Prevailing wage rates · Massachusetts · Wage determination
Prevailing wage rates: Berkshire, Franklin, Hampden and Hampshire Counties, Massachusetts
Building construction · MA20260003 modification 1, published May 18, 2026
The short answer
This sheet sets 68 classifications for building work in Berkshire, Franklin, Hampden and Hampshire Counties, Massachusetts. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $54.28 an hour (marble finisher) to $105.61 (sprinkler fitter a.). Your contract may lock an earlier modification.
Rates by classification
Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.
| Classification | Basic rate | Fringe | Total | Source |
|---|---|---|---|---|
| ASBE0006-011 · Asbestos Workers and Heat & Frost Insulators agreement, September 1, 2024 | ||||
INSULATOR/ASBESTOS WORKER…Full textINSULATOR/ASBESTOS WORKER (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS) | $44.36 | $36.63 | $80.99 | Agreement |
| BOIL0029-001 · Boilermakers agreement, January 1, 2025 | ||||
| BOILERMAKER | $50.62 | $28.82 | $79.44 | Agreement |
| BRMA0001-001 · Bricklayers agreement, August 1, 2023 | ||||
BRICKLAYER: BRICKLAYERS…Full textBRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD/PITTSFIELD CHAPTER FRANKLIN, HAMPDEN, AND HAMPSHIRE COUNTIES) | $50.81 | $32.27 | $83.08 | Agreement |
| BRMA0001-003 · Bricklayers agreement, August 1, 2023 | ||||
BRICKLAYER: BRICKLAYERS…Full textBRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD/PITTSFIELD BERKSHIRE) | $50.81 | $32.27 | $83.08 | Agreement |
| CARP0056-014 · Carpenters agreement, August 1, 2024 | ||||
| PILEDRIVERMAN | $55.79 | $35.47 | $91.26 | Agreement |
| CARP0336-006 · Carpenters agreement, September 1, 2025 | ||||
| CARPENTER (FRANKLIN COUNTY (ERVING, ORANGE, NORTH ORANGE AND WARWICK)) | $43.33 | $27.82 | $71.15 | Agreement |
| CARP0336-009 · Carpenters agreement, September 1, 2025 | ||||
| CARPENTER/LATHER/DRYWALL APPLICATOR (HAMPDEN; HAMPSHIRE AND FRANKLIN (REMAINDER)) | $43.33 | $27.82 | $71.15 | Agreement |
| CARP0336-013 · Carpenters agreement, September 1, 2025 | ||||
| CARPENTER (BERKSHIRE COUNTY) | $43.33 | $27.82 | $71.15 | Agreement |
| CARP1121-004 · Carpenters agreement, April 21, 2025 | ||||
| MILLWRIGHT | $43.42 | $33.00 | $76.42 | Agreement |
| CARP2168-003 · Carpenters agreement, September 1, 2025 | ||||
| FLOOR LAYER: CARPET | $43.23 | $27.79 | $71.02 | Agreement |
| ELEC0007-002 · Electrical Workers (IBEW) agreement, June 29, 2025 | ||||
| ELECTRICIAN (HAMPDEN (EXCEPT CHESTER & HOLYOKE); HAMPSHIRE (BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 | Agreement |
| ELEC0007-003 · Electrical Workers (IBEW) agreement, June 29, 2025 | ||||
ELECTRICIAN (BERKSHIRE…Full textELECTRICIAN (BERKSHIRE; FRANKLIN; HAMPDEN (CHESTER, HOLYOKE); HAMPSHIRE (EXCEPT BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 | Agreement |
| ELEC0007-006 · Electrical Workers (IBEW) agreement, June 29, 2025 | ||||
| TELEDATA SYSTEM INSTALLER | $52.16 | $29.56 | $81.72 | Agreement |
| ELEC0042-003 · Electrical Workers (IBEW) agreement, September 3, 2017 | ||||
| LINE CONSTRUCTION: MATERIAL MAN, TRACTOR TRAILER DRIVER, EQUIPMENT OPERATOR | $39.92 | $21.80 | $61.72 | Agreement |
| LINE CONSTRUCTION: LINEMAN, CABLE SPLICER AND DYNAMITE MAN | $46.96 | $25.05 | $72.01 | Agreement |
| LINE CONSTRUCTION: HEAVY EQUIPMENT OPERATOR | $42.26 | $22.56 | $64.82 | Agreement |
| ELEV0041-001 · Elevator Constructors agreement, January 1, 2025 | ||||
| ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | $66.41 | $38.44 | $104.85 | Agreement |
| ENGI0098-001 · Operating Engineers agreement, June 1, 2024 | ||||
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 15…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 15 BOOM LENGTHS OVER 350 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $50.73 | $30.58 | $81.31 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 14…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 14 BOOM LENGTHS OVER 300 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $49.23 | $30.58 | $79.81 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 13…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 13 BOOM LENGTHS OVER 250 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $48.23 | $30.58 | $78.81 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 12…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 12 BOOM LENGTHS OVER 200 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.23 | $30.58 | $77.81 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 11…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 11 BOOM LENGTHS OVER 150 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $45.73 | $30.58 | $76.31 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 10…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 10 MASTER MECHANIC HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $44.73 | $30.58 | $75.31 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 9…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 9 OILER HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $42.72 | $30.58 | $73.30 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 8…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 8 TRUCK CRANE CREWS HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $42.41 | $30.58 | $72.99 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 7…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 7 COMPRESSORS UP TO 315 CU FT; SMALL MIXERS WITH SKIP; PUMPS UP TO 4 INCHES; POWER HEATERS; OILER; A-FRAME TRUCKS; FORKLIFTS-UP TO 7 FT. LIFT AND UP TO 3 TON CAPACITY; HYDRO BROOM; STUD WELDER. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $52.73 | $30.58 | $83.31 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 6…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 6 COMPRESSOR (ONE OR TWO) 315 CU FT TO 900 CU FT; PUMPS 4 INCHES TO 16 INCHES (TOTAL DISCHARGE). HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $34.41 | $30.58 | $64.99 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 5…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 5 HOISTS; CONVEYORS; POWER PAVEMENT BREAKERS; SELF-POWERED CONCRETE PAVEMENT FINISHING HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAYMACHINES; TWO BAG MIXERS WITH SKIP; MCCARTHY AND SIMILAR DRILLS; BATCH PLANTS (NOT SELF LOADING); BULK CEMENT PLANTS; SELF-PROPELLED MATERIAL SPREADERS; THREE OR MORE 10 KW LIGHT PLANTS; 30 KW OR MORE GENERATORS; POWER BROOM | $36.35 | $30.58 | $66.93 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 4…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 4 ASPHALT ROLLERS; SELF-POWERED ROLLERS AND COMPACTORS; TRACTOR WITHOUT BLADE DRAWING SHEEPSFOOT ROLLER; RUBBER TIRE ROLLER; VIBRATORY ROLLER OR OTHER TYPE OF COMPACTORS INCLUDING MACHINES FOR PULVERIZING AND AERATING SOIL; YORK RAKE. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $37.47 | $30.58 | $68.05 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 3…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 3 COMBINATION BACKHOE/LOADER UP TO 3/4 CU YD; SCRAPERS UP TO 21 CU YD (STRUCK LOAD, SELF PROPELLED OR TRACTOR DRAWN); TIREMAN; FRONT END LOADERS UP TO 4 YDS; WELL DRILLERS; ENGINEER OR FIREMAN ON HIGH PRESSURE BOILER; SELF-LOADING BATCH PLANT; WELL POINT OPERATORS ELECTRIC PUMPS USED IN WELL POINT SYSTEM; PUMPS, 16 INCHES AND OVER (TOTAL DISCHARGE); COMPRESSOR, ONE OR TWO 900 CU FT AND OVER; POWERED GREASE TRUCK; TUNNEL LOCOMOTIVES AND DINGYS; GROUT PUMPS; HYDRAULIC JACKS; BOOM TRUCK; HYDRAULIC CRANES- UP TO 10 TON. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $40.70 | $30.58 | $71.28 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 2…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 2 ROTARY DRILL WITH MOUNTED COMPRESSOR; COMPRESSOR HOUSE (3 TO 6 COMPRESSORS); ROCK AND EARTH BORING MACHINES (EXCLUDING MCCARTHY AND SIMILAR DRILLS); FRONT END LOADERS 4 CU YDS TO 5 1/2 CU YDS); FORKLIFTS-7 FT LIFT AND OVER 3 TON CAPACITY; SCRAPER 21 YDS AND OVER (STRUCK LOAD); SONIC HAMMER CONSOLE; RECLAIMERS ROAD PLANER/MILLING MACHINE; CAL TRACKS; BALLAST REGULATORS; RAIL ANCHOR MACHINES; SWITCH TAMPERS, ASPHALT PAVERS; MECHANIC; WELDER AND TRANSFER MACHINE. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $40.92 | $30.58 | $71.50 | Agreement |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 1…Full textPOWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 1 SHOVELS; CRAWLERS AND TRUCK CRANES INCLUDING ALL TOWER; SELF-PROPELLED HYDRAULIC CRANES 10 TONS AND OVER; DRAGLINES; CLAM SHELLS; CABLEWAYS; SHAFT HOISTS; MUCKING MACHINES DERRICKS; BACKHOES; BULLDOZERS; GRADALLS; ELEVATING GRADERS; PILE DRIVERS; CONCRETE PAVERS; TRENCHING MACHINES; FRONT END LOADERS- 5 1/2 CU YDS AND OVER; DUAL DRUM PAVER; AUTOMATIC GRADER-EXCAVATOR(C.M.I. OR EQUAL); SCRAPERS TOWING PAN OR WAGON; TANDEM DOZERS OR PUSH CATS(2 UNITS IN TANDEM); SHOTCRETE MACHINE; TUNNEL BORING MACHINE; COMBINATION BACKHOE/LOADER 3/4 CU YD HOE OR OVER; JET ENGINE DRYER; TREE SHREDDER; POST HOLE DIGGER; POST HOLE HAMMER; POST EXTRACTOR; TRUCK MOUNTED CONCRETE PUMP WITH BOOM; ROTO-MILL; GRADER; HORIZONTAL DRILLING MACHINE; JOHN HENRY ROCK DRILL AND SIMILAR EQUIPMENT. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE: FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.23 | $30.58 | $71.81 | Agreement |
| IRON0007-014 · Ironworkers agreement, September 16, 2025 | ||||
IRONWORKER (BERKSHIRE…Full textIRONWORKER (BERKSHIRE (BECKET, EAST OTIS, HINSDALE, MONTEREY, NEW MARLBORO, NORTH OTIS, OTIS, PERU, SANDISFIELD, SAVOY, SHEFFIELD, WASHINGTON, WINDSOR); FRANKLIN; HAMPDEN; HAMPSHIRE) | $41.89 | $33.90 | $75.79 | Agreement |
| IRON0012-003 · Ironworkers agreement, July 1, 2025 | ||||
| IRONWORKER (BERKSHIRE (LEE)) | $40.75 | $31.91 | $72.66 | Agreement |
| IRON0012-004 · Ironworkers agreement, July 1, 2025 | ||||
IRONWORKERS: STRUCTURAL…Full textIRONWORKERS: STRUCTURAL, ORNAMENTAL, REINFORCING, FENCE ERECTOR, MACHINERY MOVER, RIGGER, RODMAN, STONE DERRICKMAN (BERKSHIRE (REMAINDER OF COUNTY)) | $40.75 | $31.91 | $72.66 | Agreement |
| IRONWORKERS: SHEETER (BERKSHIRE (REMAINDER OF COUNTY)) | $41.00 | $31.91 | $72.91 | Agreement |
| LABO0022-002 · Laborers agreement, December 1, 2024 | ||||
LABORERS: GROUP 6…Full textLABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (FRANKLIN (ORANGE, WARWICK)) | $40.95 | $29.70 | $70.65 | Agreement |
| LABORERS: GROUP 5 PRECAST FLOOR AND ROOF, PLANK ERECTOR (FRANKLIN (ORANGE, WARWICK)) | $39.70 | $29.70 | $69.40 | Agreement |
| LABORERS: GROUP 4 BLASTER; POWDERMAN (FRANKLIN (ORANGE, WARWICK)) | $39.95 | $29.70 | $69.65 | Agreement |
LABORERS: GROUP 3…Full textLABORERS: GROUP 3 AIR TRACK OPERATOR; BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (FRANKLIN (ORANGE, WARWICK)) | $39.70 | $29.70 | $69.40 | Agreement |
LABORERS: GROUP 2…Full textLABORERS: GROUP 2 ASPHALT RAKER; FENCE AND GUARD RAIL ERECTOR; LASER BEAM OPERATOR; MASON TENMDER; PIPELAYER; PNEUMATIC DRILL OPERATOR; PNEUMATIC TOOL OPERATOR; WAGON DRILL OPERATORM JACKHAMMER OPERATOR, PAVEMENT BREAKER, CARBIDE CORE DRILLING MACHINE, CHAIN SAW OPERATOR, BARCO TYPE JUMPING TAMPERS, CONCRETE PUMP, MOTORIZED MORTAR MINER, RIDE-ON MOTORIZED BUGGY (FRANKLIN (ORANGE, WARWICK)) | $39.20 | $29.70 | $68.90 | Agreement |
LABORERS: GROUP 1…Full textLABORERS: GROUP 1 LABORERS; CARPENTER TENDERS; CEMENT FINISHER TENDERS, PLASTERER TENDERS (FRANKLIN (ORANGE, WARWICK)) | $38.95 | $29.70 | $68.65 | Agreement |
| LABO0473-001 · Laborers agreement, December 1, 2024 | ||||
LABORERS: (BERKSHIRE COUNTY…Full textLABORERS: (BERKSHIRE COUNTY, FRANKLIN COUNTY, (THE TOWNS OF ASHFIELD, BUCKLAND, CHARLEMONT, HAWLEY, HEATH, AND ROWE ONLY) HAMPSHIRE COUNTY (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $31.54 | $25.63 | $57.17 | Agreement |
| LABO0596-001 · Laborers agreement, December 2, 2024 | ||||
LABORERS: GROUP 5…Full textLABORERS: GROUP 5 POWDERMAN AND BLASTER (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $36.00 | $28.87 | $64.87 | Agreement |
LABORERS: GROUP 4…Full textLABORERS: GROUP 4 AIR TRACK OPERATORS, BLOCK PAVERS, RAMMERS AND CURB SETTERS, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $35.75 | $28.87 | $64.62 | Agreement |
LABORERS: GROUP 3…Full textLABORERS: GROUP 3 PRECAST FLOOR AND ROOF PLANK ERECTORS, SIGN ERECTORS, ASBESTOS REMOVAL LABORERS, HAZ-MAT LABORERS (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $35.75 | $28.87 | $64.62 | Agreement |
LABORERS: GROUP 2…Full textLABORERS: GROUP 2 ASPHALT RAKERS, CARBIDE CORE DRILLER OPERATORS, CHAIN SAW OPERATORS, PIPELAYERS, JACKHAMMER AND PAVING BREAKER OPERATORS, BARCO TYPE JUMPING TAMPERS, LASER BEAM OPERATORS, CONCRETE PUMP OPERATORS, MASON TENDERS, MOTORIZED MORTAR MIXERS, RIDE-ON MOTORIZED BUGGY OPERATORS, WAGON DRILL OPERATORS (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $35.25 | $28.87 | $64.12 | Agreement |
LABORERS: GROUP 1…Full textLABORERS: GROUP 1 LABORERS, CARPENTER TENDERS, WRECKING LABORERS (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $35.00 | $28.87 | $63.87 | Agreement |
| MARB0097-001 · MARB, March 1, 2012 | ||||
| MARBLE FINISHER | $28.43 | $25.85 | $54.28 | MARB |
| PAIN0011-008 · Painters and Allied Trades agreement, June 1, 2025 | ||||
| GLAZIER FOOTNOTE: A. PAID HOLIDAY: LABOR DAY (PROVIDED EMPLOYEE HAS WORKED ANY PART OF THE WEEK PRIOR TO LABOR DAY AND ANY PART OF THE WEEK AFTER LABOR DAY | $43.13 | $21.00 | $64.13 | Agreement |
| PAIN0035-007 · Painters and Allied Trades agreement, July 1, 2024 | ||||
| PAINTER: SPRAY, SANDBLAST (NEW CONSTRUCTION) | $39.48 | $31.95 | $71.43 | Agreement |
| PAINTER: BRUSH, TAPER (NEW CONSTRUCTION) | $38.08 | $31.95 | $70.03 | Agreement |
| PAINTER REPAINT: SPRAY, SANDBLAST | $36.80 | $31.95 | $68.75 | Agreement |
| PAINTER REPAINT: BRUSH, TAPER | $35.40 | $31.95 | $67.35 | Agreement |
| PLUM0004-003 · Plumbers and Pipefitters agreement, September 1, 2025 | ||||
| PLUMBER AND STEAMFITTER (FRANKLIN (ORANGE)) | $55.00 | $31.57 | $86.57 | Agreement |
| PLUM0104-004 · Plumbers and Pipefitters agreement, September 17, 2025 | ||||
PLUMBERS AND PIPEFITTERS…Full textPLUMBERS AND PIPEFITTERS (BERKSHIRE (BECKET, OTIS, SANDISFIELD); FRANKLIN (EXCEPT MONROE, ROWE, AND THE WESTERN PART OF CHARLEMONT); HAMPDEN; HAMPSHIRE) | $52.26 | $31.05 | $83.31 | Agreement |
| PLUM0104-009 · Plumbers and Pipefitters agreement, September 17, 2025 | ||||
PLUMBER AND STEAMFITTER…Full textPLUMBER AND STEAMFITTER (BERKSHIRE (EXCEPT OTIS, BECKET, SANDISFIELD); FRANKLIN (MONROE, ROWE AND THE WESTERN PART OF CHARLEMONT)) | $52.26 | $31.05 | $83.31 | Agreement |
| ROOF0248-001 · Roofers agreement, July 16, 2025 | ||||
ROOFERS: PITCH,SLATE…Full textROOFERS: PITCH,SLATE, TILE AND PRECAST CONCRETE ALL TEAR-OFF AND/OR REMOVAL (OF ANY TYPES OF ROOFING), AND ALL SPUDDING, SWEEPING, VACUUMING AND/OR CLEANUP OF ANY AND ALL AREAS OF ANY TYPE WHERE A ROOF IS TO BE RELAID | $42.48 | $30.14 | $72.62 | Agreement |
ROOFERS: COMPOSITION ROOFERS & DAMP WATERPROOFERS ALL TEAR-OFF AND/OR REMOVAL…Full textROOFERS: COMPOSITION ROOFERS & DAMP WATERPROOFERS ALL TEAR-OFF AND/OR REMOVAL (OF ANY TYPES OF ROOFING), AND ALL SPUDDING, SWEEPING, VACUUMING AND/OR CLEANUP OF ANY AND ALL AREAS OF ANY TYPE WHERE A ROOF IS TO BE RELAID | $42.48 | $30.14 | $72.62 | Agreement |
| SFMA0550-003 · SFMA, October 1, 2025 | ||||
| SPRINKLER FITTER A. PAID HOLIDAYS: MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS BEEN IN THE EMPLOYMENT OF A CONTRACTOR 20 WORKING DAYS PRIOR TO ANY SUCH PAID HOLIDAYS | $64.85 | $40.76 | $105.61 | SFMA |
| SHEE0063-001 · Sheet Metal Workers agreement, July 1, 2025 | ||||
| SHEET METAL WORKER | $43.48 | $36.46 | $79.94 | Agreement |
| TEAM0379-001 · Teamsters agreement, June 1, 2025 | ||||
TRUCK DRIVERS: GROUP 7…Full textTRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT (DOUBLE HOOKUP) POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.82 | $37.35 | $79.17 | Agreement |
TRUCK DRIVERS: GROUP 6…Full textTRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.53 | $37.35 | $78.88 | Agreement |
TRUCK DRIVERS: GROUP 5…Full textTRUCK DRIVERS: GROUP 5 SPECIALIZED EARTH MOVING EQUIPMENT UNDER 35 TONS OTHER THAN CONVENTIONAL TYPE TRUCKS; LOW BED; VACHUAL; MECHANICS, PAVING RESTORATION EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.24 | $37.35 | $78.59 | Agreement |
TRUCK DRIVERS: GROUP 4…Full textTRUCK DRIVERS: GROUP 4 FOUR AND FIVE AXLE EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.14 | $37.35 | $78.49 | Agreement |
TRUCK DRIVERS: GROUP 3…Full textTRUCK DRIVERS: GROUP 3 THREE AXLE EQUIPMENT AND TIREMAN POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.02 | $37.35 | $78.37 | Agreement |
TRUCK DRIVERS: GROUP 2…Full textTRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $40.95 | $37.35 | $78.30 | Agreement |
TRUCK DRIVERS: GROUP 1…Full textTRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $40.78 | $37.35 | $78.13 | Agreement |
Modification history
| Modification 0 | January 2, 2026 |
| Modification 1 | May 18, 2026 (current) |
Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).
Questions people ask
- Which rate do I pay on MA20260003?
- The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
- My trade is not on this sheet. What do I do?
- Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
- Does modification 1 apply to my contract?
- Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.
How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator