CertifiedHours

Prevailing wage rates · Missouri · Wage determination

Prevailing wage rates: Camden County, Missouri

Building construction · MO20260005 modification 1, published May 18, 2026

The short answer

This sheet sets 31 classifications for building work in Camden County, Missouri. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $24.90 an hour (laborer: asbestos abatement (removal from floors, walls, & ceilings)) to $82.53 (plumber, excludes hvac pipe installation). Your contract may lock an earlier modification.

Rates by classification

Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
ASBE0063-002 · Asbestos Workers and Heat & Frost Insulators agreement, November 1, 2024
ASBESTOS WORKER/HEAT & FROST INSULATOR$31.97$14.00$45.97Agreement
BRMO0011-009 · Bricklayers agreement, April 1, 2023
TILE SETTER$32.79$21.31$54.10Agreement
CARP0005-010 · Carpenters agreement, May 1, 2024
CARPENTER (INCLUDING DRYWALL HANGING & FORM WORK)$31.51$22.25$53.76Agreement
CARP0005-012 · Carpenters agreement, May 1, 2024
CARPENTER (FLOOR LAYER) (RESILIENT/VINYL FLOOR INSTALLATION ONLY)$31.39$22.25$53.64Agreement
ENGI0101-004 · Operating Engineers agreement, April 1, 2025
POWER EQUIPMENT OPERATOR: ROLLER$30.91$18.07$48.98Agreement
POWER EQUIPMENT OPERATOR: GRADER/BLADE$31.62$18.07$49.69Agreement
POWER EQUIPMENT OPERATOR: BULLDOZER$31.62$18.07$49.69Agreement
POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$33.41$18.07$51.48Agreement
POWER EQUIPMENT OPERATOR: (PAVER)$27.91$18.07$45.98Agreement
POWER EQUIPMENT OPERATOR: (LOADER)$31.62$18.07$49.69Agreement
IRON0396-017 · Ironworkers agreement, August 7, 2024
IRONWORKER, STRUCTURAL$41.67$31.25$72.92Agreement
LABO0663-010 · Laborers agreement, April 1, 2024
LABORER (COMMON OR GENERAL & LANDSCAPE)$26.35$13.01$39.36Agreement
LABORER (BRICK MASON TENDER)$29.08$13.01$42.09Agreement
PAIN1185-005 · Painters and Allied Trades agreement, April 1, 2025
PAINTER: DRYWALL FINISHING/TAPING$33.90$17.21$51.11Agreement
PLAS0518-020 · Plasterers and Cement Masons agreement, March 1, 2025
CEMENT MASON/CONCRETE FINISHER$33.52$15.88$49.40Agreement
PLUM0562-011 · Plumbers and Pipefitters agreement, July 1, 2025
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION…
Full text

PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (ON ANY WORK UNDER 7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS OUTSTATE AREA WAGES AND FRINGES)

$50.66$23.34$74.00Agreement
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION…
Full text

PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (ON ANY WORK OVER $7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS ST. LOUIS AREA WAGES AND FRINGES.)

$52.60$29.93$82.53Agreement
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION…
Full text

PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (ON ANY WORK UNDER 7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS OUTSTATE AREA WAGES AND FRINGES)

$50.66$23.34$74.00Agreement
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION…
Full text

PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (ON ANY WORK OVER $7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS ST. LOUIS AREA WAGES AND FRINGES.)

$52.60$29.93$82.53Agreement
ROOF0020-012 · Roofers agreement, September 19, 2023
ROOFER$33.60$19.99$53.59Agreement
SFMO0669-003 · SFMO, April 1, 2025
SPRINKLER FITTER (FIRE SPRINKLERS)$45.94$27.53$73.47SFMO
SHEE0002-019 · Sheet Metal Workers agreement, July 1, 2023
SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION$47.20$26.28$73.48Agreement
SUMO2010-004 · Survey of contractors in MO, March 8, 2010
TRUCK DRIVER: DUMP TRUCK$25.57$0.00$25.57Survey
PAINTER: SPRAY$18.79$8.12$26.91Survey
PAINTER: ROLLER$18.79$8.12$26.91Survey
PAINTER: BRUSH ONLY$18.79$8.12$26.91Survey
LABORER: ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS, & CEILINGS)$24.90$0.00$24.90Survey
IRONWORKER, REINFORCING$21.02$9.49$30.51Survey
GLAZIER$29.87$1.47$31.34Survey
ELECTRICIAN$25.82$8.24$34.06Survey
BRICKLAYER$27.66$5.88$33.54Survey

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on MO20260005?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator