Prevailing wage rates · Missouri · Wage determination
Prevailing wage rates: Dent, Gasconade, Maries and 3 more counties, Missouri
Building construction · MO20260033 modification 1, published May 18, 2026
The short answer
This sheet sets 52 classifications for building work in Dent, Gasconade, Maries and 3 more counties, Missouri. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $24.90 an hour (laborer: asbestos abatement (removal from floors, walls, & ceilings)) to $85.86 (pipefitter, includes hvac pipe installation (morgan county)). Your contract may lock an earlier modification.
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| ASBE0001-011 · Asbestos Workers and Heat & Frost Insulators agreement, October 7, 2024 | ||||
| ASBESTOS WORKER/HEAT & FROST INSULATOR (DENT, GASCONADE, MARIES & MONTGOMERY COUNTIES) | $43.48 | $27.24 | $70.72 | Agreement |
| ASBE0063-005 · Asbestos Workers and Heat & Frost Insulators agreement, November 1, 2024 | ||||
| ASBESTOS WORKER/HEAT & FROST INSULATOR (MILLER & MORGAN COUNTIES) | $31.97 | $14.00 | $45.97 | Agreement |
| BRMO0011-009 · Bricklayers agreement, April 1, 2023 | ||||
| TILE SETTER | $32.79 | $21.31 | $54.10 | Agreement |
| CARP0002-004 · Carpenters agreement, May 1, 2024 | ||||
CARPENTER, INCLUDING DRYWALL HANGING &…Full textCARPENTER, INCLUDING DRYWALL HANGING & FORM WORK (MONTGOMERY COUNTY) (Projects under $1 million) | $39.53 | $21.85 | $61.38 | Agreement |
CARPENTER, INCLUDING DRYWALL HANGING &…Full textCARPENTER, INCLUDING DRYWALL HANGING & FORM WORK (MONTGOMERY COUNTY) (Projects $1 million and over) | $41.30 | $21.85 | $63.15 | Agreement |
| CARP0010-007 · Carpenters agreement, May 1, 2024 | ||||
CARPENTER: INCLUDING DRYWALL HANGING…Full textCARPENTER: INCLUDING DRYWALL HANGING, FORM WORK & RESILIENT/VINYL FLOOR INSTALLATION (MILLER & MORGAN COUNTIES) | $31.51 | $22.25 | $53.76 | Agreement |
| CARP0012-003 · Carpenters agreement, May 1, 2024 | ||||
| CARPENTER: INCLUDING DRYWALL HANGING & FORM WORK (DENT, GASCONADE & MARIES COUNTIES) | $44.19 | $21.85 | $66.04 | Agreement |
| CARP1310-004 · Carpenters agreement, May 1, 2024 | ||||
CARPENTER (FLOOR LAYER)…Full textCARPENTER (FLOOR LAYER): RESILIENT & VINYL FLOORING ONLY (DENT, GASCONADE, MARIES & MONTGOMERY COUNTIES) | $40.08 | $21.85 | $61.93 | Agreement |
| ELEC0124-021 · Electrical Workers (IBEW) agreement, September 1, 2025 | ||||
| ELECTRICIAN (MORGAN COUNTY) | $54.01 | $27.85 | $81.86 | Agreement |
| ELEC0257-010 · Electrical Workers (IBEW) agreement, March 1, 2025 | ||||
| ELECTRICIAN (DENT, GASCONADE, MARIES, & MILLER COUNTIES) | $40.50 | $23.26 | $63.76 | Agreement |
| ELEC0350-007 · Electrical Workers (IBEW) agreement, December 1, 2024 | ||||
| ELECTRICIAN (MONTGOMERY COUNTY) | $37.60 | $22.14 | $59.74 | Agreement |
| ENGI0513-001 · Operating Engineers agreement, May 1, 2025 | ||||
| POWER EQUIPMENT OPERATOR: ROLLER | $35.76 | $30.38 | $66.14 | Agreement |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE | $39.06 | $30.38 | $69.44 | Agreement |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $39.06 | $30.38 | $69.44 | Agreement |
| POWER EQUIPMENT OPERATOR: (PAVER) | $39.06 | $30.38 | $69.44 | Agreement |
| POWER EQUIPMENT OPERATOR: (LOADER) | $39.06 | $30.38 | $69.44 | Agreement |
| POWER EQUIPMENT OPERATOR: (BACKHOE/EXCAVATOR/ TRACKHOE) | $39.06 | $30.38 | $69.44 | Agreement |
| IRON0010-025 · Ironworkers agreement, April 1, 2025 | ||||
| IRONWORKER, STRUCTURAL (MORGAN COUNTY) | $36.00 | $34.25 | $70.25 | Agreement |
| IRON0396-014 · Ironworkers agreement, August 7, 2024 | ||||
| IRONWORKER, STRUCTURAL (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $41.67 | $31.25 | $72.92 | Agreement |
| LABO0660-005 · Laborers agreement, June 2, 2025 | ||||
| LABORER: COMMON OR GENERAL, LANDSCAPE & BRICK MASON TENDER (MONTGOMERY COUNTY) | $41.18 | $15.96 | $57.14 | Agreement |
| LABO0663-005 · Laborers agreement, April 1, 2023 | ||||
| LABORER: COMMON OR GENERAL & LANDSCAPE (MORGAN COUNTY) | $26.95 | $14.95 | $41.90 | Agreement |
| LABORER: BRICK MASON TENDER (MORGAN COUNTY) | $28.95 | $14.95 | $43.90 | Agreement |
| LABO0840-005 · Laborers agreement, March 1, 2025 | ||||
| LABORER: COMMON OR GENERAL & LANDSCAPE (DENT, GASCONADE & MARIES COUNTIES) | $30.33 | $15.91 | $46.24 | Agreement |
| LABORER: BRICK MASON TENDER (DENT, GASCONADE & MARIES COUNTIES) | $32.23 | $15.91 | $48.14 | Agreement |
| LABO0955-005 · Laborers agreement, March 1, 2024 | ||||
| LABORER: COMMON OR GENERAL & LANDSCAPE (MILLER COUNTY) | $27.71 | $15.50 | $43.21 | Agreement |
| LABORER: BRICK MASON TENDER (MILLER COUNTY) | $29.71 | $15.50 | $45.21 | Agreement |
| PAIN0003-017 · Painters and Allied Trades agreement, April 1, 2019 | ||||
| PAINTER: DRYWALL FINISHING/TAPING ONLY (MORGAN COUNTY) | $25.39 | $17.76 | $43.15 | Agreement |
| PAINTER: BRUSH & ROLLER ONLY (MORGAN COUNTY) | $24.43 | $17.76 | $42.19 | Agreement |
| PAIN1185-003 · Painters and Allied Trades agreement, April 1, 2025 | ||||
| PAINTER: BRUSH, ROLLER, & DRYWALL FINISHING/TAPING ONLY (GASCONADE & MONTGOMERY COUNTIES) | $28.56 | $17.21 | $45.77 | Agreement |
| PAIN1185-010 · Painters and Allied Trades agreement, April 1, 2025 | ||||
| PAINTER: DRYWALL FINISHING/TAPING ONLY (DENT, MARIES, & MILLER COUNTIES) | $34.90 | $17.21 | $52.11 | Agreement |
| PAINTER: BRUSH & ROLLER ONLY (DENT, MARIES, & MILLER COUNTIES) | $33.90 | $17.21 | $51.11 | Agreement |
| PLAS0518-001 · Plasterers and Cement Masons agreement, March 1, 2025 | ||||
| CEMENT MASON/CONCRETE FINISHER (GASCONADE, MARIES, MILLER, MONTGOMERY, & MORGAN COUNTIES) | $33.52 | $15.88 | $49.40 | Agreement |
| PLAS0527-010 · Plasterers and Cement Masons agreement, April 1, 2023 | ||||
| CEMENT MASON/CONCRETE FINISHER (DENT COUNTY) | $36.63 | $9.85 | $46.48 | Agreement |
| PLUM0008-013 · Plumbers and Pipefitters agreement, June 1, 2025 | ||||
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (MORGAN COUNTY) | $58.38 | $25.29 | $83.67 | Agreement |
| PLUM0533-010 · Plumbers and Pipefitters agreement, June 1, 2025 | ||||
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (MORGAN COUNTY) | $57.51 | $28.35 | $85.86 | Agreement |
| PLUM0562-015 · Plumbers and Pipefitters agreement, July 1, 2024 | ||||
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION…Full textPLUMBER, EXCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $50.60 | $29.38 | $79.98 | Agreement |
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION…Full textPLUMBER, EXCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $48.66 | $30.13 | $78.79 | Agreement |
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION…Full textPIPEFITTER, INCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $50.60 | $29.38 | $79.98 | Agreement |
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION…Full textPIPEFITTER, INCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER (DENT, GASCONADE, MARIES, MILLER, & MONTGOMERY COUNTIES) | $48.66 | $30.13 | $78.79 | Agreement |
| ROOF0002-010 · Roofers agreement, March 1, 2025 | ||||
| ROOFER (GASCONADE & MONTGOMERY COUNTIES) | $40.00 | $22.05 | $62.05 | Agreement |
| ROOF0002-013 · Roofers agreement, June 1, 2025 | ||||
| ROOFER (DENT COUNTY) | $32.25 | $17.46 | $49.71 | Agreement |
| ROOF0020-027 · Roofers agreement, September 19, 2023 | ||||
| ROOFER (MARIES, MILLER, & MORGAN COUNTIES) | $33.60 | $19.99 | $53.59 | Agreement |
| SFMO0669-003 · SFMO, April 1, 2025 | ||||
| SPRINKLER FITTER (FIRE SPRINKLERS) | $45.94 | $27.53 | $73.47 | SFMO |
| SHEE0002-022 · Sheet Metal Workers agreement, July 1, 2023 | ||||
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION (MILLER & MORGAN COUNTIES) | $47.20 | $26.28 | $73.48 | Agreement |
| SHEE0036-018 · Sheet Metal Workers agreement, August 1, 2025 | ||||
SHEET METAL WORKER…Full textSHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION (DENT, GASCONADE, & MONTGOMERY COUNTIES) | $52.00 | $27.12 | $79.12 | Agreement |
| SHEE0036-024 · Sheet Metal Workers agreement, July 1, 2025 | ||||
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION (MARIES COUNTY) | $36.51 | $22.39 | $58.90 | Agreement |
| SUMO2010-032 · Survey of contractors in MO, March 8, 2010 | ||||
| TRUCK DRIVER: DUMP TRUCK | $25.57 | $0.00 | $25.57 | Survey |
| PAINTER: SPRAY | $18.79 | $8.12 | $26.91 | Survey |
| LABORER: ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS, & CEILINGS) | $24.90 | $0.00 | $24.90 | Survey |
| IRONWORKER, REINFORCING | $21.02 | $9.49 | $30.51 | Survey |
| GLAZIER | $29.87 | $1.47 | $31.34 | Survey |
| BRICKLAYER | $27.66 | $5.88 | $33.54 | Survey |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on MO20260033?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator