

PAID HOLIDAYS: The last day prior to the Christmas and New Year's Day observed holiday: 4 hrs. pay

$55.80$40.80$96.60Agreement
BRNJ0002-013 · Bricklayers agreement, May 1, 2021
BRICKLAYER Work on high stacks: 22% per hour additional.$45.20$33.26$78.46Agreement
BRNJ0004-001 · Bricklayers agreement, May 1, 2025
CEMENT MASON$49.60$37.96$87.56Agreement
BRNJ0007-001 · Bricklayers agreement, June 2, 2025
TILE SETTER$64.90$37.28$102.18Agreement
Group definitions, zones and premiums for BRNJ0007-001
TILE FINISHER Work grouting all epoxy: $10.00 additional per day. $ 50.05 33.90
CARP0006-009 · Carpenters agreement, May 1, 2025
CARPENTER (SCAFFOLD The first sixty feet at the regular rate…
Full text

CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter

$57.42$34.17$91.59Agreement
CARP0006-011 · Carpenters agreement, May 1, 2025
CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK)$57.42$34.17$91.59Agreement
CARP0715-007 · Carpenters agreement, May 1, 2025
Work of erection and dismantling of elevators and towers…
Full text

Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.

$58.84$35.06$93.90Agreement
ELEC0102-019 · Electrical Workers (IBEW) agreement, June 2, 2025
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING)…
Full text

ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING) (HUNTERDON COUNTY (Townships of Alexandria and Bethlehem; Boroughs of Bloomsbury and Califon; Town of Clinton; Township of Clinton; Township of Delaware (west of a line following County Route 523 from the Delaware River north to the Raritan Township line); Township of East Amwell (east of State Hwy. 31); Township of Franklin; Boroughs of Frenchtown, Glen Gardner, Hampton and High Bridge; Townships of Holland and Kingwood; Borough of Lebanon; Township of Lebanon; Borough of Milford; Township of Raritan (east of State Hwy. 31 and north of County Route 523); Townships of Readington, Tewksbury and Work forty ft. or more above the ground or protective rigging (does not apply to pole work, or to use of a manlift or high reach-type lift): 10% per hour Work with, or the removal of, asbestos materials: 114% times the journeyman rate

$65.43$42.86$108.29Agreement
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING)…
Full text

ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING): CABLE SPLICER (HUNTERDON COUNTY (Townships of Alexandria and Bethlehem; Boroughs of Bloomsbury and Califon; Town of Clinton; Township of Clinton; Township of Delaware (west of a line following County Route 523 from the Delaware River north to the Raritan Township line); Township of East Amwell (east of State Hwy. 31); Township of Franklin; Boroughs of Frenchtown, Glen Gardner, Hampton and High Bridge; Townships of Holland and Kingwood; Borough of Lebanon; Township of Lebanon; Borough of Milford; Township of Raritan (east of State Hwy. 31 and north of County Route 523); Townships of Readington, Tewksbury and Work forty ft. or more above the ground or protective rigging (does not apply to pole work, or to use of a manlift or high reach-type lift): 10% per hour Work with, or the removal of, asbestos materials: 114% times the journeyman rate

$69.72$44.27$113.99Agreement
ELEC0269-018 · Electrical Workers (IBEW) agreement, January 5, 2026
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING)…
Full text

ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING) (HUNTERDON COUNTY (Township of Delaware (east of a line following County Route 523 from the Delaware River north to the Raritan Township line); Township of East Amwell (west of State Hwy. 31); Borough of Flemington; City of Lambertville; Township of Raritan (west of State Hwy. 31 and south of County Route 523); Borough of Stockton; Township of West Amwell))

$63.82$41.99$105.81Agreement
ELEV0084-006 · Elevator Constructors agreement, January 1, 2025
ELEVATOR a.

PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas b. VACATION PAY CREDIT: A worker with 6 months but less than 5 years of service receives two weeks vacation; a worker with 5 years or more of service receives three weeks vacation

$61.41$38.44$99.85Agreement
ENGI0825-020 · Operating Engineers agreement, July 1, 2025
POWER EQUIPMENT OPERATORS: GROUP 5…
Full text

POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$52.88$37.50$90.38Agreement
POWER EQUIPMENT OPERATORS: GROUP 4…
Full text

POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$56.59$37.50$94.09Agreement
POWER EQUIPMENT OPERATORS: GROUP 3…
Full text

POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$58.22$37.50$95.72Agreement
POWER EQUIPMENT OPERATORS: GROUP 2…
Full text

POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$60.13$37.50$97.63Agreement
POWER EQUIPMENT OPERATORS: GROUP 1…
Full text

POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$61.72$37.50$99.22Agreement
IRON0011-009 · Ironworkers agreement, July 1, 2025
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (Hunterdon County (Western Half of County))$52.24$50.32$102.56Agreement
IRONWORKER: REINFORCING (Hunterdon County (Western Half of County))$49.94$50.32$100.26Agreement
IRON0399-017 · Ironworkers agreement, July 1, 2024
IRONWORKER: REINFORCING (Hunterdon County (Eastern Half of County))$53.24$38.40$91.64Agreement
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (Hunterdon County (Eastern Half of County))$54.24$38.40$92.64Agreement
LABO0008-001 · Laborers agreement, May 1, 2011
ASBESTOS REMOVAL LABORER The removal…
Full text

ASBESTOS REMOVAL LABORER The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and machinery relating to asbestos and/or toxic and hazardous waste or materials which shall include but not necessarily be limited to: the erection, moving, servicing and dismantling of all enclosures, scaffolding and barricades; the operation of all tools and equipment normally used in the removal or abatement of asbestos and toxic or hazardous waste or materials; the labeling, bagging, cartoning, crating, or other packaging of materials for disposal; the clean-up of the worksite; and all other work incidental to the removal, abatement, encapsulation, enclosure, and decontamination of asbestos and toxic or hazardous waste or materials; and, in addition, all work tasks involved in the maintenance and operation of energy resource recovery plants (co-generation plants)

$28.37$21.62$49.99Agreement
LABO0077-002 · Laborers agreement, May 1, 2022
LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE$36.50$30.22$66.72Agreement
LABO0077-005 · Laborers agreement, May 1, 2022
LABORER: ASPHALT SHOVELER…
Full text

LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, PIPELAYER, POWER TOOL OPERATOR AND SCREEDMAN

$35.75$30.22$65.97Agreement
PAIN0711-018 · Painters and Allied Trades agreement, May 1, 2025
DRYWALL FINISHER/TAPER$44.87$30.15$75.02Agreement
PAIN0711-020 · Painters and Allied Trades agreement, May 1, 2025
PAINTER (BRUSH & ROLLER)$45.55$29.86$75.41Agreement
PAINTER (PAPERHANGER)$45.55$29.86$75.41Agreement
PAINTER (SPRAY)$45.55$29.86$75.41Agreement
PAIN0711-021 · Painters and Allied Trades agreement, May 1, 2025
Work welding or using a cutting torch…
Full text

Work welding or using a cutting torch: $1.00 per hour additional. Work on a swing stage scaffold; on a pipe scaffold providing the working height of the platform is 30 ft. or above; and on motorized lifts provided that the height of the lift platform is above the second floor or above thirty feet: $1.00 per hour additional

$52.68$31.29$83.97Agreement
PLAS0008-008 · Plasterers and Cement Masons agreement, May 1, 2021
PLASTERER$38.37$31.64$70.01Agreement
PLUM0009-019 · Plumbers and Pipefitters agreement, July 1, 2025
PLUMBER, EXCLUDING HVAC PIPE INSTALLATION…
Full text

PLUMBER, EXCLUDING HVAC PIPE INSTALLATION (HUNTERDON COUNTY (south of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon/Mercer county line)

$59.57$46.45$106.02Agreement
PIPEFITTER, INCLUDING HVAC PIPE INSTALLATION…
Full text

PIPEFITTER, INCLUDING HVAC PIPE INSTALLATION (HUNTERDON COUNTY (south of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon/Mercer county line)

$59.57$46.45$106.02Agreement
PLUMBER/PIPEFITTER…
Full text

PLUMBER/PIPEFITTER: SERVICE AND REPAIR (HUNTERDON COUNTY (south of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon/Mercer county line)

$46.23$29.23$75.46Agreement
PLUM0024-012 · Plumbers and Pipefitters agreement, May 1, 2025
PLUMBER, EXCLUDING HVAC PIPE INSTALLATION…
Full text

PLUMBER, EXCLUDING HVAC PIPE INSTALLATION (HUNTERDON COUNTY (north of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell -Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon - Mercer County line)

$62.09$45.05$107.14Agreement
PLUM0475-011 · Plumbers and Pipefitters agreement, May 1, 2025
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION HUNTERDON COUNTY…
Full text

PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION HUNTERDON COUNTY (north of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon/Mercer county line)

$56.34$50.80$107.14Agreement
ROOF0030-028 · Roofers agreement, May 1, 2025
ROOFER: ALL OTHER Mopper…
Full text

ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour

PAID HOLIDAY: The last working day before Christmas, to be paid at the rate of four hours pay

$46.03$34.27$80.30Agreement
ROOFER: SLATE AND Mopper…
Full text

ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour

PAID HOLIDAY: The last working day before Christmas, to be paid at the rate of four hours pay

$38.95$21.85$60.80Agreement
ROOFER: Mopper, and operator of felt-laying machine…
Full text

ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour

PAID HOLIDAY: The last working day before Christmas, to be paid at the rate of four hours pay

$35.95$21.85$57.80Agreement
SFNJ0669-007 · SFNJ, April 1, 2025
SPRINKLER FITTER (FIRE SPRINKLERS)$59.19$36.51$95.70SFNJ
SHEE0027-010 · Sheet Metal Workers agreement, June 1, 2024
SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION)$59.08$47.06$106.14Agreement
TEAM0469-005 · Teamsters agreement, May 1, 2025
TRUCK DRIVER: OFF THE ROAD HAZARDOUS WASTE REMOVAL WORK…
Full text

TRUCK DRIVER: OFF THE ROAD HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour

PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas VACATION PAY CREDIT: Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours)

$48.78$42.66$91.44Agreement
TRUCK DRIVER: DUMP HAZARDOUS WASTE REMOVAL WORK…
Full text

TRUCK DRIVER: DUMP HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour

PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas VACATION PAY CREDIT: Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours)

$48.63$42.66$91.29Agreement

Modification history

Modification 1January 30, 2026
Modification 2May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on NJ20260034?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 2 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.