Prevailing wage rates: Tolland County, Connecticut

Building construction · CT20260025 modification 2, published May 18, 2026

The short answer

This sheet sets 33 classifications for building work in Tolland County, Connecticut. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $64.55 an hour (laborer: mason tender-cement/concrete) to $105.16 (elevator mechanic). Your contract may lock an earlier modification.

Rates by classification

Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
ASBE0033-002 · Asbestos Workers and Heat & Frost Insulators agreement, June 1, 2025
HEAT & FROST INSULATOR (INCLUDES DUCT, PIPE AND MECHANICAL SYSTEMS)$48.81$33.65$82.46Agreement
BRCT0001-001 · Bricklayers agreement, January 5, 2026
BRICKLAYER$45.56$36.94$82.50Agreement
BRCT0001-002 · Bricklayers agreement, January 5, 2026
BRICK POINTER/CAULKER/CLEANER$45.56$36.94$82.50Agreement
BRCT0001-005 · Bricklayers agreement, January 5, 2026
CEMENT MASON/CONCRETE FINISHER$45.56$36.94$82.50Agreement
CARP0326-024 · Carpenters agreement, May 5, 2025
FLOOR LAYER: CARPET ONLY$42.03$29.19$71.22Agreement
CARP0326-025 · Carpenters agreement, May 5, 2025
FLOOR LAYER: HARDWOOD FLOORS ONLY$42.03$29.19$71.22Agreement
CARP0326-027 · Carpenters agreement, May 5, 2025
CARPENTER (SCAFFOLD BUILDER)$42.03$29.19$71.22Agreement
CARP0326-028 · Carpenters agreement, May 5, 2025
CARPENTER (INCLUDES ACOUSTICAL CEILING INSTALLATION…
Full text

CARPENTER (INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION)

$42.03$29.19$71.22Agreement
CARP0326-032 · Carpenters agreement, May 5, 2025
CARPENTER (ACOUSTICAL CEILING INASTALLATION ONLY)$42.03$29.19$71.22Agreement
CARP0326-033 · Carpenters agreement, May 5, 2025
CARPENTER (INCLUDES FORM WORK ONLY)$42.03$29.19$71.22Agreement
ELEC0035-014 · Electrical Workers (IBEW) agreement, June 1, 2025
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING)$48.25$36.67$84.92Agreement
ELEV0091-002 · Elevator Constructors agreement, January 1, 2025
ELEVATOR MECHANIC

FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY

$66.72$38.44$105.16Agreement
ENGI0478-004 · Operating Engineers agreement, April 6, 2025
POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE

PAID HOLIDAYS: NEW YEAR'S DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS 3 DAYS DURING THE WEEK IN WHICH THE HOLIDAY FALLS, IF SCHEDULED, AND IF SCHEDULED, THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY

$51.92$29.80$81.72Agreement
ENGI0478-005 · Operating Engineers agreement, April 6, 2025
POWER EQUIPMENT OPERATOR, BULLDOZER: ROUGH GRADE DOZER

PAID HOLIDAYS: NEW YEAR'S DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS 3 DAYS DURING THE WEEK IN WHICH THE HOLIDAY FALLS, IF SCHEDULED, AND IF SCHEDULED, THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY

$50.22$29.80$80.02Agreement
POWER EQUIPMENT OPERATOR, BULLDOZER: FINEGRADE (SLOPES, SHAPING, LASER OR GPS, ETC.)

PAID HOLIDAYS: NEW YEAR'S DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS 3 DAYS DURING THE WEEK IN WHICH THE HOLIDAY FALLS, IF SCHEDULED, AND IF SCHEDULED, THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY

$51.92$29.80$81.72Agreement
ENGI0478-012 · Operating Engineers agreement, April 6, 2025
POWER EQUIPMENT OPERATOR: CRANE UNDER 100 TON RATED CAPACITY)

PAID HOLIDAYS: NEW YEAR'S DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS 3 DAYS DURING THE WEEK IN WHICH THE HOLIDAY FALLS, IF SCHEDULED, AND IF SCHEDULED, THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY

$56.79$29.80$86.59Agreement
ENGI0478-016 · Operating Engineers agreement, April 6, 2025
POWER EQUIPMENT OPERATOR: LOADER - 7 CUBIC YARDS OR OVER

PAID HOLIDAYS: NEW YEAR'S DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS 3 DAYS DURING THE WEEK IN WHICH THE HOLIDAY FALLS, IF SCHEDULED, AND IF SCHEDULED, THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY

$53.33$29.80$83.13Agreement
IRON0015-010 · Ironworkers agreement, June 2, 2025
IRONWORKER: REINFORCING, STRUCTURAL, ORNAMENTAL$45.25$43.62$88.87Agreement
LABO0230-001 · Laborers agreement, April 6, 2025
LABORER: MASON TENDER-CEMENT/CONCRETE$35.70$28.85$64.55Agreement
LABORER: COMMON OR GENERAL$35.70$28.85$64.55Agreement
PAIN0011-014 · Painters and Allied Trades agreement, June 1, 2025
GLAZIER$43.13$26.75$69.88Agreement
PAIN0011-021 · Painters and Allied Trades agreement, June 1, 2025
PAINTER: BRUSH AND ROLLER$39.57$26.75$66.32Agreement
PAIN0011-023 · Painters and Allied Trades agreement, June 1, 2025
DRYWALL FINISHER/TAPER$40.32$26.75$67.07Agreement
PLUM0777-001 · Plumbers and Pipefitters agreement, June 1, 2025
PLUMBER$50.58$35.85$86.43Agreement
PLUM0777-003 · Plumbers and Pipefitters agreement, June 1, 2025
PIPEFITTER$50.58$35.85$86.43Agreement
PLUM0777-004 · Plumbers and Pipefitters agreement, June 1, 2025
PLUMBER: HVAC PIPE INSTALLATION$50.58$35.85$86.43Agreement
ROOF0009-001 · Roofers agreement, January 1, 2026
ROOFER: SLATE AND TILE$45.65$23.53$69.18Agreement
ROOFER: COMPOSITION$45.15$23.53$68.68Agreement
SFCT0669-002 · SFCT, April 1, 2025
SPRINKLER FITTER$53.76$33.44$87.20SFCT
SHEE0040-001 · Sheet Metal Workers agreement, July 1, 2025
SHEET METAL WORKER (INCLUDING HVAC UNIT INSTALLATION)$44.70$44.50$89.20Agreement
SHEE0040-002 · Sheet Metal Workers agreement, July 1, 2025
SHEET METAL WORKER (METAL FLASHING AND HVAC DUCT INSTALLATION ONLY)$44.70$44.50$89.20Agreement
SHEE0040-008 · Sheet Metal Workers agreement, July 1, 2025
SHEET METAL WORKER (METAL ROOFS INSTALLATION)$44.70$44.50$89.20Agreement
TEAM0191-001 · Teamsters agreement, April 6, 2025
TRUCK DRIVER: DUMP TRUCK$36.39$32.68$69.07Agreement

Modification history

Modification 1January 23, 2026
Modification 2May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on CT20260025?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 2 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator