CertifiedHours

Prevailing wage rates · Michigan · Wage determination

Prevailing wage rates: Gladwin County, Michigan

Building construction · MI20260119 modification 1, published May 18, 2026

The short answer

This sheet sets 79 classifications for building work in Gladwin County, Michigan. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $12.84 an hour (laborer: landscape & irrigation) to $82.05 (millwright). Your contract may lock an earlier modification.

Rates by classification

Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
BOIL0169-002 · Boilermakers agreement, July 1, 2025
BOILERMAKER$43.50$37.64$81.14Agreement
BRMI0009-018 · Bricklayers agreement, August 1, 2024
TILE SETTER$31.43$21.13$52.56Agreement
PLASTERER$33.09$26.58$59.67Agreement
BRICKLAYER$35.14$24.20$59.34Agreement
CARP0706-008 · Carpenters agreement, June 1, 2025
CARPENTER (ACOUSTICAL CEILING INSTALLATION…
Full text

CARPENTER (ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION)

$35.86$23.69$59.55Agreement
CARP0706-011 · Carpenters agreement, June 1, 2025
CARPENTER (EXCLUDING ACOUSTICAL CEILING INSTALLATION…
Full text

CARPENTER (EXCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION, AND SOFT FLOOR LAYER - CARPET)

$35.86$23.69$59.55Agreement
CARP1102-003 · Carpenters agreement, June 1, 2025
MILLWRIGHT$42.92$39.13$82.05Agreement
ELEC0692-006 · Electrical Workers (IBEW) agreement, June 1, 2025
ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING)$40.00$26.52$66.52Agreement
ENGI0324-023 · Operating Engineers agreement, June 1, 2022
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL D)

$38.18$24.85$63.03Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL D WHEN CAPPING LANDFILL)

$40.83$24.85$65.68Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL B AND C)

$36.43$24.85$61.28Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 2: LEVEL A)

$28.86$24.85$53.71Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2 (AREA 2: LEVEL D)$39.08$24.85$63.93Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2 (AREA 2: LEVEL D WHEN CAPPING LANDFILL)

$36.43$24.85$61.28Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2 (AREA 2: LEVEL B AND C)

$44.13$24.85$68.98Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2 (AREA 2: LEVEL A)$26.38$24.85$51.23Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 (AREA 2: LEVEL D)$26.38$24.85$51.23Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 (AREA 2: LEVEL B AND C)

$30.61$24.85$55.46Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 (AREA 2: LEVEL A)$39.08$24.85$63.93Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL D)

$34.72$24.85$59.57Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL B AND C)

$36.47$24.85$61.32Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL A)

$34.72$24.85$59.57Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL B AND C)

$26.13$24.85$50.98Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL A)

$42.38$24.85$67.23Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL D)

$26.38$24.85$51.23Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL D WHEN CAPPING LANDFILL)

$26.13$24.85$50.98Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: REGULAR CRANE OPERATOR, MECHANIC, DRAGLINE OPERATOR, BOOM TRUCK OPERATOR AND CONCRETE PUMP WITH BOOM OPERATOR, POWER SHOVEL OPERATOR (AREA 1: LEVEL A)

$30.61$24.85$55.46Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2 (AREA 1: LEVEL D)$39.08$24.85$63.93Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2 (AREA 1: LEVEL D WHEN CAPPING LANDFILL)

$30.61$24.85$55.46Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2 (AREA 1: LEVEL B AND C)

$36.47$24.85$61.32Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2 (AREA 1: LEVEL A)$36.43$24.85$61.28Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1 (AREA 1: LEVEL D)$38.18$24.85$63.03Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1 (AREA 1: LEVEL D WHEN CAPPING LANDFILL)

$28.86$24.85$53.71Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1 (AREA 1: LEVEL B AND C)

$44.13$24.85$68.98Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1 (AREA 1: LEVEL A)$40.83$24.85$65.68Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL D)

$34.72$24.85$59.57Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL D WHEN CAPPING LANDFILL)

$44.13$24.85$68.98Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL B AND C)

$26.13$24.85$50.98Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL A)

$42.38$24.85$67.23Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL D)

$42.38$24.85$67.23Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL D WHEN CAPPING LANDFILL)

$36.47$24.85$61.32Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL B AND C)

$40.83$24.85$65.68Agreement
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL…
Full text

POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL A)

$28.86$24.85$53.71Agreement
OPERATOR: POWER EQUIPMENT: GROUP 6…
Full text

OPERATOR: POWER EQUIPMENT: GROUP 6 OILER CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE.

PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY.

$26.13$24.85$50.98Agreement
OPERATOR: POWER EQUIPMENT: GROUP 5…
Full text

OPERATOR: POWER EQUIPMENT: GROUP 5 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE.

PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY.

$30.61$24.85$55.46Agreement
OPERATOR: POWER EQUIPMENT: GROUP 4…
Full text

OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; FORK TRUCK (OVER 20' LIFT) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE.

PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY.

$36.47$24.85$61.32Agreement
OPERATOR: POWER EQUIPMENT: GROUP 3…
Full text

OPERATOR: POWER EQUIPMENT: GROUP 3 CRANE; LOADER; PAVER; SCRAPER; STIFF LEG DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE.

PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY.

$40.83$24.85$65.68Agreement
OPERATOR: POWER EQUIPMENT: GROUP 2…
Full text

OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER; TOWER CRANE; GANTRY CRANE AND WHIRLEY DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE.

PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY.

$38.18$24.85$63.03Agreement
OPERATOR: POWER EQUIPMENT: GROUP 1…
Full text

OPERATOR: POWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE.

PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY.

$44.13$24.85$68.98Agreement
IRON0025-009 · Ironworkers agreement, April 1, 2025
IRONWORKER: STRUCTURAL (METAL BUILDING ERECTION ONLY)$30.02$27.43$57.45Agreement
IRON0025-010 · Ironworkers agreement, June 1, 2025
IRONWORKER, STRUCTURAL$36.55$35.93$72.48Agreement
IRONWORKER, REINFORCING$36.55$33.37$69.92Agreement
LABO1098-029 · Laborers agreement, July 1, 2025
LABORER: SANDBLASTER$28.21$13.45$41.66Agreement
LABORER (MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; AND PIPELAYER)$27.68$13.45$41.13Agreement
PAIN1803-001 · Painters and Allied Trades agreement, June 1, 2025
PAINTER: DRYWALL FINISHING/TAPING$30.22$22.22$52.44Agreement
PAINTER: BRUSH, ROLLER AND SPRAY$29.23$19.11$48.34Agreement
PLAS0016-038 · Plasterers and Cement Masons agreement, April 1, 2014
CEMENT MASON/CONCRETE FINISHER$25.47$12.38$37.85Agreement
PLUM0085-004 · Plumbers and Pipefitters agreement, May 4, 2023
PLUMBER (EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION)$43.50$22.10$65.60Agreement
PIPEFITTER (HVAC PIPE INSTALLATION ONLY)$45.50$21.75$67.25Agreement
PIPEFITTER (EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION)$45.50$21.75$67.25Agreement
PLUM0085-004 · Plumbers and Pipefitters agreement, May 1, 2024
PLUMBER (EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION)$43.50$22.10$65.60Agreement
PIPEFITTER (HVAC PIPE INSTALLATION ONLY)$45.50$21.75$67.25Agreement
PIPEFITTER (EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION)$45.50$21.75$67.25Agreement
SHEE0007-021 · Sheet Metal Workers agreement, May 1, 2018
SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION)$26.83$23.78$50.61Agreement
SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION)$26.83$23.78$50.61Agreement
SUMI2011-044 · Survey of contractors in MI, February 14, 2011
TRUCK DRIVER: FLATBED TRUCK$16.80$3.97$20.77Survey
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK$15.65$3.12$18.77Survey
SPRINKLER FITTER (FIRE SPRINKLERS)$19.36$4.53$23.89Survey
ROOFER$15.73$7.41$23.14Survey
OPERATOR: TRACTOR$19.60$7.31$26.91Survey
OPERATOR: ROLLER$28.02$7.07$35.09Survey
OPERATOR: GRADER/BLADE$24.04$6.03$30.07Survey
OPERATOR: BULLDOZER$22.34$1.22$23.56Survey
OPERATOR: BACKHOE/EXCAVATOR$19.00$1.22$20.22Survey
LABORER: LANDSCAPE & IRRIGATION$12.84$0.00$12.84Survey
LABORER: COMMON OR GENERAL$11.75$1.22$12.97Survey
GLAZIER$16.95$4.74$21.69Survey
CARPENTER (FLOOR LAYING-CARPET ONLY)$19.59$7.57$27.16Survey
ASBESTOS WORKER/HEAT & FROST INSULATOR$19.82$7.31$27.13Survey

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on MI20260119?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator