Prevailing wage rates · Michigan · Wage determination
Prevailing wage rates: St Clair County, Michigan
Heavy construction · MI20260072 modification 1, published May 18, 2026
The short answer
This sheet sets 39 classifications for heavy work in St Clair County, Michigan. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $24.51 an hour (truck driver: off the road truck) to $86.17 (line construction: linemen/cable splicer). Your contract may lock an earlier modification.
Scope
Heavy, Includes Water, Sewer Lines and Excavation (Excludes Hazardous Waste Removal; Coal, Oil, Gas, Duct and other similar Pipeline Construction)
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| BOIL0169-003 · Boilermakers agreement, July 1, 2025 | ||||
| BOILERMAKER | $43.50 | $36.74 | $80.24 | Agreement |
| CARP0687-008 · Carpenters agreement, June 1, 2024 | ||||
| PILEDRIVERMAN | $38.48 | $30.22 | $68.70 | Agreement |
| CARPENTER, INCLUDES FORM WORK | $42.44 | $31.43 | $73.87 | Agreement |
| CARP0687-008 · Carpenters agreement, June 1, 2025 | ||||
| PILEDRIVERMAN | $38.48 | $30.22 | $68.70 | Agreement |
| CARPENTER, INCLUDES FORM WORK | $42.44 | $31.43 | $73.87 | Agreement |
| ELEC0017-003 · Electrical Workers (IBEW) agreement, June 1, 2025 | ||||
| LINE CONSTRUCTION: LINEMEN/CABLE SPLICER | $61.06 | $25.11 | $86.17 | Agreement |
| ELEC0058-007 · Electrical Workers (IBEW) agreement, June 28, 2024 | ||||
| ELECTRICIAN | $51.32 | $28.54 | $79.86 | Agreement |
| ENGI0325-019 · Operating Engineers agreement, September 1, 2025 | ||||
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4…Full textPOWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | $39.95 | $25.25 | $65.20 | Agreement |
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3…Full textPOWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | $40.52 | $25.25 | $65.77 | Agreement |
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2…Full textPOWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | $41.25 | $25.25 | $66.50 | Agreement |
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1…Full textPOWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPER, TRENCHER (OVER 8 FT. DIGGING CAPACITY) | $45.98 | $25.25 | $71.23 | Agreement |
| ENGI0326-008 · Operating Engineers agreement, June 1, 2025 | ||||
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 9 OILER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $35.29 | $25.35 | $60.64 | Agreement |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 8 FORKLIFT FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $43.63 | $25.35 | $68.98 | Agreement |
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 7…Full textOPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 7 BACKHOE/EXCAVATOR, BOBCAT/SKID LOADER, BORING MACHINE, BROOM/SWEEPER, BULLDOZER, GRADER/BLADE, LOADER, ROLLER, SCRAPER, TRACTOR, TRENCHER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $45.34 | $25.35 | $70.69 | Agreement |
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6…Full textOPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 REGULAR CRANE OPERATOR FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $46.31 | $25.35 | $71.66 | Agreement |
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5…Full textOPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5 CRANE WITH BOOM & JIB OR LEADS 120' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $47.17 | $25.35 | $72.52 | Agreement |
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4…Full textOPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 CRANE WITH BOOM & JIB OR LEADS 140' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $47.99 | $25.35 | $73.34 | Agreement |
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3…Full textOPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 CRANE WITH BOOM & JIB OR LEADS 220' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $48.29 | $25.35 | $73.64 | Agreement |
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2…Full textOPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 CRANE WITH BOOM & JIB OR LEADS 300' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $49.79 | $25.35 | $75.14 | Agreement |
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1…Full textOPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE WITH BOOM & JIB OR LEADS 400' OR LONGER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM | $51.29 | $25.35 | $76.64 | Agreement |
| IRON0025-006 · Ironworkers agreement, June 1, 2025 | ||||
| IRONWORKER: STRUCTURAL | $36.55 | $35.93 | $72.48 | Agreement |
| IRONWORKER: REINFORCING | $36.55 | $33.37 | $69.92 | Agreement |
| LABO0334-009 · Laborers agreement, June 1, 2025 | ||||
LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION: GROUP 2…Full textLANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | $27.71 | $9.10 | $36.81 | Agreement |
LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION: GROUP 1…Full textLANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER (OR EQUIVALENT) | $29.93 | $9.10 | $39.03 | Agreement |
| LABO0334-015 · Laborers agreement, September 1, 2022 | ||||
| LABORER ((7) LANDSCAPE) | $18.29 | $12.85 | $31.14 | Agreement |
| LABORER ((5) PIPELAYER) | $23.84 | $13.52 | $37.36 | Agreement |
| LABORER ((4) GRADE CHECKER) | $23.70 | $13.15 | $36.85 | Agreement |
| LABORER ((2) MASON TENDER-CEMENT/CONCRETE) | $23.53 | $13.15 | $36.68 | Agreement |
| LABORER ((1) COMMON OR GENERAL) | $23.39 | $13.15 | $36.54 | Agreement |
| LABO1075-005 · Laborers agreement, June 1, 2024 | ||||
LABORER: COMMON OR GENERAL…Full textLABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE; PIPELAYER (EXCLUDES OPEN CUT CONSTRUCTION) | $30.35 | $17.90 | $48.25 | Agreement |
| PAIN1474-003 · Painters and Allied Trades agreement, June 1, 2010 | ||||
| PAINTER: SPRAY | $24.79 | $12.02 | $36.81 | Agreement |
| PAINTER: BRUSH & ROLLER | $23.79 | $12.02 | $35.81 | Agreement |
| PLAS0514-005 · Plasterers and Cement Masons agreement, June 1, 2023 | ||||
| CEMENT MASON/CONCRETE FINISHER | $32.23 | $22.11 | $54.34 | Agreement |
| PLUM0098-005 · Plumbers and Pipefitters agreement, June 1, 2019 | ||||
| PLUMBER | $35.77 | $35.13 | $70.90 | Agreement |
| PLUM0636-002 · Plumbers and Pipefitters agreement, June 5, 2017 | ||||
| PIPEFITTER | $40.41 | $29.35 | $69.76 | Agreement |
| SUMI2010-070 · Survey of contractors in MI, November 9, 2010 | ||||
| TRUCK DRIVER: OFF THE ROAD TRUCK | $20.82 | $3.69 | $24.51 | Survey |
| TEAM0007-008 · Teamsters agreement, June 1, 2025 | ||||
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | $33.55 | $0.75 | $34.30 | Agreement |
| TRUCK DRIVER: DUMP TRUCK, 8 CU. YDS. AND OVER | $33.40 | $0.75 | $34.15 | Agreement |
| TRUCK DRIVER: DUMP TRUCK UNDER 8 CU. YDS.; TRACTOR HAUL TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | $33.30 | $0.75 | $34.05 | Agreement |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on MI20260072?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator