Prevailing wage rates: Ascension, Calcasieu, Cameron and 12 more counties, Louisiana

Highway construction · LA20260013 modification 1, published May 18, 2026

The short answer

This sheet sets 18 classifications for highway work in Ascension, Calcasieu, Cameron and 12 more counties, Louisiana. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $12.69 an hour (truck drivers: dump truck) to $33.45 (mechanic). Your contract may lock an earlier modification.

Rates by classification

Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
ENGI0406-001 · Operating Engineers agreement, October 28, 2010
MECHANIC$25.40$8.05$33.45Agreement
LABO0099-003 · Laborers agreement, July 1, 2006
LABORER: COMMON OR GENERAL (CALCASIEU AND CAMERON COUNTIES)$12.79$1.73$14.52Agreement
LABO0099-010 · Laborers agreement, January 1, 2005
LABORER: COMMON OR GENERAL (GRANT, LAFAYETTE, AND RAPIDES COUNTIES)$11.00$3.50$14.50Agreement
LABO0099-013 · Laborers agreement, September 1, 2005
LABORER: COMMON OR GENERAL…
Full text

LABORER: COMMON OR GENERAL (ASCENSION, EAST BATON ROUGE, EAST FELICIANA, IBERVILLE, LIVINGSTON, POINTE COUPEE, ST. HELENA, ST. MARTIN, WEST BATON ROUGE, AND WEST FELICIANA COUNTIES)

$15.00$2.77$17.77Agreement
SULA2011-005 · Survey of contractors in LA, August 17, 2011
TRUCK DRIVERS: WATER TRUCK$13.79$0.00$13.79Survey
TRUCK DRIVERS: DUMP TRUCK$12.69$0.00$12.69Survey
POWER EQUIPMENT OPERATORS: TRENCHER$14.38$0.00$14.38Survey
POWER EQUIPMENT OPERATORS: ROLLER (ASPHALT AND DIRT COMPACTION)$14.29$4.23$18.52Survey
POWER EQUIPMENT OPERATORS: MILLING MACHINE$15.38$2.14$17.52Survey
POWER EQUIPMENT OPERATORS: GRADER/BLADE$15.88$0.00$15.88Survey
POWER EQUIPMENT OPERATORS: CRANE$24.30$0.00$24.30Survey
POWER EQUIPMENT OPERATORS: BULLDOZER$16.40$0.00$16.40Survey
POWER EQUIPMENT OPERATORS: BROOM/SWEEPER$14.05$0.00$14.05Survey
POWER EQUIPMENT OPERATORS: BACKHOE/EXCAVATOR/TRACKHOE$16.13$0.00$16.13Survey
POWER EQUIPMENT OPERATORS: ASPHALT PAVER$17.20$4.97$22.17Survey
IRONWORKER, REINFORCING$17.49$0.00$17.49Survey
CEMENT MASON/CONCRETE FINISHER$20.03$4.24$24.27Survey
CARPENTER, INCLUDES FORM WORK$18.22$4.48$22.70Survey

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on LA20260013?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator