Prevailing wage rates · Michigan · Wage determination
Prevailing wage rates: Montcalm County, Michigan
Heavy construction · MI20260040 modification 1, published May 18, 2026
The short answer
This sheet sets 26 classifications for heavy work in Montcalm County, Michigan. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $12.63 an hour (laborer: landscape) to $74.23 (operator: power equipment: excludes underground construction group 1). Your contract may lock an earlier modification.
Scope
Heavy, Includes Water, Sewer Lines and Excavation (Excludes Hazardous Waste Removal; Coal, Oil, Gas, Duct and other similar Pipeline Construction)
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| CARP0100-008 · Carpenters agreement, June 1, 2025 | ||||
| CARPENTER (FORM WORK ONLY) | $31.50 | $21.15 | $52.65 | Agreement |
| ELEC0275-001 · Electrical Workers (IBEW) agreement, June 1, 2024 | ||||
| ELECTRICIAN | $36.52 | $25.15 | $61.67 | Agreement |
| ENGI0325-021 · Operating Engineers agreement, September 1, 2025 | ||||
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4…Full textPOWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR | $39.95 | $25.25 | $65.20 | Agreement |
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3…Full textPOWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | $40.52 | $25.25 | $65.77 | Agreement |
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2…Full textPOWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | $41.25 | $25.25 | $66.50 | Agreement |
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1…Full textPOWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, SCRAPER, LOADER, TRENCHER (OVER 8 FT. DIGGING CAPACITY) | $45.98 | $25.25 | $71.23 | Agreement |
| ENGI0326-020 · Operating Engineers agreement, June 1, 2025 | ||||
| OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 5 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $32.98 | $25.25 | $58.23 | Agreement |
OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 4…Full textOPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 4 BOOM TRUCK (NON-SWINGING) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.32 | $25.25 | $66.57 | Agreement |
OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 3…Full textOPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 3 BACKHOE/EXCAVATOR; BULLDOZER; COMPACTOR; CRANE; SCRAPER; LOADER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $44.00 | $25.25 | $69.25 | Agreement |
OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 1…Full textOPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $48.98 | $25.25 | $74.23 | Agreement |
OPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 2…Full textOPERATOR: POWER EQUIPMENT: EXCLUDES UNDERGROUND CONSTRUCTION GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $45.68 | $25.25 | $70.93 | Agreement |
| IRON0025-011 · Ironworkers agreement, June 1, 2025 | ||||
| IRONWORKER: STRUCTURAL | $36.55 | $34.04 | $70.59 | Agreement |
| IRONWORKER: REINFORCING | $36.55 | $34.04 | $70.59 | Agreement |
| LABO0334-003 · Laborers agreement, September 1, 2022 | ||||
| LABORER ((4) GRADE CHECKER) | $22.73 | $12.95 | $35.68 | Agreement |
| PLAS0016-017 · Plasterers and Cement Masons agreement, April 1, 2014 | ||||
| CEMENT MASON/CONCRETE FINISHER | $21.15 | $12.78 | $33.93 | Agreement |
| PLUM0174-008 · Plumbers and Pipefitters agreement, July 1, 2022 | ||||
| PLUMBER/PIPEFITTER | $39.89 | $23.82 | $63.71 | Agreement |
| SUMI2010-038 · Survey of contractors in MI, November 9, 2010 | ||||
| TRUCK DRIVER: DUMP TRUCK | $14.06 | $1.25 | $15.31 | Survey |
| OPERATOR: ROLLER | $13.74 | $7.93 | $21.67 | Survey |
| OPERATOR: GRADER/BLADE | $15.50 | $3.62 | $19.12 | Survey |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $12.98 | $6.12 | $19.10 | Survey |
| LABORER: PIPELAYER | $15.28 | $3.99 | $19.27 | Survey |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $15.97 | $3.51 | $19.48 | Survey |
| LABORER: LANDSCAPE | $10.89 | $1.74 | $12.63 | Survey |
| LABORER: COMMON OR GENERAL | $11.15 | $4.31 | $15.46 | Survey |
| CARPENTER, EXCLUDES FORM WORK | $23.97 | $6.29 | $30.26 | Survey |
| TEAM0007-010 · Teamsters agreement, June 1, 2025 | ||||
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | $33.55 | $0.75 | $34.30 | Agreement |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on MI20260040?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator