Prevailing wage rates: Franklin County, Arkansas

Highway construction · AR20260137 modification 1, published May 18, 2026

The short answer

This sheet sets 34 classifications for highway work in Franklin County, Arkansas. Each line is a basic hourly rate plus a fringe rate, and the sum is the minimum you must pay for that work, from $10.38 an hour (laborer: common or general) to $25.60 (operator: crane). Your contract may lock an earlier modification.

Rates by classification

Total is the basic rate plus the fringe. Source is the agreement or survey the rate came from; a marker means the group changed in this modification. A dagger (†) means the fringe carries a footnote or percentage the total does not include; read the group’s notes.

ClassificationBasic rateFringeTotalSource
SUAR2014-009 · Survey of contractors in AR, July 21, 2014
TRUCK DRIVER: SEMI/TRAILER TRUCK$10.75$0.00$10.75Survey
TRUCK DRIVER: WATER TRUCK$16.09$0.00$16.09Survey
TRUCK DRIVER: LOWBOY TRUCK$18.15$0.00$18.15Survey
TRUCK DRIVER: FLATBED TRUCK$12.75$0.00$12.75Survey
TRUCK DRIVER: DUMP TRUCK$13.40$0.00$13.40Survey
TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER$13.76$0.00$13.76Survey
TRAFFIC CONTROL: FLAGGER$10.50$0.00$10.50Survey
OPERATOR: TRANSFER MATERIAL MACHINE$15.06$0.00$15.06Survey
OPERATOR: SCREED$15.91$0.00$15.91Survey
OPERATOR: SCRAPER$17.78$0.00$17.78Survey
OPERATOR: ROLLER$14.00$0.00$14.00Survey
OPERATOR: POST DRIVER (GUARDRAIL/FENCES)$19.30$0.00$19.30Survey
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE)$17.90$0.00$17.90Survey
OPERATOR: OILER$18.38$0.00$18.38Survey
OPERATOR: MILLING MACHINE$18.75$0.00$18.75Survey
OPERATOR: MECHANIC$19.10$0.00$19.10Survey
OPERATOR: LOADER$14.86$0.00$14.86Survey
OPERATOR: GRADER/BLADE$22.68$0.00$22.68Survey
OPERATOR: CRANE$25.60$0.00$25.60Survey
OPERATOR: BULLDOZER$15.98$0.00$15.98Survey
OPERATOR: BROOM/SWEEPER$14.94$0.00$14.94Survey
OPERATOR: BOBCAT/SKID STEER/SKID LOADER$19.49$0.00$19.49Survey
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$20.77$0.00$20.77Survey
OPERATOR: ASPHALT PLANT$17.67$0.00$17.67Survey
LABORER: MASON TENDER - CEMENT/CONCRETE$11.51$0.00$11.51Survey
LABORER: LANDSCAPE$11.53$0.00$11.53Survey
LABORER: COMMON OR GENERAL$10.38$0.00$10.38Survey
LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR$13.23$0.00$13.23Survey
IRONWORKER, STRUCTURAL$19.58$0.00$19.58Survey
IRONWORKER, REINFORCING$15.36$0.00$15.36Survey
HIGHWAY/PARKING LOT STRIPING: OPERATOR (STRIPING MACHINE)$13.49$0.00$13.49Survey
CEMENT MASON/CONCRETE FINISHER$15.79$0.00$15.79Survey
CARPENTER, EXCLUDES FORM WORK$15.78$0.00$15.78Survey
CARPENTER (FORM WORK ONLY)$19.92$0.00$19.92Survey

Modification history

Modification 0January 2, 2026
Modification 1May 18, 2026 (current)

Published by the Wage and Hour Division; read from sam.gov. The sheet is checked for a newer modification each day. Contracts awarded since January 1, 2017 also carry Executive Order 13706 paid sick leave (one hour per 30 worked, up to 56 a year).

Questions people ask

Which rate do I pay on AR20260137?
The line for the classification of work actually performed: the basic rate plus the fringe. You may pay the fringe into benefit plans, as cash on every hour, or a mix. Overtime after 40 hours is 1.5 times the basic rate; fringe is paid on every hour and never multiplied.
My trade is not on this sheet. What do I do?
Do not borrow the nearest name. Ask the contracting agency for a conformance on Standard Form 1444 before the first week of that work, and note it as pending on the payroll.
Does modification 1 apply to my contract?
Only if it was in force when your contract was awarded (generally at bid opening). An earlier modification locked into the contract keeps applying, except on option years, added scope and indefinite-quantity contracts. The number and modification are on the first page of the exhibit in your contract.

How to read a wage determination · Paying the fringe in cash or through plans · Overtime on these rates · Fringe credit calculator